STANDARD SPECIFICATIONS FOR HIGHWAY CONSTRUCTION (2022) available at https://www.dot.state.al.us/publications/construction/Specifications.html
Alabama Std. Spec. § 108.09 generally provides for a time extension for delaying circumstances beyond the contractor’s control. It does not specifically identify pandemics, epidemics, or quarantines as potentially excusable events.
STANDARD SPECIFICATIONS FOR HIGHWAY CONSTRUCTION (2020) available at https://dot.alaska.gov/stwddes/dcsspecs
Alaska Std. Spec. § 108-1.06 provides for a noncompensable time extension for delays from unforeseeable causes beyond the contractor’s control, specifically including epidemics and quarantine restrictions.
STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION (2021) available at https://azdot.gov/business/contracts-and-specifications/specifications-pay-items-list
Arizona Std. Spec. § 108.08 generally provides for a time extension for delays due to unforeseeable causes beyond the contractor’s control. It does not specifically identify pandemics, epidemics, or quarantines as potentially excusable events.
STANDARD SPECIFICATIONS FOR HIGHWAY CONSTRUCTION (2014) available at http://www.ahtd.ar.gov/standard_specifications.aspx
Arkansas Std. Spec. § 108.06(d) generally provides for a time extension for delaying circumstances beyond the contractor’s control. It does not specifically identify pandemics, epidemics, or quarantines as potentially excusable events. A separate provision, Arkansas Std. Spec. § 107.01, requires the contractor to observe and comply with all quarantines.
STANDARD SPECIFICATIONS (2022) available at https://dot.ca.gov/programs/design/october-2022-ccs-standard-plans-and-standard-specifications
California Std. Spec. § 1-1.07 defines “working day” to exclude any day that the contractor cannot perform work due to unanticipated events not caused by a contracting party, specifically including epidemics and quarantine restrictions.
STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION (2022) available at https://www.codot.gov/business/designsupport/cdot-construction-specifications/2022-construction-specifications/2022-specs-book
Colorado Std. Spec. § 108.08(c) provides for a noncompensable time extension for delaying circumstances beyond the contractor’s control, specifically including force majeure circumstances. A separate provision, Colorado Std. Spec. § 107.06(a), specifically requires the contractor’s safety plan to address sanitization and protective measures taken during a pandemic.
SPECIFICATIONS FOR ROADS, BRIDGES, AND INCIDENTAL CONSTRUCTION (2004) available at https://portal.ct.gov/DOT/IT/ConnDOT-Publications-Manuals
Connecticut Std. Spec. § 1.08.08 generally provides for a time extension for delays due to unforeseeable causes beyond the contractor’s control. It does not specifically identify pandemics, epidemics, or quarantines as potentially excusable events.
STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION (2020) available at https://deldot.gov/Publications/manuals/standard_specifications
Delaware Std. Spec. § 108.7.B provides for a noncompensable time extension for delays due to unforeseeable causes beyond the contractor’s control, specifically including epidemics.
STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION (202324) available at https://www.fdot.gov/programmanagement/implemented/specbooks/default.shtm
Florida Std. Spec. § 87.3.2 generally provides for a time extension for delays due to unforeseeable causes beyond the contractor’s control. It does not specifically identify pandemics, epidemics, or quarantines as potentially excusable events.
STANDARD SPECIFICATIONS CONSTRUCTION OF TRANSPORTATION SYSTEMS (2021) available at https://www.dot.ga.gov/GDOT/Pages/TheSource.aspx
Georgia Std. Spec. § 108.07.E generally provides for a time extension for delaying circumstances beyond the contractor’s control. A separate section, Georgia Std. Spec. § 101.04, defines “available day” to exclude any day that the contractor cannot perform work due to causes beyond the contractor’s control, specifically including epidemics and quarantines.
STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION (2005) available at https://hidot.hawaii.gov/highways/s2005-standard-specifications
Hawaii Std. Spec. § 108.05(B)(3) provides for a time extension for delaying circumstances beyond the contractor’s control, specifically including epidemics and quarantine restrictions.
