Previous Chapter: 2 Literature Review
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.

CHAPTER 3

State of the Practice Survey

Introduction

This chapter presents current practices, tools, and approaches used by state DOTs for managing compliance with state and federal construction stormwater permit requirements. To collect the most current information on policies, procedures, and guidelines used by DOTs to track and report on construction stormwater compliance, a web-based survey was distributed to the voting members of the AASHTO Committee on Construction, which includes representatives from all 50 state DOTs, the District of Columbia, and Puerto Rico. The findings presented are based on 42 state DOT respondents (an 81% response rate) (see Figure 3). In addition, the analysis of relevant documents obtained from the survey is also included to support the findings. The chapter begins by reporting the general findings of construction stormwater management, including types of construction stormwater programs, best management practices (BMPs), and the preparation and management of stormwater pollution prevention plans (SWPPPs) for highway construction projects. The chapter then presents responsible parties for the development of construction stormwater management programs. Next, qualifications and design standards for construction stormwater management are discussed. The chapter concludes by presenting the current practices in tracking, monitoring, and auditing the implementation of construction components of the stormwater program.

It is important to note that the 42 state DOT respondents were not required to respond to all questions in the survey. As a result, the sample size (N) for each question varies. Additionally, some questions were marked as “Select all that apply,” meaning that the frequencies for some questions did not add up to 100% as respondents were allowed to choose more than one selection. Appendix A provides the complete survey questionnaire. Appendix B provides individual agency responses to each survey question.

Overview of Construction Stormwater Management Programs

The survey results indicate that construction stormwater management practices vary among state DOTs. Figure 4 shows that DOTs use three approaches for construction stormwater management. Construction stormwater management can be a part of the project management process into which it is infused with the rest of the project management processes carried out during construction. Within a formal construction stormwater management program, the DOT has a separate office or division outside of project management that manages the construction stormwater program for highway construction. Some DOTs also use a combination of these two approaches: the DOT determines from project to project which approach to use. Of 42 DOT responses, 25 (60%) have handled construction stormwater management practices as a part of

Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
The map of the United States is shown with each state individually outlined and labeled by its two-letter abbreviation. States that responded to the survey are shaded in dark gray, while those that did not respond are left unshaded. The majority of the country, including continental states and Alaska and Hawaii, is shaded, showing widespread participation. Notable exceptions are a small group of unshaded states, including Montana, Wyoming, Washington, Oregon, Kentucky, Tennessee, Louisiana, and South Carolina, which indicates that these state departments of transportation, abbreviated D O T s, did not respond to the survey.
Figure 3. Map of state DOTs responding to the survey.

their project management process; 11 (26%) have a formal construction stormwater management program; and 6 (14%) have managed their construction stormwater systems by using either a formal program or a project management process, depending on the scope and size of a project.

The survey respondents were asked to identify divisions involved in the construction stormwater management programs in their state DOTs and were allowed to select all that apply. Figure 5 summarizes the results of this question. More than half of the 42 DOTs indicated that the following four divisions are involved in the construction stormwater management program:

  1. Construction division (41 of 42 DOTs, 98%)
  2. Environment division (35 of 42 DOTs, 83%)
The chart uses a scale along the horizontal axis for the number of D O T responses, ranging from 0 to 30. The top bar, labeled “construction stormwater management is part of the project management process,” extends to 60 percent. The second bar, labeled “formal construction stormwater management program, separate from project management,” reaches 26 percent. The third bar, labeled “both options above are used depending on project scope and size,” extends to 14 percent.
Figure 4. Construction stormwater programs managed by state DOTs (N = 42).
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
The chart uses a scale along the horizontal axis ranging from 0 to 50. Different DOT divisions involved in stormwater management programs are listed along the vertical axis. Ten horizontal bars show response percentages for divisions in stormwater programs: construction 98, environment 83, design or engineering 74, stormwater management or drainage 55, permitting 43, maintenance or operations 43, landscape design 24, policy and regulations 19, materials 17, other 2. The bars decrease in length from top to bottom, with counts shown on the x-axis.
Figure 5. Divisions involved in construction stormwater management programs (N = 42).
  1. Design/Engineering division (31 of 42 DOTs, 74%)
  2. Stormwater Management/Drainage division (23 of 42 DOTs, 55%)

Figure 5 also shows that 18 state DOTs (43%) have managed their construction stormwater management programs through either permitting or maintenance and operation divisions; 10 (24%) have managed their construction stormwater management programs through the landscape design division; 8 (19%) have managed their construction stormwater management programs through the policy and regulation divisions; and 7 (17%) have managed their construction stormwater management programs through materials divisions.

