
To achieve the objective of this research project, researchers were interested in using case studies to explore the economic impact of implementing BIM within an organization to deliver and maintain projects. Therefore, the unit of analysis for a case study selected for this effort was an individual project. However, to understand each case study project, it was also necessary to investigate the organization to gain insights into the longer-term costs and benefits associated with BIM implementation. A total of five projects were selected for investigation. To help normalize data for the ROI calculator, the research team selected four domestic projects and one international project.
Several selection criteria and characteristics were identified for evaluating potential case study projects and organizations. These criteria were developed to provide a diverse set of case studies that cover a breadth of BIM use cases. The criteria identified for consideration include the level of BIM adoption, data availability, ability to share case study information, geographic location diversification, size, complexity, and project delivery method.
The researchers also worked with a group of BIM subject matter experts to validate the data collected during the case studies.
The NYSDOT BIM journey dates to late 2009 when the agency began promoting the use of digital design data for layout, AMG operations, and global positioning systems (GPS) equipment for construction inspection (New York State Department of Transportation, n.d.). Since then, NYSDOT has launched several initiatives to advance the use of BIM, including but not limited to
Early pilot projects focused on creating accurate geometric models of roadways, utilities and drainage, and 3D solids for some bridge elements. The intended uses of the 3D models (BIM use cases) for these early pilots were to help construction activities with automation tools for stakeout, AMG, inspection verification, and quantity measurements. Later pilot projects tested the capture of 3D digital as-built models in real time that could be exported to GIS. In 2014, NYSDOT piloted the use of 4D models on the Kosciuszko Bridge, or K-Bridge, the first DB contract with BIM requirements. The Kew Gardens Interchange (KGI) improvement was the next large, complex project with BIM requirements, and it is the focus of this case study.
The next generation of pilot projects for NYSDOT to advance the use of BIM is model-based delivery, in which the 3D model becomes the legal contract document. The first-ever NYSDOT project in which the 3D model has been issued as the contract document is the Route 28 bridge over the Esopus Creek, which was awarded in Spring 2020 and is now under construction. The agency is currently documenting lessons learned on that project. A second project with a model as the legal contract document was planned for Spring 2021.
NYSDOT has funded several operational improvements for the KGI, which is a complex intersection connecting the Grand Central Parkway, Van Wyck Expressway, Jackie Robinson Parkway, and Union Turnpike. The KGI serves the region by carrying almost 600,000 vehicles daily. Improvements to the KGI have been broken down into a total of four phases, three of which have been completed and one of which is under construction. Each of the phases was advertised under a separate contract.
The first two phases of the project did not initially have any BIM requirements. However, during Phase 2 a 4D model requirement was added after a construction contract was awarded.
The BIM requirements for KGI Phase 3 included the delivery of a 3D model from the design as supplemental information. For the contractor, the contract required the development and maintenance of 4D and 5D animation models during the construction phase to compare the planned and completed work against a critical path method schedule. There was also a separate requirement to deliver an as-built 3D computer-aided design and drafting (CADD) record model.
To capture asset information, a GIS dataset for major asset classification—including bridges and bridge spans, abutments, pavement, overhead signs, noise barriers, retaining walls, guide rail and bridge rail, and large and small culverts—was created. This GIS model included data attributes tracked by NYSDOT in asset management databases.
The project team used BIM as part of the design process and to meet specific contract requirements. These BIM requirements are very similar to those requested in previous phases of the improvement and include the development, utilization, and maintenance of 3D CADD files to produce contract plans as well as 4D and 5D animation models.
In Phase 3 and Phase 4, requirements include level of development (LOD) specifications as shown in Table 3-1.
The requirements do not specify intended use cases for these models. The contract also requires the delivery of a combination of traditional as-builts (i.e., marked up plan sheets) and digital as-builts at the end of the project.
A 4D model was used to determine locations for crane placement and sequencing of construction activities, as well as a constructability review. The constructability review resulted in modifications to the design prior to the start of the project.
