Systematic Approach for Determining Construction Contract Time: A Guidebook (2022)

Chapter: Chapter 6 - Post-Construction Contract Time Evaluation and Feedback Loop

Previous Chapter: Chapter 5 - Relationship of Contract Time to Risk Management
Suggested Citation: "Chapter 6 - Post-Construction Contract Time Evaluation and Feedback Loop." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 104
Suggested Citation: "Chapter 6 - Post-Construction Contract Time Evaluation and Feedback Loop." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 105
Suggested Citation: "Chapter 6 - Post-Construction Contract Time Evaluation and Feedback Loop." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 106
Suggested Citation: "Chapter 6 - Post-Construction Contract Time Evaluation and Feedback Loop." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 107
Suggested Citation: "Chapter 6 - Post-Construction Contract Time Evaluation and Feedback Loop." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 108
Suggested Citation: "Chapter 6 - Post-Construction Contract Time Evaluation and Feedback Loop." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 109
Suggested Citation: "Chapter 6 - Post-Construction Contract Time Evaluation and Feedback Loop." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 110
Suggested Citation: "Chapter 6 - Post-Construction Contract Time Evaluation and Feedback Loop." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 111
Suggested Citation: "Chapter 6 - Post-Construction Contract Time Evaluation and Feedback Loop." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 112
Suggested Citation: "Chapter 6 - Post-Construction Contract Time Evaluation and Feedback Loop." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 113
Suggested Citation: "Chapter 6 - Post-Construction Contract Time Evaluation and Feedback Loop." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 114
Suggested Citation: "Chapter 6 - Post-Construction Contract Time Evaluation and Feedback Loop." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 115
Suggested Citation: "Chapter 6 - Post-Construction Contract Time Evaluation and Feedback Loop." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 116
Suggested Citation: "Chapter 6 - Post-Construction Contract Time Evaluation and Feedback Loop." National Academies of Sciences, Engineering, and Medicine. 2022. Systematic Approach for Determining Construction Contract Time: A Guidebook. Washington, DC: The National Academies Press. doi: 10.17226/26537.
Page 117
Next Chapter: Abbreviations