Figure 6 summarizes the approaches to construction stormwater management state DOTs regularly use for highway projects. Of 42 DOT responses (selecting all that apply), 33 (79%) have used statewide approaches; 27 (64%) indicated that the approaches to construction stormwater management vary project by project; 14 (33%) selected an approach to construction stormwater management based on types of projects; and 9 (21%) have relied on state DOT districts to manage construction stormwater systems for highway projects.

The horizontal axis ranges from 0 to 40, showing the number of D O T responses. The vertical axis lists management approaches: statewide at 79 percent, project-by-project at 64 percent, by types of projects at 33 percent, by state D O T district at 21 percent, and other at 7 percent.
Figure 6. Approaches to construction stormwater management (N = 42).
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.

From the responding state DOTs that selected “Other” for this question, one DOT mentioned that all projects that disturb 1 or more acres of land require a CGP to follow its water quality specifications and that all projects smaller than 1 acre are required to follow a special standard. Another DOT uses the DOT Resident Construction Engineer Office to manage construction stormwater systems. In addition, one other DOT stated that their approach to construction stormwater management is based on the size of the contributing area.

The survey respondents were asked to select all the construction stormwater management control measures approved by their DOTs for use in highway construction projects, as each respondent could choose more than one selection. Figure 7 summarizes the results of this question.

The horizontal axis is labeled number of D O T responses and ranges from 0 to 50. The vertical axis lists construction stormwater management control measures, each paired with a percentage. Erosion control logs, check dams, stabilized construction entrances or exits, silt fence or barriers, sediment basins, and hydro mulching or seeding all have a 100 percent response. Erosion control blankets, drainage swales or ditches, limitations of disturbance, riprap, and inlet protection each have 98 percent. Diversion berms or dikes are at 95 percent. Construction de-watering, sediment traps, and mulching each have 93 percent. Dust control, turbidity barrier, and preserving existing vegetation are at 90 percent. Temporary stream crossing is 88 percent. Surface roughening and outlet protection are both at 86 percent. Water quality structural controls and pipe slope drains both have 83 percent. Bonded fiber matrix has 79 percent. Water quality non-structural controls, turf reinforcement mats, and sodding each have 76 percent. Subsurface drains and bales have 55 percent. Flexible growth medium and level spreader both have 52 percent. Flocculants are 48 percent. Active treatment systems are at 33 percent, other chemical treatments are at 26 percent, and other is at 12 percent.
Figure 7. Construction stormwater management control measures (N = 42).
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.

More than 90% of the responding 42 state DOTs have approved the following construction stormwater management control measures for use in highway construction projects:

  • Erosion control logs such as wattles, sediment tubes, fiber rolls, or composite socks (42 of 42 DOTs, 100%)
  • Check dams, including rock, sandbags, socks, rolls, silt fence, or tubes (42 of 42 DOTs, 100%)
  • Stabilized construction entrances and exits (42 of 42 DOTs, 100%)
  • Silt fence and barriers (42 of 42 DOTs, 100%)
  • Sediment basins (42 of 42 DOTs, 100%)
  • Temporary or permanent hydromulching/seeding (42 of 42 DOTs, 100%)
  • Erosion control blankets such as channel or slope (41 of 42 DOTs, 98%)
  • Drainage swales/ditches (41 of 42 DOTs, 98%)
  • Limitations of disturbance, such as grading limits (41 of 42 DOTs, 98%)
  • Riprap (41 of 42 DOTs, 98%)
  • Inlet protection (41 of 42 DOTs, 98%)
  • Diversion berms/dikes (40 of 42 DOTs, 95%)
  • Construction dewatering (39 of 42 DOTs, 93%)
  • Sediment traps (39 of 42 DOTs, 93%)
  • Mulching such as grass, hay, wood chips, wood fibers, or straw (39 of 42 DOTs, 93%)

More than 80% of the responding 42 state DOTs have approved the following construction stormwater management control measures for use in highway construction projects:

  • Dust control (38 of 42 DOTs, 90%)
  • Turbidity barrier such as staked or floating (38 of 42 DOTs, 90%)
  • Preservation of existing vegetation (38 of 42 DOTs, 90%)
  • Temporary stream crossing (37 of 42 DOTs, 88%)
  • Surface roughening, such as tracking, stair-step grading, and grooving (36 of 42 DOTs, 86%)
  • Outlet protection (36 of 42 DOTs, 86%)
  • Water quality structural controls such as detention ponds and vegetated filter strips (35 of 42 DOTs, 83%)
  • Pipe slope drains (35 of 42 DOTs, 83%)

Five state DOT responses selected “Other” and provided additional information. One DOT mentioned using topography (landform), vegetative buffers, and temporary stabilization phasing (tracking, terracing, slope controls). The same DOT allows non-standard control measures if a project specialist or engineer approves. Another DOT has a stormwater design manual that includes standard permanent practices and an environmental handbook for construction operations that covers standard temporary control measures.

Figure 7 also shows that 20 of the 42 responding state DOTs (48%) have used flocculants for their construction stormwater management control measures. For the five DOTs that selected “Other,” one DOT had used flocculants in the form of synthetic polymers (e.g., polyacrylamide), and two DOTs had used flocculants in the form of inorganic polymers (e.g., polyaluminum chloride). Additionally, one DOT indicated that anionic polyacrylamide is allowed but has not yet been used. One DOT mentioned that it does not have restrictions on flocculants and that contractors determine the use of flocculants. The same DOT also pointed out using flocculants in some cases of sediment discharges.

Preparation and Management of Stormwater Pollution Prevention Plans

The survey respondents were asked to identify parties responsible for preparing and managing SWPPPs in highway construction projects and to select all parties that apply. Figure 8 summarizes the results of this question. The main parties responsible for preparing SWPPPs include

Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
The horizontal axis is labeled number of D O T responses and ranges from 0 to 50. The vertical axis lists roles involved in stormwater pollution prevention plans. For each role, two horizontal bars are shown: one for managing and one for preparing plans. The percentages for manage and prepare are as follows: Design engineer, 5 percent manage and 62 percent prepare; contractor, 79 percent manage and 57 percent prepare; consultants, 38 percent manage and 50 percent prepare; D O T project management team, 31 percent manage and 21 percent prepare; environmental control specialist, 14 percent manage and 19 percent prepare; stormwater or drainage program manager, 19 percent manage and 17 percent prepare; environmental engineer, 7 percent manage and 17 percent prepare; environmental department manager, 7 percent manage and 14 percent prepare; construction project manager, 62 percent manage and 10 percent prepare; other, 10 percent manage and 12 percent prepare.
Figure 8. Preparation and management of SWPPPs (N = 42).

design engineers (26 of 42 responding state DOTs, 62%), contractors (24 of 42 DOTs, 57%), and consultants (21 of 42 DOTs, 50%). The main parties responsible for managing SWPPPs include contractors (33 of 42 DOTs, 79%), construction project managers (26 of 42 DOTs, 62%), and consultants (16 of 42 DOTs, 38%).

From the “Other” responses, two state DOTs mentioned that an agronomist is responsible for preparing SWPPPs for their highway construction projects. One DOT uses a District Environmental Planner to prepare SWPPPs. Another DOT indicated that an inspector is responsible for preparing and managing SWPPPs. One DOT stated that the contractor prepares SWPPPs for design-build projects but that the department approves and oversees the plan during construction. Another DOT uses a Resident Engineer to manage SWPPPs. One DOT responded that preparation and management of SWPPPs are incorporated into municipal separate storm sewer systems (MS4s) permit requirements for a design-bid-build project.

Figure 9 shows the timeline for state DOTs preparing a SWPPP for a highway construction project. Each responding DOT was allowed to select all that apply. Of 42 DOTs, 25 (60%) reported that they prepare SWPPPs during project design and engineering; 15 (36%) prepare SWPPPs

The horizontal axis is labeled number of D O T responses and ranges from 0 to 30. The vertical axis lists timing options for preparing stormwater pollution prevention plans. During design and engineering of a project is reported by 60 percent. Pre-construction is reported by 36 percent. Just prior to construction is 19 percent. In conjunction with the National Environmental Policy Act plan is 10 percent. 17 percent is other.
Figure 9. Timeline to prepare SWPPPs (N = 42).
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.

during the pre-construction phase; and 8 (19%) prepare SWPPPs prior to the construction phase. Four responding DOTs (10%) prepare the SWPPP for a highway construction project in conjunction with the National Environmental Policy Act plan.