A 3D model was used for communicating design intent and served as the basis for the 4D model. The 4D model was used as a project management tool to understand the construction sequence of activities and schedule progress. The project management team held model management meetings on a quarterly basis. During these meetings, the team would compare the baseline and actual schedules and discuss courses of action. The 4D model was crucial for communication, coordination, and risk management review during construction. It is important to note that the contractor performing the work had experience with BIM. A 5D model (a 4D model tied to a loaded schedule) was also used to manage resources and determine payments.
While intended uses for the BIM deliverables are not specified in the requirements, the 3D models were highly beneficial to the design team, mostly for conflict analysis during design
Table 3-1. NYSDOT Kew Gardens LOD specifications.
| LOD | Model Content Requirements | Authorized Uses |
|---|---|---|
| 100 | Overall massing indicative of height, volume, location, and orientation. Massing will be 3D and may include other data. | Limited analysis, aggregate preliminary cost estimating, conceptual level scheduling and staging. |
| 200 | Elements are modeled as generalized assemblies or systems with approximate quantities, sizes, shapes, locations, and orientations. Attributes may be linked to model elements. | Preliminary analysis, accurate for cost estimating and scheduling. |
| 300 | Elements are modeled as specific assemblies and are accurate in quantity, size, shape, location, and orientation. Attributes may be linked to model elements as required by the engineer. | Construction documents, detailed QTOs, analysis and project management and controls. |
| 400 | Requirements per LOD 300, plus complete fabrication, assembly, and detailing information. | Model-based fabrication, actual cost-tracking look-aheads and virtual mock-ups. |
| 500 | Elements are modeled as constructed or as-built, field-verified accurate assemblies, quantities, dimensions, shapes, locations, and orientations. Major transportation asset class attributes are linked to modeled elements as required by the engineer. | Maintenance and operations asset management applications and future planning. |
development. The design team developed 3D models for roadway and bridge structures. The model was developed as part of the requirements for submitting a bid. The 3D model prepared as part of the proposal was leveraged by the project team as part of the final design.
The project team used the 3D model specifically for
Researchers interviewed agency representatives and the design team separately. The following section is a summary of the identified benefits and costs.
The following is a list of the top three challenges identified by the owner.
The following list includes some of the lessons learned by designers.
Utah Department of Transportation (UDOT) has been a leader in the implementation of BIM, starting the journey to adopting BIM in 2013. UDOT set an agency goal to develop processes and procedures to advertise projects with the model as the legal document. The agency was a leader in 3D-EM for construction in FHWA’s Every Day Counts initiative, round two, which started UDOT’s efforts to develop detailed 3D engineering models for construction (FHWA 2017). To do so, the agency developed an implementation plan to make models as legal documents for construction.
After exploring BIM efforts at Iowa DOT, UDOT developed a short-term implementation plan to make electronic files available for current projects, collected lessons learned, and initiated a series of workshops. During the initial workshop, the agency brought in approximately 60 to 70 experienced people to gain insight into the risk of not delivering models as legal documents. The following week, UDOT met with a separate group to identify the perceived risks regarding the adoption of hardware and software in the field. This eventually led to the adoption of a digital delivery process with model-based contracts.
UDOT’s initial implementation of the model-based contracting approach started with a small project in southern Utah that was relatively straightforward. The agency decided to use a Construction Manager/General Contractor (CMGC) delivery approach to manage the project’s primary risk by ensuring high-quality digital model development. UDOT had challenges with the earlier versions of 3D modeling software used to create the contractual models. Even when considering these challenges, due to BIM and the collaborative nature of the contract delivery method, the project duration was shortened by almost 25 percent for the initial pilot project.
After piloting the model-based contracting approach on a small CMGC project, UDOT pursued the process on projects with increasing levels of complexity, including an interstate project. At the same time, the agency performed two DBB projects with the model as the legal document. UDOT has continued to use this model-based delivery strategy over the last five years and expanded the approach for all project types. Currently, UDOT uses mobile devices to access needed information in the field, and no longer develops cut sheets for the projects. The first project performed without cut sheets was 90 South, a landmark for UDOT.
