Previous Chapter: 4 CASE STUDIES
Page 111
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

CHAPTER 5. CHANGE ORDER ANALYSIS

INTRODUCTION

This chapter summarizes the results of an analysis of sample change order data the research team received from state DOTs. As part of the practitioner survey (see Appendix A), respondents were asked whether their agency could provide a copy of change order and claim databases to the research team. For DOTs that responded on the affirmative, the research team followed up with emails and formal requests through official channels, including open-record requests.

Table 42 shows a list of change order and claim data that was available for the analysis. The table also includes entries for data the research team had received as part of previous research efforts going back to the late 2000s. Per NCHRP’s request, DOTs are identified by case numbers (not by name) to anonymize the discussion and results. Analyzing data from all 11 cases in detail was not feasible, so the research team focused on six cases (1, 2, 5, 6, 8, and 9), which covered a wide range of change order record practices and styles.

Table 42. Change Order and Claim Data Received from State DOTs.

Case Data Period Number of Records Data Included
1 Change orders 2010–2022 1,364 Description, approval date, and amount.
2 Change orders 2010–2022 4,225 Description, reason, date of approval, amount, and status.
Claims 2008–2021 130 Description, date of acceptance, amount, status, and last event.
3 Change orders1 2008–2013 21,405 Description, amount, date of approval, item description, and contract information provided, but no change order reason codes.
4 Change orders 12,585 Description, amount, type, and number of days added; date stamps not included.
5 Change orders 2007–2021 11,659 Description, status, remarks, and dates.
6 Supplemental agreements 2007–2022 19,912 Description, justification, decision date, and amount.
Claims 2007–2022 9,151 Description, status, compensation requested and granted, time requested and granted, and claim date.
7 Change orders 2007–2021 46,893 Change order date stamps not included.
8 Change orders 2011–2021 237 Description, amount, and date of approval.
9 Change orders 2001–2022 104,540 Codes, explanation, amount, days allowed, and date of approval.
Claims 1996–2021 177 Description, amount accepted, and date of acceptance.
10 Change orders 2019–2022 211 Description, items, reason, approval date, and amount.
11 Change orders1 2008–2013 78 Change order date stamps not included.

1 Data the research team received as part of previous research efforts going back to the late 2000s.

Page 112
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

METHODOLOGY TO CLASSIFY UTILITY-RELATED CHANGE ORDERS

The research team classified individual change order records as one of the following (regardless of what the reason code indicated):

  • UR: UR records were those for which the research team had a high-level of confidence the change order was UR.
  • NUR: NUR records were those for which the research team had a high-level of confidence the change order was NUR.
  • Utility-related suspected (URS): URS records were those for which the research team suspected the change order was UR, but the change order description was not sufficiently clear.
  • Non-utility-related suspected (NURS): NURS records were those for which the research team suspected the change order was NUR, but the change order description was not sufficiently clear.

The research team used three different methodologies to classify change orders:

  • Use commonly used UR terms.
  • Review the description and justification columns to assess whether the change order was UR, NUR, URS, or NURS. This methodology also included classifying UR change orders according to a list of nine potential disaggregated reasons.
  • Use AI models to detect trends and patterns that could indicate a change order was UR or NUR. Chapter 6 includes a detailed description of the methodology and results of this analysis. After using the AI models, the research team reviewed individual records to validate or, if necessary, change the label the AI tools predicted. The research team also used the AI models to augment the list of commonly used UR terms. In practice, the research team used the AI-generated list of commonly used UR terms to filter change orders and accelerate the review process. In turn, the research team used the result of the manual review of individual change order description and justification columns to augment the list of terms.

Commonly Used UR Terms

The research team prepared a dictionary of commonly used one-word and two-word UR terms based on the thousands of records from Cases 1, 2, 5, 6, 8, and 9 (Table 43). The dictionary of one-word UR terms includes 60 entries. The dictionary of two-word UR terms includes 148 entries. The research team also considered three-word UR terms, but the predictive power of these terms was low.

Page 113
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

Table 43. Commonly Used One-Word and Two-Word UR Terms.