From the responding state DOTs that selected “Other,” one DOT mentioned that the contractor is required to complete the SWPPP following the permitting requirements before starting any earth-disturbing activities. Another DOT indicated that a contractor is responsible for preparing the SWPPP before getting a permit. One DOT reported that the design team completes SWPPP components as known and that contractors prepare an implementation plan for unknown items such as schedule-related items and dewatering activities. Another DOT prepares the SWPPP after the project is awarded. One DOT mentioned that “preparing the SWPPP varies based on contract types. It is a requirement from the Form 128 Clearance process in most cases. The design of the SWPPP is completed on projects before the advertisement on design-bid-build projects and modified by the contractor per specifications when the project is active.”

Responsibilities for Construction Stormwater Management

State DOTs rely on in-house staff, contractors, or consultants to design, monitor, and maintain construction stormwater systems. Figure 10 summarizes the responsibilities of state DOTs, contractors, and consultants associated with typical tasks in construction stormwater management. For each party listed (state DOT, consultant, contractor), responding state DOTs could select all that apply.

Figure 10 also shows that more than three-quarters of 41 state DOT responses (one responding DOT did not answer this question) indicated that contractors are responsible for the following tasks related to construction stormwater management:

  • Installation (41 of 41 DOTs, 100%)
  • Violation remediation (40 of 41 DOTs, 98%)
The horizontal axis is labeled number of D O T responses and ranges from 0 to 50, while the vertical axis lists responsibilities in construction stormwater management. For each responsibility, three horizontal bars represent consultants, contractors, and state departments of transportation, D O Ts. Installation is reported by consultants at 7 percent, contractors at 100 percent, and state D O Ts at 17 percent. Violation remediation reported by consultants has no data, contractors at 98 percent, and state D O Ts at 63 percent. Maintenance is reported by consultants at 7 percent, contractors at 95 percent, and state D O Ts at 27 percent. Inspection deficiency remediation is reported by consultants at 17 percent, contractors at 88 percent, and state D O Ts at 44 percent. Monitoring and tracking control measures is reported by consultants at 46 percent, contractors at 80 percent, and state D O Ts at 88 percent. Inspections are reported by consultants at 54 percent, contractors at 76 percent, and state D O Ts at 85 percent. Reporting is reported by consultants at 41 percent, contractors at 63 percent, and state D O Ts at 80 percent. Training project personnel is reported by consultants at 29 percent, contractors at 39 percent, and state D O Ts at 83 percent. Design guidance development is reported by consultants at 37 percent, contractors at 15 percent, and state D O Ts at 88 percent.
Figure 10. Responsibilities of construction stormwater management (N = 41).
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
  • Maintenance (39 of 41 DOTs, 95%)
  • Inspection deficiency remediation (36 of 41 DOTs, 88%)
  • Monitoring and tracking control measures (33 of 41 DOTs, 80%)
  • Inspections (31 of 41 DOTs, 76%)

More than half of 41 state DOTs responding to this question indicated they are responsible for the following tasks related to construction stormwater management:

  • Design guidelines development (36 of 41 DOTs, 88%)
  • Monitoring and tracking control measures (36 of 41 DOTs, 88%)
  • Inspections (35 of 41 DOTs, 85%)
  • Training project personnel (34 of 41 DOTs, 83%)
  • Reporting (33 of 41 DOTs, 80%)
  • Violation remediation (26 of 41 DOTs, 63%)

More than one-third of 41 state DOT responses indicated that consultants are responsible for the following tasks related to construction stormwater management:

  • Inspections (22 of 41 DOTs, 54%)
  • Monitoring and tracking control measures (19 of 41 DOTs, 46%)
  • Reporting (17 of 41 DOTs, 41%)
  • Design guidelines development (15 of 41 DOTs, 37%)

The survey respondents were asked about the percentage of construction stormwater management inspections conducted by consultants. Figure 11 summarizes the results of this question. Of 42 responding state DOTs, 15 (36%) indicated that consultants conduct less than 10% of their construction stormwater inspections; 6 (14%) have not used consultants to inspect their construction stormwater management; and 5 (12%) have used consultants for more than 50% of their construction stormwater management inspections.