More recently, UDOT received a grant to focus on the development of a detailed GIS approach to collecting, managing, and using asset information for lifecycle asset management. This expansion into the coordination of final asset information will help UDOT improve its information management within the asset management phase.
UDOT has awarded 14 projects using modeling to create the legal document. Five of those were CMGC, and seven have been done using cut sheets. The following three projects were identified by UDOT as examples for review during this case study:
These case study projects are representative of the scope of work performed by UDOT. One project example is shown in Figure 3-1 and Figure 3-2. UDOT typically performs projects that
range from approximately $5 million to $50 million for DBB delivery. In rare instances, the agency might implement a project approaching $1 billion using CMGC or DB delivery.
As discussed earlier, UDOT defines the design model as the contractual design, thus requiring the construction to be consistent with the design model. Currently, UDOT has digital as-built requirements, but the agency is continuing to develop its ability to leverage information for asset management. Contractors are required to give UDOT an as-built model developed from the original design model, although there are remaining QC concerns regarding model updates. UDOT also has additional electronic submittal requirements, but the quality of these submissions remains inconsistent. UDOT continues to expand its efforts in these areas.
BIM Use Cases
This section provides information on the primary BIM uses that are frequently adopted or required on UDOT projects.
Researchers interviewed agency representatives and the design team separately. The following section is a summary of the identified benefits and costs.
The top challenges identified by UDOT and project teams were staff training and learning curves.
The following list includes some of the lessons learned that were shared by UDOT and project teams.
CDOT has been using 3D model-based design for roadways for a long time, and the agency is moving toward inclusion of 3D models from other disciplines, such as drainage and dry utilities. So far, CDOT has not officially implemented a BIM program. This is mainly due to
a lack of awareness on the multiple benefits of BIM. CDOT’s construction program typically includes maintenance-type projects, such as resurfacing and pavement repairs and bridge rehabilitation.
However, CDOT is in the process of implementing its collection of digital as-builts, a BIMspecific use case, as part of FHWA’s Every Day Counts initiative, round six. Digital as-builts are considered living records that are updated during construction to support effective lifecycle asset and performance management. Specifically, one of CDOT’s main motivations to implement digital as-builts is to mitigate utility strikes during construction. The CDOT digital as-built program is thus a prevention management strategy to improve safety and save costs associated with such incidents.
The department is in the process of building a statewide digital as-built database in which subsurface utility records will be hosted to make the data available to project teams in the future. CDOT anticipates that the initiative to establish, populate, and create a data management plan for digital as-builts will take approximately five years. It is CDOT’s desire to incorporate data from design and construction, including permitting and existing CAD and legacy utility information. CDOT’s vision for a mature subsurface utility system of record is to use the information to verify or supplement field surveys.
CDOT has funded several projects within the I-70 corridor to improve many intersections, as this is a critical corridor within the interstate system. It is a tourist travelway with many connectors and great importance to the community. The I-70G Edwards Spur Road Improvement, Phase II, is one of many I-70 corridor improvements. An atypical project for CDOT, Phase II of the I-70G Edwards Spur Road Improvement leveraged BIM for design, construction, and record modeling. This $21 million project was funded for improvements to the intersection of I-70G Spur Road and U.S. Highway 6, which included converting a signalized intersection to a two-lane roundabout; replacing one bridge and widening another; and installing pedestrian bridges, a drainage network system, lighting, signage, striping, and guardrail. The scope also included roadway widening, along with utility upgrades and relocation. The project was delivered through a CMGC delivery contract. The construction phase was completed in October 2020, approximately two years after initial groundbreaking. This project has recently been awarded the Colorado Department of Transportation Best Environmental Project.
CDOT does not currently have any agencywide BIM requirements that are adopted on every project. The design team used the 3D-design capabilities of the software to create corridors, surfaces, and solids of infrastructure objects to perform clash detection and prepare traditional 2D plan sets. CDOT is investigating the development of a set of core BIM requirements. To date, CDOT has invested in the development of a subsurface utility and drainage analysis library, containing standards for 3D objects for drainage and utilities, to be used in future projects.