One-Word Terms Two-Word Terms

Abandon

Abandoned

Abandonment

Adjustment

Asbestos

Betterment

Box

Cabinet

Cable

Casing

Circuit

Communication

Conductor

Conduit

Conflict

Coordination

Delay

Diameter

Discovered

Ductile

Easement

Electric

Exploratory

Fiber

Gravity

Handhole

HDPE1

Installation

Iron

Line

Manhole

Meter

Optic

Overhead

Petroleum

Phone

Pipe

Pipeline

Pole

Post

Power

Relocate

Relocating

Relocation

Removal

Repair

Sanitary

Service

Sewer

Sewerline

Splice

Television

Trenching

Trenchless

Underground

Utility

Valve

Vault

Water

Waterline

Abandon existing

Abandon utility

Abandonment existing

Adjustment manhole

Adjustment meter

Adjustment water

Asbestos assessment

Bore jack

Broad band

Concrete pole

Conductor cable

Conduit dia

Conduit system

Copper line

County water

Directional bore

Discovered existing

Ductile iron

Due utility

Electrical conduit

Electrical service

Encasement pipe

Existing conduit

Existing fiber

Existing line

Existing manhole

Existing pipe

Existing sanitary

Existing sewer

Existing utility

Existing valve

Existing water

Existing waterline

Exploratory digging

Fiber optic

Fire hydrant

Force main

Force sewer

Gas line

Gas service

Gas system

Gravity sewer

Guy wire

HDPE pipe

Hydrant relocation

Inch water

Inch waterline

Insertion valve

Installation waterline

Iron pipe

Iron sewer

Iron water

Iron waterline

Item power

Junction box

Line relocation

Main sewer

Manhole adjustment

Manhole located

Manhole type

Manhole valve

Meter relocation

Meter valve

New water

New waterline

Optic cable

Optic line

Overhear utility

Pipe casing

Pipe fitting

Pipe installation

Pipe line

Pipe removal

Power line

Power service

Public utility

Pull box

PVC pipe

PVC sewer

Relocate existing

Relocate water

Relocating existing

Relocation existing

Relocation water

Relocation waterline

Rigid electrical

Remove utility

Sanitary gravity

Sanitary sewer

Service installation

Sewer cleanout

Sewer facility

Sewer force

Sewer lateral

Sewer line

Sewer manhole

Sewer pipe

Sewer relocation

Sewer service

Sewer system

Sewer utility

Single conductor

Sleeve valve

Steel casing

Steel encasement

Television cable

Trenchless install

Trenchless installation

Underground utility

Utility adjustment

Utility agreement

Utility company

Utility conflict

Utility construction

Utility coordination

Utility delay

Utility department

Utility exploration

Utility line

Utility location

Utility manhole

Utility owner

Utility pipe

Utility plan

Utility pole

Utility relocation

Utility service

Utility work

Valve adjustment

Valve box

Valve installed

Valve located

Valve manhole

Water facility

Water line

Water main

Water meter

Water pipe

Water service

Water sewer

Water system

Water valve

Waterline conflict

Waterline installation

Waterline installed

Waterline relocation

Waterline work

Wood pole

1 HDPE: High-density polyethylene

Page 114
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

The research team used several metrics to analyze change order records using the commonly used terms. One of the metrics was the number of times a change order description mentioned UR terms. Another metric was the number of change orders that mentioned UR terms, regardless of the number of times a change order mentioned a UR term. At first, it appeared the first metric could be a more reliable indicator of the usage of individual UR terms because it might suggest how important UR terms were for the DOT officials completing change order descriptions. In the end, the second metric, which was simpler to conceptualize and calculate, was just as effective in measuring the usage of UR terms. To normalize the metric, the research team defined relative usage of UR terms as follows:

R e l a t i v e = N u m b e r o f U R c h a n g e o r d e r s t h a t m e n t i o n e d t h e t e r m T o t a l n u m b e r o f c h a n g e o r d e r s t h a t m e n t i o n e d t h e t e r m

Relative usage is an indicator of the predictive power of a term. As the relative usage increases, so does the predictive power of the term. For example, if the term “sewer” has a 100 percent relative usage, what it means is that a thorough review of all change orders that mentioned the term “sewer” were indeed UR that only UR change orders included that term.

Disaggregated Reasons for UR Change Orders

The research team used the results of the practitioner survey, as described in Chapter 3, to prepare a list of potential reasons for UR change orders. This list was more disaggregated than what DOTs normally use (e.g., DSCs, utility delays, or errors in plans and specifications). Table 44 shows the list of nine disaggregated reasons, along with a corresponding description.

As a reference, 23 CFR 635.109 has three standardized changed condition clauses in highway construction projects (unless prohibited by state law or if a DOT has developed or implemented one or more of those clauses):

  • DSCs.
  • Suspensions of work ordered by the engineer.
  • Significant changes in the character of work.

One of the disadvantages of labeling a change order as DSC is that the risk of missing or masking the actual reason behind a change order increases considerably. If a more disaggregated list of reasons is not available, a change order might be labeled as DSC even though the cause was, for instance, that information about existing utilities was inadequate, a utility owner relocated its facility to the wrong place, or the PS&E documents had errors. As the research team reviewed individual change order records, an important focus was to find the actual reason behind the change order, regardless of whether the change order was originally labeled as DSC.