Respondents were asked about the cost of installing and maintaining control measures; each respondent could select all parties that apply. Figure 12 shows that 27 of 41 responding state DOTs (66%) (one responding state DOT did not answer this question) indicated that they are responsible for the cost of installing stormwater control measures for highway construction

The horizontal axis is labeled number of D O T responses and ranges from 0 to 20. The vertical axis lists categories for the percentage of construction stormwater management inspections conducted by consultants. Thirty-six percent of responses fall in the 0 to 10 percent range. Twelve percent report 11 to 20 percent, 10 percent report 21 to 30 percent, 5 percent report 31 to 40 percent, and another 5 percent report 41 to 50 percent. Twelve percent report that more than 50 percent of inspections are conducted by consultants. Fourteen percent state that they do not conduct inspections, and 7 percent are not sure.
Figure 11. Percentage of construction stormwater management inspections conducted by consultants (N = 42).
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
The horizontal axis is labeled number of D O T responses and ranges from 0 to 50. The vertical axis lists cost allocation categories for stormwater control measures. Each category includes two bars: one for cost to maintain or replace and one for cost to install. For the state D O T, 44 percent report covering maintenance or replacement and 66 percent report covering installation. For contractors, 20 percent are reported for maintenance or replacement and 32 percent for installation. For an agreed percentage between D O Ts and contractors, 5 percent report maintenance or replacement and 7 percent report installation. Under the other category, both installation and maintenance or replacement are reported at 20 percent each.
Figure 12. Cost of installing and maintaining construction stormwater control measures (N = 41).

projects. In contrast, 13 DOTs (32%) mentioned that contractors are responsible for the cost of installing stormwater control measures.

Figure 12 also shows that 18 of 41 responding state DOTs (44%) indicated that they are responsible for the cost of maintaining and replacing stormwater control measures. In comparison, 8 DOTs (20%) reported that contractors are responsible for the cost of maintaining and replacing stormwater control measures. Two DOTs (5%) have used a percentage agreed upon between DOTs and contractors for the cost of maintaining and replacing stormwater control measures. Three DOTs (7%) have used a percentage agreed upon between DOTs and contractors for the cost of installing stormwater control measures.

Of the responding state DOTs that selected “Other,” one DOT mentioned that the cost of installing and maintaining control measures varies by project and is included as separate bid price items, a change order, or a percentage of the total contract bid. Another DOT emphasized that “there is a bid item for temporary erosion control, and the costs are included in the bidding process. The contractor includes the costs in their bid. Additionally, erosion control is incorporated into the individual bid items.” One DOT mentioned that “during construction, the contractor is not reimbursed for short-term stabilization and repair (such as covering an excavation area with straw prior to rain or repairing an eroded temporary construction access road) but is paid for building the permanent practices and for most of the temporary practices such as silt fence, hydroseeding, mulch, topsoil, and turf establishment.”

Survey respondents were asked about estimating initial costs to install and maintain control measures for highway construction projects. Figure 13 summarizes the results of this question. Of 37 responding state DOTs (five responding DOTs did not answer this question), 22 (59%) have used a standard estimating approach to initial costs to install and maintain stormwater control measures; and 9 (24%) have used estimated ranges based on project size and complexity.

Additionally, for the state DOTs that responded with “Other,” one DOT uses established cost for individual items and includes a stormwater budget item for payment on the contract. Another DOT uses a combination of cost ranges based on size and complexity and risk management to estimate the costs of installing and maintaining stormwater control measures for a highway construction project. One DOT responded: “The DOT defines the initial cost of installing and maintaining stormwater control measures per project based on the quantities of the SWPPP plan sets. The plan sets are part of the contract documents, and bids are prepared according to the contract type.”

Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
The horizontal axis is labeled number of D O T responses and ranges from 0 to 30. The vertical axis lists methods used to estimate the cost of installing and maintaining construction stormwater control measures. Fifty-nine percent report use a standard estimating approach. Twenty-four percent use estimated cost ranges based on project size and complexity. Five percent are not sure, and 11 percent use other methods.
Figure 13. Cost-estimating approaches to stormwater control measures (N = 37).