BIM Use Cases
Although CDOT does not have extensive experience with BIM, the project team decided to use a 3D model-based design approach beyond the traditional roadway modeling as a risk mitigation strategy. The team modeled more than is typically done on a CDOT project to understand the location of utilities and coordinate elements of construction related to phasing. The team started with an existing condition model created from aerial lidar and ground survey data.
The existing condition model included traditional survey mapping deliverables, such as a digital terrain model, or 3D surface, and 2D geometry displaying the topographic features. There were no 3D reality models or 3D solids requirements for survey deliverables for this project.
The design team created 3D models for bridges and other structures (e.g., retaining walls), roadways, subsurface utilities, and drainage. During design, the only data property added to the 3D modeled objects was the utility owner information. The 3D model was helpful in automating the calculation of earthwork quantities needed for construction phasing of the roundabout, but due to the limitations of the technology being used (i.e., Bentley’s InRoads SS2), the team used traditional 2D methods to estimate other quantities.
The most beneficial use of BIM on this project was the ability to analyze the engineering design. Traffic modeling showed that the peak traffic time was during the school year. Because this was the main road to take kids to school, the project had to be completed over the summer (10 weeks). A major component was the ability to visualize the design alternatives between the original signalized intersection and the proposed two-lane roundabout. Visualizing traffic movements was helpful for the design team to understand how traffic could be least impacted during construction. Coupled with this analysis, the use of BIM becomes increasingly more valuable when it is used for coordinating work or activities.
The CMGC delivery approach gave the project team a unique opportunity to work with the contractor during the design of the project. The design team held working meetings with the contractor to get as much input as possible. During these project team meetings, the 3D model was used to identify the best construction phasing approach. The model was put on the screen and the designer walked through the 3D model to help the team make decisions in real time. It was through this process that the team was able to review various design alternatives to manage the construction phases for the roundabout area. The roundabout construction portion of the project was originally scheduled to take place in four phases. Through the use of BIM, the team was able to find design alternatives and traffic phasing that allowed the construction to be reduced to only two phases. This two-phase construction option helped to reduce time and project cost, providing a more positive traveling experience for the public.
A new effort within CDOT related to use cases is the approach the department took to record the as-built model of installed utilities. CDOT is in the process of implementing specific data collection requirements for digital as-built information for utilities and buffer zones. The department is piloting a new system in which data from the model will be pushed to a mobile application during construction. Because this effort to collect information for digital as-builts is new at CDOT, the project team was only able to collect a digital as-built for the waterline work. The data collected with GPS technology was imported into a legacy database instead of the new system.
This new digital, as-built system is based on GIS technology. Field staff were equipped with GPS equipment for field data collection. The new CDOT system, which the department calls PointMan, is a GIS database developed in-house for use by field construction personnel. Trimble Catalyst, a geospatial application that uses a GPS receiver connected to a mobile device, will be used to collect precise GPS positions for each asset location. CDOT will be connecting the information collected in the field from Trimble Catalyst to PointMan to obtain an accurate record of the asset locations.
The following list includes benefits and costs identified by the agency representatives and design team.
earthwork quantities on this project were relatively straightforward, and they did not have any issues with the contractor regarding those quantities.
In general, this project is considered to be very successful. BIM was used as a tool to communicate the design intent, find the best design solutions to ease congestion, and improve safety along the corridor. All project stakeholders were pleased with the results of the project, and CDOT received very positive feedback.
The top challenge identified by the owner and project team was learning curves. The biggest challenge for the design team was learning the process of model-based design. There was a lot of experimentation and new concepts to learn and put into practice. Once everyone achieved BIM proficiency, the team was able to realize more benefits.
One lesson learned that was shared by the owner and project team was staff training. Because BIM is new to CDOT, it would be beneficial to evaluate an overall training program that incorporates the use of technology (ORD software), effective processes and methods for BIM, and the value of using modeling standards.
