This chapter describes the results of a survey designed to capture the current state of collaboration between transit agencies and electric utilities that goes beyond the basic relationship of the agency as an electricity customer.
Table 3 shows the programs and policies identified by the author and the expert panel that an electric utility could potentially offer to support a transit agency’s deployment of BEBs. Survey respondents were asked whether any of these programs or policies were already in place, were not in place, or were under discussion. (Please note that the survey did not include the definitions in the interest of keeping the survey concise and minimizing the time to respond.)
In addition to asking about utility programs, the survey asked respondents to indicate
The survey also asked some open-ended questions, including whether respondents had any agreements or contracts with their electric utility to formalize their partnership and if they had included the utility in their Low-No grant application.
Finally, the survey asked for basic information on the size of the agency; the climate conditions of their service territory; and whether the service is urban, rural, or suburban. These elements help to ensure that the respondents represent a mix of demographic, regulatory, and climate conditions. These were then used when selecting the case examples, again to ensure that they would represent a range of conditions.
The complete survey is provided in Appendix B.
The survey was sent to 85 agencies and garnered 34 results, as shown in Table 4. The results represent a cross-section of agencies encompassing a range of geographic and climate conditions, fleet size, and BEB program maturity. There was less diversity in the service environment of the respondents, which tended to be in “urbanized” environments. The agencies in this survey
Table 3. Programs and policies that an electric utility may potentially offer to support a transit agency’s deployment of BEBs.
| Types of Utility Programs | Definition |
|---|---|
| Capital Funding/Financing | |
| Financing of charging equipment | The utility would directly fund, in part or whole, the EVSE installed by the agency in its facility. |
| Financing of construction | The utility would fund construction that occurs “behind the meter” such as conduit to the switchgear or trenching. |
| Financing of engineering/planning | The utility would offer, at no cost to the agency, engineering, and planning services for the infrastructure deployment. |
| Make-ready program | Full funding of the infrastructure up to the charger |
| Equipment leasing | Leasing the charging equipment |
| Charging as a service | The utility pays up-front costs for installation of charging equipment. The agency then pays these costs back through its monthly utility bill. This service may or may not include the operation and maintenance costs as well. The utility may retain ownership of the charger, or it may become the property of the agency once it is paid for through the monthly bills. |
| On-site energy storage/microgrid solution | Energy storage such as battery storage to provide emergency backup power or to even out power demands; microgrid is a distributed energy resource that enables the agency to generate electricity independently. |
| Operational Financial Support | |
| Special EV rate structure | Rates that support electric vehicles’ usage patterns and reduce demand charges, including lower EV rates or time-of-use rates |
| Managed charging/load management | Tools to manage the BEB load to optimize off-peak rates and lower costs |
| Advanced metering/net metering | Separate meter for the BEB fleet and/or metering that provides more granular usage data such as 15-minute interval data |
| Renewable electricity sourcing | Providing renewable energy subscription plans |
| Vehicle-to-grid (V2G) | Bidirectional charging that allows the utility to “buy back” energy from an EV battery |
| Planning Support and/or Grant Funding Support | |
| Help writing transition plan | Partnering with the agency in writing its ZEB Transition plan |
| Power capacity evaluation | Providing engineering and analysis services to assess power capacity needs for BEB fleet |
| Help with route design/planning | Providing engineering and analysis services to help determine BEB route deployment based on range and power availability |
| Help with charging strategy | Providing services to develop a charging strategy to manage energy use and incorporate BEB fleet into existing transit agency service and routes |
| Help with energy management strategy | Providing services to develop an energy management strategy |
Table 4. Survey results showing fleet size.
| Number of Survey Agencies | Percent of Survey Agencies | |
| Small: Fewer than 100 peak fixed-route buses operated in maximum service | 15 | 44.12% |
| Mid-size: 100 to 499 peak fixed-route buses operated in maximum service | 9 | 26.47% |
| Large: 500+ peak fixed-route buses operated in maximum service | 10 | 29.41% |
| Total | 34 |
represented a total of 540 BEBs in service. They also reported having a total of 2,019 BEBs on order, although half of that number is at a single agency.
Agencies were also asked specifically how many BEBs they had in service and how many were on order. Most agencies reported having five or fewer BEBs in service, as shown in Table 7.
Table 5. Survey results showing climate conditions.
| Climate Conditions | Number of Survey Agencies That Experience These Conditions | Percent of Survey Agencies That Experience These Conditions |
|---|---|---|
| High temperatures (over 90 degrees) | 29 | 85.29% |
| Cold temperatures (below 35 degrees) | 27 | 79.41% |
| Service has temperate climate | 8 | 23.53% |
| Hurricane conditions | 6 | 17.65% |
| Other notable climatic condition | 8 | 23.53% |
Note: Respondents could indicate more than one condition.