Design Standards and Qualifications of Construction Stormwater Programs

Installing and maintaining construction stormwater systems require designers and inspectors to have specific qualifications to comply with permit requirements. Therefore, state DOTs were asked to select the qualification requirements for designers, inspectors, and installers; respondents were allowed to select all the qualifications that apply to each party. For designers, Figure 14 shows that 19 of 42 DOTs (45%) require designers to have a Professional Engineer (PE); 9 (21%) require designers to have DOT-administered certification; and 6 (14%) require designers to have national certifications such as Certified Professional in Erosion and Sediment Control (CPESC), Certified Inspector of Sediment and Erosion Control (CISEC), or State Stormwater Program Certification. Additionally, one DOT mentioned that licensed professionals

The horizontal axis is labeled number of D O T responses and ranges from 0 to 30. The vertical axis lists qualifications required by state National Pollutant Discharge Elimination System programs. Each qualification has three horizontal bars representing installers, inspectors, and designers. For professional engineers, 0 percent are installers, 10 percent are inspectors, and 45 percent are designers. For national certification such as C P E S C or C I S E C, 2 percent are installers, 14 percent are inspectors, and 14 percent are designers. For state regulator administered certification, 5 percent are installers, 14 percent are inspectors, and 10 percent are designers. For the D O T administered certification, 21 percent are installers, 43 percent are inspectors, and 21 percent are designers. For state stormwater program certification, 2 percent are installers, 19 percent are inspectors, and 14 percent are designers. For professional landscape architects, 0 percent are installers, 2 percent are inspectors, and 5 percent are designers. Under other qualifications, 10 percent are installers, 10 percent are inspectors, and 19 percent are designers.
NOTE: For the PE category, 0% refers to installers. For the PLA category, 0% refers to installers.

Figure 14. Qualifications required by state NPDES (N = 42).
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.

(e.g., PE, Professional Geologist, Registered Landscape Architect, Professional Land Surveyor) are required for permanent stormwater control measures design. One DOT indicated that qualification requirements for designers vary by project. Another DOT requires field project engineers to be certified through the DOT E&SC measures certification program.

In relation to inspectors, 18 of 42 responding state DOTs (43%) require them to have DOT-administered certification; 8 (19%) require inspectors to have State Stormwater Program Certification; and 6 (14%) require inspectors to have national certification (CPESC, CISEC) or state regulator administered certification.

Figure 14 also shows that 9 of 42 responding state DOTs (21%) require installers to have a DOT-administered certification. From the “Other” responses, one DOT indicated that “the SPDES General Permit requires the prime contractor and all subcontractors performing earthwork or soil-disturbing activities to identify at least one trained individual from each company who is responsible for implementing the SWPPP and who shall be on-site daily when the company is performing soil disturbance activities. These activities include clearing, grubbing, grading, filling, excavation, stockpiling, demolition.”

The survey respondents were asked to identify the basis for design guidelines for construction stormwater management; respondents selected all that apply. Figure 15 summarizes the results of this question. Of 42 responding state DOTs, 40 (95%) have relied on DOT guidelines for their construction stormwater management; 34 (81%) have relied on state regulator guidelines; and 21 (50%) have used federal guidelines or general construction practices. Less than a third of DOTs have used scientific research or rules of thumb and current practices to develop design standards for their construction stormwater management.

In addition, two responding state DOTs selected “Other” for this question. One DOT has used its Department of Environmental Conservation guidelines to develop design standards for construction stormwater management. Another DOT mentioned that its primary guidelines are based on state permit requirements and current practices.

The survey respondents were asked to identify the parties responsible for developing design standards for construction stormwater management. Responses included selecting all that apply for this question, as multiple parties are responsible for developing design standards at state DOTs. Figure 16 shows that, of 42 responding state DOTs, 37 (88%) indicated state DOTs; 22 (52%) indicated state environmental agency; 6 (14%) indicated FHWA; and 4 (10%) indicated AASHTO as the parties responsible for the development of design standards for construction stormwater management. Additionally, one DOT mentioned that it relied on the state’s Soil and

The horizontal axis is labeled number of D O T responses and ranges from 0 to 50. The vertical axis lists sources of design guidelines for construction stormwater management. D O T guidelines are reported by 95 percent of respondents, state regulator guidelines by 81 percent, federal guidelines by 50 percent, general construction practices by 48 percent, scientific research by 26 percent, rules of thumb or current practices by 24 percent, and other sources by 7 percent.
Figure 15. Design guidelines for construction stormwater management (N = 42).
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
The horizontal axis is labeled number of D O T responses and ranges from 0 to 50. The vertical axis lists parties responsible for developing design standards for construction stormwater management. State D O Ts are reported by 88 percent of respondents, state environmental agencies by 52 percent, the Federal Highway Administration by 14 percent, the American Association of State Highway and Transportation Officials by 10 percent, and other entities by 10 percent.
Figure 16. Parties responsible for the development of design standards for construction stormwater management (N = 42).
The horizontal axis is labeled number of D O T responses and ranges from 0 to 30. The vertical axis lists timelines for updating construction stormwater guidelines. Annual updates are reported by 5 percent, every 2 to 3 years by 10 percent, every 4 to 5 years by 10 percent, every 6 to 7 years by 5 percent, every 8 to 9 years by 0 percent, and every 10 years or more by 2 percent. As-needed updates are reported by 48 percent of respondents, updates based on federal and state requirements are reported by 12 percent, and other timelines by 10 percent.
Figure 17. Timeline to update construction stormwater guidelines (N = 42).