Denver International Airport (DEN) in Colorado first opened in 1995, capturing attention with its unique structural design and use of technology. In 2019, DEN serviced 69 million passengers. As of 2021, DEN is the fifth-busiest airport and the largest in terms of area (53 square miles) in the United States (Ball 2015). DEN generates more than $33.5 billion in revenue for the region every year, making it Colorado’s largest revenue generator. Originally built to service 50 million passengers, the airport has increasingly been exceeding its original capacity and is in need of major expansion. There are many ongoing large projects, including expansion and enhancement of Concourses A-West, B-West, B-East, and C-East. Work also includes improvements to the existing infrastructure in each concourse. There are approximately 80–200 ongoing concurrent projects, including civil projects (Denver International Airport n.d.).
DEN was one of the early adopters of BIM among airport agencies. The BIM journey dates to August 2007, when the agency recognized the need to collect as much information about its assets as possible. The main objective of the DEN BIM program is data collection for improved decision-making, specifically for preventive maintenance of airport assets. DEN began implementing BIM in 2010 with its Hotel and Transit Center (HTC) project, the first of many expansion projects to increase airport capacity and operational service. While at first the BIM implementation was very project-driven, the agency has since mandated the use of BIM on all its projects, institutionalizing its use in all lifecycle phases (McCuen and Pittenger 2016). In addition, the airport authority has invested in an organizational BIM deployment strategy that enables the standardization of project deliverables by leveraging in-house resources to manage the overall program. BIM program staff provide technical support, assist with project prioritization, develop and conduct training, and assist project teams with the BIM process.
This case study focuses on the use of BIM during the HTC Program. This $720 million project included the construction of a commuter rail transit center and a 519-room hotel. DEN chose to pilot BIM on this project as a strategy to manage project risk. BIM has proven to be beneficial on large and complex capital improvement projects like the HTC Program. DEN hoped to realize the benefits promised by the BIM model-based approach, including improved collaboration between disciplines and avoidance of change orders. The project size, scope and complexity made it ideal for a BIM model-based approach.
The project used the CMGC delivery method. The design team collaborated with the contractors during the design phase to receive input and adjust the design.
Like many large institutional owners, DEN started its BIM implementation without the use of any BIM requirements. In the absence of DEN-provided BIM requirements, the design firm used its own standards to develop design models. In 2009, DEN hired a BIM consultant to help develop the agency’s first set of standard BIM requirements. BIM requirements for civil works were added to the standard requirements in 2016 and 2017. As of 2021, DEN has a complete set of standards for the use of BIM published in Design Standards Manual: Digital Facilities and Infrastructure. The manual provides minimum requirements for the use of BIM on all design, facilities, and infrastructure projects at DEN, including
BIM Use Cases
Several primary BIM uses are frequently adopted or required on DEN’s projects (see BIM Use Cases text box).
BIM was implemented in the design phase as much as possible within the project’s organizational and contractual structure. While the design model was used to create quantities and cost estimates, it was difficult for design teams to trust the calculations performed under their new approach. BIM was implemented for 3D coordination to improve design accuracy. This was accomplished through the strong leadership of key design champions. BIM information made creating sheets from models easier, although that was not the case at first. However, by the end of the project, all sheets were created from the design model. Although drawings were the contractually binding documents, models were still shared with constructors. Surprisingly, these contractors were more comfortable with BIM than DEN expected, although there was an inconsistency of tools used for developing 3D models between contractors and the design team. The design team used Revit while the contractors used 3D CAD tools for reviewing and developing 3D models.
The 3D models and the construction schedules were used to develop 4D models to visually track the progression of construction. BIM was also used as the primary source of data for FM during operations. DEN personnel were able to access asset information. Examples of information that was available through BIM data exchanges include date of purchase, cost, specific asset location, when it was installed, and the maintenance schedule.
