Systematic Approach for Determining Construction Contract Time: A Guidebook (2022)

Chapter: Chapter 5 - Relationship of Contract Time to Risk Management

Previous Chapter: Chapter 4 - CTD Guide for APDMs
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 86
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 87
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 88
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 89
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 90
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 91
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 92
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 93
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 94
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 95
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 96
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 97
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 98
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 99
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 100
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 101
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 102
Suggested Citation: "Chapter 5 - Relationship of Contract Time to Risk Management." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 103
Next Chapter: Chapter 6 - Post-Construction Contract Time Evaluation and Feedback Loop