Water Conservation Committee, and two DOTs indicated that the Environmental Protection Agency is the main party responsible for developing design standards for construction stormwater management.

The survey results also identify the frequency of updating state DOT guidelines for construction stormwater management. Figure 17 shows that, of 42 responding state DOTs, 20 (48%) have updated their guidelines as needed; 5 (12%) have updated their guidelines based on the federal and state requirements; and 4 (10%) have updated their construction stormwater management guidelines every 2–3 years or every 4–5 years. Additionally, one DOT mentioned that its major construction stormwater design manual has been updated every 5 years in line with nationwide permit updates.

Stormwater Management Tracking and Inspection

State DOTs were asked to provide methods used to track construction stormwater compliance. The responses from state DOTs included selecting all that apply, as DOTs use multiple methods. Figure 18 shows that the top five methods that state DOTs have used for tracking their construction stormwater management compliance are as follows:

  • Site investigations (38 of 42 DOTs, 90%)
  • Field logs and databases (33 of 42 DOTs, 79%)
  • Photographs and videos (31 of 42 DOTs, 74%)
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
The horizontal axis is labeled number of D O T responses and ranges from 0 to 50. The vertical axis lists methods for tracking construction stormwater compliance. Site investigations are used by 90 percent of respondents, field logs and databases are reported by 79 percent, photos and videos by 74 percent, field applications used on smartphones and tablets by 45 percent, internal software systems are used by 24 percent, proprietary software systems by 12 percent, and off-the-shelf software systems by 10 percent. Seven percent report that no standardized methodology is used statewide, and 14 percent report using other methods.
Figure 18. Methods for tracking construction stormwater compliance (N = 42).
  • Field applications on smartphones and tablets (19 of 42 DOTs, 45%)
  • Internal software system (10 of 42 DOTs, 24%)

Some responding state DOTs selected “Other.” One DOT uses standardized inspection forms to track its construction stormwater management compliance. In contrast, another DOT uses highly customized, off-the-shelf software for tracking construction stormwater compliance.

The survey respondents were asked to identify all methods used to monitor the performance of construction stormwater management requirements; respondents were allowed to choose all selections that apply, as some DOTs use more than one method. Figure 19 summarizes the results of this question. Of 42 responding state DOTs, 35 (83%) have an inspection of control measures in place; 33 (79%) have conducted regular site investigations; 20 (48%) constantly review control measures; and 16 (38%) have used their internal audits to monitor the performance of construction stormwater management requirements.

Additionally, from the “Other” selections, one responding state DOT uses a proprietary software program that contains quality controls such as picture documentation to monitor the performance of construction stormwater management requirements. Another DOT reported: “the DOT has contractors perform inspections per the general construction permit, and we do audits of the projects per our MS4 permit. Innovative contracts may have additional quality assurance/quality control requirements built into the contract.”

The horizontal axis is labeled number of D O T responses and ranges from 0 to 50. The vertical axis lists methods used to monitor the performance of construction stormwater management. Inspection of control measures in place is reported by 83 percent of respondents. Regular site investigations are used by 79 percent, constant review of control measures by 48 percent, internal audits by 38 percent, audits performed by consultants are used by 14 percent, using performance metrics by 12 percent, and other methods by 10 percent.
Figure 19. Monitoring performance of construction stormwater management (N = 42).
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
The horizontal axis is labeled number of D O T responses and ranges from 0 to 30. The vertical axis lists timeframes for correcting inspection deficiencies. Less than 5 days is reported by 40 percent of respondents, 5 to 10 days by 36 percent, 11 to 15 days by 5 percent, and 16 to 20 days by 2 percent. Seventeen percent report other timeframes.
Figure 20. Time to correct an inspection deficiency (N = 42).