The BIM program launched as part of the asset management program, although there was no coordinated program before 2012. The BIM model was used for “everything” related to an asset. The 3D models were used for maintaining critical systems—mechanical, electrical, plumbing, and security. The process focused mainly on developing a detailed model to inform all ongoing actions instead of creating visualizations. DEN’s priority in implementing BIM was to capture asset tracking. Then DEN pushed information into the GIS (a priority use) and information for downstream tenant projects (tenant improvements or renovation). For example, there are frequently tenants that will be performing projects within a space soon after projects are delivered, and the ability to provide a detailed model to the designers of these projects is very valuable. Design-intent models are continuously updated as new projects are performed.
Researchers interviewed agency representatives, and the following section is a summary of the identified benefits and costs.
carried throughout the whole lifecycle of the project, leading to reduced redundancy. In the HTC Program, DEN implemented BIM for daily asset management of the entire airport facility with hopes that the BIM system will make maintenance of the airport infrastructure more efficient, which in turn saves time and money and improves quality.
methods. For example, jobsite changes can impact mechanical performance when they are not entirely constructed as designed. As a result, rework is costly and time-consuming if a contractor installs the ductwork and piping differently. Besides, identifying design issues in early design review provides significant savings by modifying the design phase compared to redoing the work later. DEN has already saved 6,000 hours in labor by creating O&M asset information in Maximo. BIM allowed DEN to shave three months off the schedule for the HTC project. BIM 360 Glue Coordination saved 8 hours per worker per week in design and construction (8,000 hours saved in total). BIM 360 Field saved 2 hours per issue and 1,100 hours in the first six months. It has been reported that BIM reduced RFIs, change orders, and rework by 40 percent (Autodesk n.d.).
The following section lists top challenges identified by DEN.
The following section includes some of the lessons learned that were shared by the owner.
outreach and by simplifying BIM requirements. DEN is seeing experienced companies lowering costs, especially for designers. Contractors are also lowering prices but at a slower pace. MEP/Arch designers shared a 40 percent reduction in their costs from their early experience working with DEN requirements through the current requirements. There were also significant reductions in costs associated with certain required tasks, such as laser scanning.
Highways England is a government-owned company and the largest road authority in the UK. It works closely with the Department of Transport and operates as a company on behalf of the UK government to maintain the Strategic Road Network.
Highways England’s BIM journey dates to 2011, when the UK first mandated the use of BIM on public projects. BIM was first used during project delivery to improve the management of large, complex projects. During the early planning, efforts were not supported by a dedicated budget or strategic plan for BIM adoption and execution, although more recent efforts have supported the planning initiatives.
The construction industry in the UK saw the opportunity to use BIM as a risk management tool and adopt more integrated project delivery approaches, such as DB delivery. Costain, a contractor in the UK, sought to use BIM to deliver projects better, faster, and cheaper. In 2012, a Lean Six Sigma group was developed within Costain to investigate the company’s BIM deployment strategy. Part of this evaluation included smaller working groups to investigate technologies, such as 3D modeling and Common Data Environment (CDE) processing. The company started to transform its process from developing CAD standards to adopting BIM processes. The adoption of BIM by Costain on highway projects was accelerated due to the government mandate for BIM Level 2 requirements that was released in early 2016.
This case study is based on the highway project A556. The site is in Cheshire in Northwest England. This 7.6-kilometer stretch of highway serves as one of the primary routes into Manchester City. The project objective was to expand the highway capacity of the congested corridor and improve the geometry of the 7.6-kilometer section connecting the M6 Junction 19 near Knutsford with the M56 Junction 7 near Bowdon. The project was procured as a DB delivery, a newer delivery approach for Highways England. The scope of work included significant roadway work to convert the existing undivided highway to a divided facility. Also, the project included the construction of seven new bridges, one pedestrian underpass, and refurbishment works to two existing bridges (England Highways Agency 2014). The total project cost was £200 million, including the construction cost of £107 million. The timeline included three phases: 1) 18-month planning phase; 2) 18-month design phase; and 3) two-year construction phase.
BIM Use Cases
Several primary BIM uses were frequently adopted or required on this project, as seen in the following examples.
