Improving the Accuracy of Early Cost Estimates for Federal Construction Projects (1990)

Chapter: 2 Factors Other Than Estimates That Contribute to Budget-Related Problems

Previous Chapter: 1 Introduction
Suggested Citation: "2 Factors Other Than Estimates That Contribute to Budget-Related Problems ." National Research Council. 1990. Improving the Accuracy of Early Cost Estimates for Federal Construction Projects. Washington, DC: The National Academies Press. doi: 10.17226/1693.
Page 7
Suggested Citation: "2 Factors Other Than Estimates That Contribute to Budget-Related Problems ." National Research Council. 1990. Improving the Accuracy of Early Cost Estimates for Federal Construction Projects. Washington, DC: The National Academies Press. doi: 10.17226/1693.
Page 8
Suggested Citation: "2 Factors Other Than Estimates That Contribute to Budget-Related Problems ." National Research Council. 1990. Improving the Accuracy of Early Cost Estimates for Federal Construction Projects. Washington, DC: The National Academies Press. doi: 10.17226/1693.
Page 9
Suggested Citation: "2 Factors Other Than Estimates That Contribute to Budget-Related Problems ." National Research Council. 1990. Improving the Accuracy of Early Cost Estimates for Federal Construction Projects. Washington, DC: The National Academies Press. doi: 10.17226/1693.
Page 10
Suggested Citation: "2 Factors Other Than Estimates That Contribute to Budget-Related Problems ." National Research Council. 1990. Improving the Accuracy of Early Cost Estimates for Federal Construction Projects. Washington, DC: The National Academies Press. doi: 10.17226/1693.
Page 11
Suggested Citation: "2 Factors Other Than Estimates That Contribute to Budget-Related Problems ." National Research Council. 1990. Improving the Accuracy of Early Cost Estimates for Federal Construction Projects. Washington, DC: The National Academies Press. doi: 10.17226/1693.
Page 12
Suggested Citation: "2 Factors Other Than Estimates That Contribute to Budget-Related Problems ." National Research Council. 1990. Improving the Accuracy of Early Cost Estimates for Federal Construction Projects. Washington, DC: The National Academies Press. doi: 10.17226/1693.
Page 13
Suggested Citation: "2 Factors Other Than Estimates That Contribute to Budget-Related Problems ." National Research Council. 1990. Improving the Accuracy of Early Cost Estimates for Federal Construction Projects. Washington, DC: The National Academies Press. doi: 10.17226/1693.
Page 14
Next Chapter: 3 Procedures Currently Used by Federal Agencies to Prepare Early Estimates
Subscribe to Email from the National Academies
Keep up with all of the activities, publications, and events by subscribing to free updates by email.