Table 6. Survey results showing status of BEB programs.
| Status of BEB Program | Percent | Number of Survey Agencies |
|---|---|---|
| Planning stage only | 14.71% | 5 |
| Pilot stage: 10 or fewer BEBs | 35.29% | 12 |
| Beyond pilot stage: 11 or more BEBs | 50.00% | 17 |
| Total | 34 | |
Table 7. Survey results showing how many BEBs were in service and how many were on order.
| Number of Battery Electric Buses in Service at Survey Agency | Percentage | Number of Survey Agencies |
|---|---|---|
| 0–5 | 29% | 10 |
| 6–10 | 20% | 7 |
| 11–15 | 14% | 5 |
| 16–20 | 14% | 4 |
| 21–35 | 14% | 5 |
| 50–81 | 9% | 3 |
| Total | 34 | |
Table 8. Types of charging equipment in use by survey agency.
| Charging Option | Percentage of All Agencies | Number of Agencies |
|---|---|---|
| DC chargers for depot charging | 79% | 27 |
| AC chargers for depot charging | 9% | 3 |
| Overhead charging on route | 29% | 10 |
| Overhead charging for depot charging | 9% | 3 |
| Wireless charging | 15% | 5 |
Note: Respondents could indicate more than one condition.
Most agencies who responded are using depot-based DC chargers: 27 of the 34 agencies surveyed have DC chargers for depot-based charging. Three agencies reported using AC chargers for depot-based charging, and three are using overhead charging in their depot.
Ten agencies have on-route charging. Although wireless charging is still a relatively new technology, five of the agencies who responded to this survey reported that they were deploying wireless charging for their BEB fleets.
A majority—28 or 80 percent—of respondents have a ZEB transition plan in place. Of the six respondents that do not, a few are the agencies still in the planning stage. However, several agencies that reported being in the planning stage do have ZEB transition plans. The broad adoption of ZEB transition plans is likely a combination of the requirements by states with mandates and the recent requirement by the FTA that agencies applying for zero-emission bus and facility funding under the Buses and Bus Facilities grant program must include a transition plan with their application.
Financing of charging equipment and engineering/planning services are the next most common services offered. Charging as a service and on-site energy storage/microgrids are uncommon,
Table 9. Capital funding or financing programs offered by agency utility.
| Yes | No | In Discussion | |
| Make-ready program | 9 | 19 | 6 |
| Financing of charging equipment | 8 | 20 | 6 |
| Financing of engineering/planning | 8 | 20 | 6 |
| Financing of construction | 6 | 19 | 9 |
| Equipment leasing | 5 | 27 | 2 |
| On-site energy storage/microgrid solution | 3 | 16 | 15 |
| Charging as a service | 2 | 26 | 6 |
Note: N = 34.
which aligns with their status as fairly new and somewhat untried solutions. However, the on-site storage/microgrid option had the highest number of responses that agencies were in discussions about. This result seems to align with the case example conversations in which some agencies said they were considering either backup power, a microgrid, or both.
Only one agency mentioned vehicle-to-grid as an established option, demonstrating that this technology solution remains fairly outside the mainstream for transit agencies. The FTA is investing in a project that will explore how to use electric bus batteries for a backup power source,
Table 10. Operational financial support offered by agency utility.
| Yes | No | In Discussion | |
| Special EV Rate structure | 10 | 9 | 15 |
| Renewable electricity sourcings | 10 | 16 | 8 |
| Managed charging/load management | 7 | 13 | 14 |
| Advanced metering/net metering | 7 | 16 | 11 |
| Vehicle-to-grid (V2G) | 1 | 28 | 5 |
Note: N = 34.
which would require utilizing a vehicle-to-grid technology option, but this is still in an early stage. In addition, TCRP is developing a guide under TCRP Project H-61, “Guide for Resilient Zero-Emission Transit Bus Fleets.”
Utilities are also offering help with charging strategies—which may be due to the utilities’ interest in managing new loads and preventing the need for costly power upgrades. Finally, Low-No Grant support is reasonably widely available; since 2022, Low-No grant applicants have been required to demonstrate engagement with the relevant energy provider—whether a utility or hydrogen provider.
Table 11. Planning or grant support from agency utility.
| Yes | No | In Discussion | |
| Power capacity evaluation | 18 | 10 | 6 |
| Support in Low-No Grant application | 13 | 20 | 1 |
| Help with charging strategy | 11 | 20 | 3 |
| Help writing transition plan | 8 | 26 | 0 |
| Help with energy management strategy | 8 | 17 | 9 |
| Help with route design/planning | 6 | 27 | 1 |
Note: N = 34.