STANDARD SPECIFICATIONS FOR HIGHWAY CONSTRUCTION (2023) available at https://apps.itd.idaho.gov/apps/manuals/manualsonline.html
Idaho Std. Spec. § 108.07 provides for a noncompensable time extension for delays due to unforeseeable causes not caused by a contracting party, specifically including epidemics.
STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION (2022) available at https://idot.illinois.gov/doingbusiness/procurements/engineering-architectural-professional-services/consultant-resources/standard-specifications.html
Illinois Std. Spec. § 108.08 provides for a time extension only for specific delaying circumstances beyond the contractors’ control, including epidemics (but not quarantines).
STANDARD SPECIFICATIONS (2022) available at https://www.in.gov/dot/div/contracts/standards/book/sep21/sep.htm
Indiana Std. Spec. § 108.08(a) provides for a noncompensable time extension for delaying circumstances that are not the fault or responsibility of the contractor, specifically including epidemics.
STANDARD SPECIFICATIONS FOR HIGHWAY AND BRIDGE CONSTRUCTION (2023) available at https://iowadot.gov/specifications
Iowa Std. Spec. § 1108.07 provides for a time extension only for extra work. There is no express remedy for delays due to force majeure circumstances.
STANDARD SPECIFICATIONS FOR STATE ROAD AND BRIDGE CONSTRUCTION (2015) available at https://www.ksdot.gov/burconsmain/specprov/specifications.asp
Kansas Std. Spec. § 108.6 generally provides for a time extension where the work is delayed due to acts of God. A separate provision, Kansas Std. Spec. § 104.7, provides that delays due to acts of God are noncompensable. Pandemics, epidemics, and quarantines are not specifically identified as acts of God that would warrant a time extension.
STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION (2019) available at https://transportation.ky.gov/Construction/Pages/Kentucky-Standard-Specifications.aspx
Kentucky Std. Spec. § 105.13.03 provides that delays due to unforeseeable circumstances that are not the fault or responsibility of the contractor, specifically including epidemics, are excusable.
STANDARD SPECIFICATIONS FOR ROADS AND BRIDGES (2016) available at http://wwwsp.dotd.la.gov/Inside_LaDOTD/Divisions/Engineering/Standard_Specifications/Pages/Standard%20Specifications.aspx
Louisiana Std. Spec. § 108.07 generally provides for a time extension for delaying circumstances beyond the contractor’s control. It does not specifically identify pandemics, epidemics, or quarantines as potentially excusable events.
STANDARD SPECIFICATIONS (2020) available at https://www.maine.gov/mdot/contractors/publications/standardspec
Maine Std. Spec. § 109.5.1 provides that delays due to uncontrollable events are excusable. A separate provision, Maine Std. Spec. § 101.2, defines uncontrollable events as those that are unforeseeable at bid time and beyond the contractor’s control, specifically including quarantine restrictions.
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS (2023) available at https://roads.maryland.gov/mdotsha/pages/sscm.aspx?PageId=853
Maryland Std. Spec. § GP8.08(d) provides for a time extension for delays due to unforeseeable causes beyond the contractor’s control, specifically including epidemics and quarantine restrictions.
STANDARD SPECIFICATIONS FOR HIGHWAYS AND BRIDGES (2023) available at https://www.mass.gov/lists/construction-specifications
Massachusetts Std. Spec. § 8.10 provides for a time extension for delaying circumstances beyond the contractor’s control, specifically including epidemics.
STANDARD SPECIFICATIONS FOR CONSTRUCTION (2020) available at https://www.michigan.gov/mdot/business/construction/standard-specifications-and-publications
Michigan Std. Spec. § 108.08 provides for a time extension for delays due to unforeseen causes beyond the contractor’s control, specifically including epidemics.
STANDARD SPECIFICATIONS FOR CONSTRUCTION (2020) available at https://www.dot.state.mn.us/pre-letting/spec
Minnesota Std. Spec. § 1806.2 provides for a noncompensable time extension for delays due to unforeseeable causes beyond the contractor’s control, specifically including pandemics, epidemics, public health emergencies, and government-ordered quarantines.
STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION (2017) available at https://mdot.ms.gov/portal/engineering_standards_guides_manuals
Mississippi Std. Spec. § 108.06.1.3 provides for a time extension for delays due to specific unforeseen circumstances including “abnormal delays caused solely by the State or other governmental authorities, or unforeseeable disastrous phenomena of nature.” Pandemics, epidemics, and quarantines are not specifically identified as circumstances that would warrant a time extension.
STANDARD SPECIFICATIONS FOR HIGHWAY CONSTRUCTION (2023) available at https://www.modot.org/missouri-standard-specifications-highway-construction
Missouri Std. Spec. § 108.14.1 provides for a noncompensable time extension for delaying circumstances not caused by the contractor, specifically including epidemics and quarantine restrictions.
STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION (2020) available at https://www.mdt.mt.gov/business/contracting/standard-specs.aspx
Montana Std. Spec. § 108.07.4 provides for a noncompensable time extension for delaying circumstances not caused by the contractor, specifically including epidemics and quarantine restrictions.
STANDARD SPECIFICATIONS FOR HIGHWAY CONSTRUCTION (2017) available at https://dot.nebraska.gov/media/g4qp4y0d/2017-specbook.pdf
Nebraska Std. Spec. § 108.02 generally provides for a time extension for delaying circumstances beyond the contractor’s control. It does not specifically identify pandemics, epidemics, or quarantines as potentially excusable events.
STANDARD SPECIFICATIONS FOR HIGHWAY CONSTRUCTION (2017) available at https://www.dot.nv.gov/doing-business/contractors-construction/contract-services/standard-specifications-and-plans
Nevada Std. Spec. § 108.08 provides for a time extension for delays due to unforeseen causes beyond the contractor’s control, specifically including epidemics.
STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION (2016) available at https://www.dot.nh.gov/about-nh-dot/divisions-bureaus-districts/highway-design/highway-standard-specifications
New Hampshire Std. Spec. § 108.07 provides for a noncompensable time extension for delaying circumstances not caused by a contracting party, specifically including epidemics and quarantine restrictions.
STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION (2019) available at https://www.nj.gov/transportation/eng/specs/2019/Division.shtml
New Jersey Std. Spec. § 108.11,01 provides for a noncompensable time extension for delaying circumstances not caused by a contracting party, specifically including “epidemic or quarantine restrictions, states of emergency, and State shutdowns.”
STANDARD SPECIFICATIONS FOR HIGHWAY AND BRIDGE CONSTRUCTION (2019) available at https://www.dot.nm.gov/infrastructure/plans-specifications-estimates-pse-bureau/standards
New Mexico Std. Spec. § 107.20 provides for a noncompensable time extension for delaying circumstances beyond the contractor’s control, specifically including epidemics and quarantine restrictions.
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS (2024) available at https://www.dot.ny.gov/main/business-center/engineering/specifications/updated-standard-specifications-us
New York Std. Spec. § 108-03 generally provides for a time extension for delaying circumstances beyond the contractor’s control. It does not specifically identify pandemics, epidemics, or quarantines as potentially excusable events.
STANDARD SPECIFICATIONS FOR ROADS AND STRUCTURES (2018) available at https://connect.ncdot.gov/resources/Specifications/StandSpecLibrary
North Carolina Std. Spec. § 108-10 generally provides for a time extension for delaying circumstances beyond the contractor’s control. It does not specifically identify pandemics, epidemics, or quarantines as potentially excusable events.
STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION (2023) available at https://www.dot.nd.gov/dotnet/supplspecs/standardspecs.aspx
North Dakota Std. Spec. § 108.06 provides for a noncompensable time extension for delaying circumstances not caused by a contracting party, specifically including epidemics and quarantines.
CONSTRUCTION AND MATERIAL SPECIFICATIONS (2023) available at https://www.transportation.ohio.gov/working/publications/spec-book
Ohio Std. Spec. § 108.06 provides for a noncompensable time extension for delaying circumstances not caused by a contracting party, specifically including epidemics.