From a technology standpoint, the initial bridge and highway design models were developed by the design engineers on this project using 3D parametric modeling software. The bridge models were then exported into openBIM data files (IFC) to allow for further design review. The designs were reviewed by leveraging a nonproprietary 3D viewer to show design, properties, and ownership (Petri et al. 2017). The team delivered the design through a federated 3D model.
A new approach was adopted by the design engineers for this project. To meet the project schedule, the design needed to be complete prior to starting construction. This required revising the detailed 3D modeling process, the overall design process, and design reviews with stakeholders, which helped to identify potential future issues.
One benefit of this approach was the identification of a massive utility that would have been diverted around if discovered later. The design team was able to demonstrate the value to the owner of leaving the utility in place because of the modeling approach and investigation of existing utility locations, since the entire team could visualize the utility conditions and impact. This decision is estimated to have saved £1 million in cost with reduced redundancy since they were able to plan properly. Without this process, they would have diverted around the utility. The lead designer perceived that early contractor involvement, with the right parties on board from the outset informing the design, makes a huge difference.
The construction team performed some 3D modeling during the construction phase, partially focused on developing the target price for the construction estimate. This model content was then used to develop and extract quantities for the estimated costs. One example provided by the team was related to the modeling of fencing. On a typical project of this scale, it might take three days to perform a detailed take-off of the construction fencing; but after developing the model, the take-off only took three minutes to extract the modeled quantities.
The IFC models of the bridges were used for performing detailed 3D coordination. The models were used within an automated collision detection software to identify 3D geometric clashes. The clashes were then resolved prior to construction.
The contractor reflected upon a previous project for which the management of RFIs was a full-time job, referring to the previous project as “chaotic.” This was avoided in the A556 project by getting parties involved earlier and leveraging model content to resolve design coordination issues. The construction team’s familiarity with the design early in the process cascaded through the rest of the team. Few problems were identified with the early involvement of everyone in the pre-construction work except for unforeseen factors, such as unknown utilities.
In the construction phase, the constructor used AMG for equipment operations. The process focused on leveraging the 3D model as an input, along with some post-processing routines, to extract a terrain that could be leveraged by the AMG software. There are no current minimum requirements for delivering AMG information to constructors. Construction industry practitioners speculate that if a set of standard minimum information requirements were adopted by
the owner, the resulting process would create greater efficiencies, which would help drive down prices for equipment operations.
Throughout this project, design and construction teams developed the model to include asset data and leverage template parametric content libraries within the 3D software. After completion of construction, the teams performed an extract, transform, and load process to transition the data from the design model into the asset management system. The operations phase was managed by leveraging GIS data, which is populated from the content within the 3D models.
The following section contains a summary of the identified benefits and costs based upon an interview with team participants.
team worked with potential suppliers and leveraged models to solicit their constructability views, while also performing collaborative workshops that ultimately yielded changed profiles of bridge beams. These detailed reviews significantly reduced concrete volumes used in this project, which yielded estimated savings of £300,000.
A confidential benefit-cost analysis (BCA) was performed for this project, and it clearly demonstrated the potential for savings during the project delivery phase.
The following list includes top challenges identified by the team.
The following list includes several lessons learned.
Researchers worked with a BIM expert panel to validate and confirm information collected through the literature review and case study interviews regarding BIM adoption. This expert panel was consulted to help fill in any data gaps for the ROI framework.
Specifically, the panel was asked to
The panel consisted of a multidisciplinary group, including bridge and roadway engineers, asset management strategists, and BIM technical support staff from both the building and infrastructure domains.
As shown in Figure 3-3, a series of two virtual workshops were held. During the first workshop, researchers introduced the expert panel to the project objectives and desired outcomes
for their participation, research methodology, and preliminary examination of cost and benefit measures. At the end of the workshop, the researchers provided a data collection booklet that the expert panel could use to assist with filling in the data gaps for specific measures. During the second workshop, the expert panel reconvened to discuss specific input for each of the cost and benefit measures in the workbook.
The information collected during these two virtual workshops was used to fill in data gaps and finalize the cost and benefit data values used for the ROI framework in Chapter 4.