Figure 19 also shows that 5 of 42 responding state DOTs (12%) have used performance metrics to monitor their construction stormwater management requirements. The main performance metrics used by these four DOTs include the following:

  • Regular intervals for inspecting control measures and BMPs (4 of 4 DOTs, 100%)
  • Number of control measures and BMPs in place (3 of 4 DOTs, 75%)
  • Percentage of time the project is in non-compliance with stormwater permit requirements (3 of 4 DOTs, 75%)
  • Amount of time used to remedy deficiencies (2 of 4 DOTs, 50%)

When an inspection deficiency of construction stormwater occurs, state DOTs often take less than 2 weeks to correct it, as the timeline for correcting deficiencies is typically a requirement included in contract documents. Figure 20 shows that, of 42 responding state DOTs, 17 (40%) take fewer than 5 days to correct deficiencies found in an inspection, while 15 (36%) take 5–10 days to correct an inspection deficiency of construction stormwater.

Furthermore, seven responding state DOTs selected “Other” for this question. One DOT mentioned that, if sediment from a deficiency has already entered receiving waters or the department’s right-of-way, the deficiency must be addressed within 24 hours. Another DOT reported that “deficiencies are listed as low-, medium-, or high-priority. Low-priority must be addressed within 7 calendar days, medium-priority within 3 days, and high-priority within 24 hours.”

Construction Stormwater Management Audits

Audits of construction stormwater management are detailed inspections by internal DOT personnel (internal audits) or third-party agencies or firms (regulatory audits) to help ensure that construction stormwater practices and associated BMPs and E&SC measures adhere to all permit requirements. In the survey, state DOTs were asked about the frequency of audits performed, and each response included selecting all that apply. As shown in Figure 21, of 40 responding state DOTs (two responding state DOTs did not answer this question), 17 (43%) indicated that internal audits have been conducted annually or as needed, and 5 (13%) have internal audits when revisions to federal and state permit and regulatory requirements occur. In relation to regulatory audits, 20 DOTs (50%) are subject to them as needed; 8 (20%) have been involved in audits of their construction stormwater management program every 4 to 5 years; and 6 (15%) are subject to regulatory audits annually.

Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
The horizontal axis is labeled number of D O T responses and ranges from 0 to 30. The vertical axis lists audit frequencies for construction stormwater management implementation. Each category contains two bars representing regulatory audits and internal audits. For the category every 10 years or more, 5 percent report regulatory audits and 0 percent report internal audits. For every 4 to 5 years, 20 percent report regulatory audits and 0 percent report internal audits. For every 2 to 3 years, regulatory audits are reported by 3 percent and internal audits by 3 percent. Annually, regulatory audits are reported by 15 percent and internal audits by 43 percent. For as needed, regulatory audits are 50 percent and internal audits are 43 percent. Federal and state requirements are cited by 5 percent for regulatory and 13 percent for internal audits. Other frequencies are reported by 8 percent for both regulatory and internal audits.
NOTE: For the “Every 10 years or more” category, 0% refers to internal audits. For the “Every 4-5 years" category, 0% refers to internal audits.

Figure 21. Audits of construction stormwater management implementation (N = 40).

From the “Other” responses, one DOT mentioned that “the internal audit of contractors per project is every 30 days. Our regulating agency typically audits our projects at about 12 per year.” Two DOTs indicated that the regulatory agency determines the frequency of audits of construction stormwater management programs.

Finally, survey respondents were asked whether their DOTs had been fined for non-compliance with construction stormwater management requirements. Of 42 responding state DOTs, 22 (52%) indicated that they had been fined for non-compliance or stormwater discharge issues within the past 10 years.

Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
Page 19
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
Page 20
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
Page 21
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
Page 22
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
Page 23
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
Page 24
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
Page 25
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
Page 26
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
Page 27
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
Page 28
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
Page 29
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
Page 30
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
Page 31
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
Page 32
Suggested Citation: "3 State of the Practice Survey." National Academies of Sciences, Engineering, and Medicine. 2025. Construction Stormwater Program Management, Tracking, Reporting, and Compliance. Washington, DC: The National Academies Press. doi: 10.17226/29051.
Page 33
Next Chapter: 4 State DOT Case Examples
Subscribe to Email from the National Academies
Keep up with all of the activities, publications, and events by subscribing to free updates by email.