STANDARD SPECIFICATIONS FOR HIGHWAY CONSTRUCTION (2019) available at https://oklahoma.gov/odot/business-center/construction/construction-engineering.html
Oklahoma Std. Spec. § 108.07 provides for a noncompensable time extension for delaying circumstances not caused by the contractor, specifically including epidemics and quarantine restrictions.
STANDARD SPECIFICATIONS FOR CONSTRUCTION (2024) available at https://www.oregon.gov/odot/business/pages/standard_specifications.aspx
Oregon Std. Spec. § 00180.50 provides that the contract time excludes days that the contractor cannot perform work due to specific circumstances including acts of God. Pandemics, epidemics, and quarantines are not specifically identified as acts of God that would warrant a time extension.
CONSTRUCTION SPECIFICATIONS (2020) available at https://www.penndot.pa.gov/ProjectAndPrograms/Construction/Pages/ConstructionSpecifications.aspx
Pennsylvania Std. Spec. § 108.08 provides for a time extension for specific delaying circumstances beyond the contractors’ control. It does not specifically identify pandemics, epidemics, or quarantines as potentially excusable events.
STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION (2023) available at https://www.dot.ri.gov/business/bluebook/index.php
Rhode Island Std. Spec. § 108.07 generally provides for a time extension for delaying circumstances beyond the contractor’s control. It does not specifically identify pandemics, epidemics, or quarantines as potentially excusable events.
STANDARD SPECIFICATIONS FOR HIGHWAY CONSTRUCTION (2007) available at https://www.scdot.org/business/standard-specifications.aspx
South Carolina Std. Spec. § 108.6 generally provides for a time extension for delaying circumstances beyond the contractor’s control. It does not specifically identify pandemics, epidemics, or quarantines as potentially excusable events.
STANDARD SPECIFICATIONS FOR ROADS AND BRIDGES (2015) available at https://dot.sd.gov/doing-business/contractors/standard-specifications
South Dakota Std. Spec. § 8.7 generally provides for a time extension for delays due to unforeseeable causes beyond the contractor’s control. It does not specifically identify pandemics, epidemics, or quarantines as potentially excusable events.
STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION (2021) available at https://www.tn.gov/tdot/tdot-construction-division/transportation-construction-division-resources/2021-standard-specifications.html
Tennessee Std. Spec. § 108.07 provides for a noncompensable time extension for delays due to force majeure circumstances not caused by a contracting party, specifically including pandemics and epidemics.
STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MAINTENANCE OF HIGHWAYS, STREETS, AND BRIDGES (2024) available at https://www.txdot.gov/business/resources/txdot-specifications.html
Texas Std. Spec. Item 8, § 5.5.4 generally provides for a time extension for delaying circumstances beyond the contractor’s control. It does not specifically identify pandemics, epidemics, or quarantines as potentially excusable events.
STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION (2024) available at https://udot.utah.gov/connect/business/standards
Utah Std. Spec. § 00777, pt. 1.4 provides a noncompensable time extension for delays caused by force majeure circumstances (specifically including epidemics and quarantine restrictions) or other unforeseeable circumstances beyond the contrator’s control
STANDARD SPECIFICATIONS FOR CONSTRUCTION (2024) available at https://vtrans.vermont.gov/highway/construct-material/construct-services/pre-contractspecifications/vermont
Vermont Std. Spec. § 108.11 generally provides for a time extension for delays caused by unforeseen circumstances beyond the contractor’s control. It does not specifically identify pandemics, epidemics, or quarantines as potentially excusable events.
ROAD AND BRIDGE SPECIFICATIONS (2020) available at https://www.virginiadot.org/business/const/spec-default.asp
Virginia Std. Spec. § 108.04 generally provides for a time extension for delays caused by unforeseen circumstances beyond the contractor’s control. A separate provision, Virginia Std. Spec. § 109.05, provides that delays due to epidemics or quarantine restrictions are noncompensable.