Page 115
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

Table 44. Disaggregated List of Reasons for UR Change Orders.

Reason Description
Changes initiated by project owner, contractor, or utility owner UR changes to the construction scope of work, resulting from a request by the project owner, contractor, or utility owner to improve the project. A typical situation is when the project owner or the contractor identifies a better design option than what the PS&E package includes. Another typical situation is when the contractor identifies a better construction method that results in economic or time savings.
Delays acquiring or clearing the right-of-way or utility relocation sites Delays or other impacts the contractor experiences resulting from delays in the acquisition or clearing of the right-of-way. It also includes delays or impacts if the utility relocations are delayed because the right-of-way was not cleared or acquired on time.
Delays getting utility owners to schedule utility relocations Delays or other impacts the contractor experiences resulting from delays in utility relocations caused by utility owners.
Differing site conditions DSCs the contractor encounters compared to what the contractor expected to find based on the available project documentation. This category does not include inaccurate or deficient utility relocation work, inaccurate or incomplete data about utility facilities, or errors and omissions in PS&E, which are listed below as separate reasons.
Difficult or inadequate constructability of highway work or utility relocation Impacts the contractor experiences resulting from constructability issues related to highway work affecting utility facilities or constructability issues related to utility relocations.
Inaccurate or deficient utility relocation work Impacts the contractor experiences resulting from inaccurate or deficient utility relocation work. A typical situation is when a utility owner relocates its facility to a location different from what was approved or causes damage to a highway feature, resulting in a construction issue.
Inaccurate or incomplete data about existing or relocated utility facilities Impacts the contractor experiences resulting from inaccurate or incomplete data about existing or relocated utility facilities. This category includes data about abandoned facilities and obsolete utility location data that were not updated prior to letting. A typical situation is showing incorrect locations or attributes for existing or relocated utility facilities.
Errors and omissions in PS&E Impacts the contractor experiences resulting from errors in PS&E documentation, information the PS&E package should have included but did not, or lack of design compliance with a specification or an industry standard. A typical situation is missing bidding codes or utility work for utility relocations that are included in the highway contract. Another example is impacts resulting from project owner survey errors.
Other Impacts the contractor experiences due to other reasons.

CASE 1

The change order database included 1,364 records from 2007 to 2022. It included contract number, description, change order number, approval date, and amount. According to state officials, the 1,364 records correspond to change orders for which the primary cause was a utility issue. The change order database had a brief description column (on average, 4 words per change order, with a range of 1–36 and a standard deviation of 3). However, the DOT often uses acronyms in the description column. Spelling out the acronyms would have the effect of increasing the average number of words per change order.

Page 116
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

The DOT uses four-letter codes to classify change orders. The first character corresponds to the change order type and can be one of eight codes (e.g., A for contract or supplemental work or B for acceleration). The second character corresponds to the specification or asset affected by the change order and can be one of 25 codes (e.g., C for different site conditions or L for utility). The third and four characters correspond to the source of the document that created the need for the change order and can be one of 43 codes (e.g., PV for utility plans or SB for standard specifications). The database the research team received did not include the four-letter codes, but it is reasonable to assume all or most records had L in the second code or PV in the third and fourth codes.

For the analysis, the research team used the description column to examine each record in the database. Of the 1,364 records in the database, the research team had to assume that all the records were UR records because there was not a practical way to prove the opposite. Using the change order reasons in the database, the research team prepared Table 45, which shows the number and percentage of UR change orders for each disaggregated change order reason.

Table 45. Case 1: Reasons for UR Change Orders.

Disaggregated Change Order Reason Number of Change Orders %
Errors and omissions in PS&E 458 33.6%
Inaccurate or incomplete data about existing or relocated utility facilities 334 24.5%
Changes initiated by project owner, contractor, or utility owner 143 10.5%
Differing site conditions 45 3.3%
Difficult or inadequate constructability of highway work or utility relocation 45 3.3%
Inaccurate or deficient utility relocation work 30 2.2%
Delays acquiring or clearing right-of-way or utility relocation sites 27 2.0%
Delays getting utility owners to schedule utility relocations 20 1.4%
Other 262 19.2%
Total 1,364 100%

Change orders classified as other were challenging because the description column did not provide much valuable information to assess what the actual UR reason for the change order was. Examples of those descriptions were as follows:

  • Additional funds.
  • Delineators.
  • Irrigation controller various locations.
  • Place additional inductive loops.
  • Water connection and capacity fees.

Labeling records as inaccurate or incomplete data about existing or relocated utility facilities was also challenging because the change order description did not normally include wording confirming this reason. As a strategy to deal with this issue, the research team assumed that if a utility facility was a “high-priority” facility, the DOT probably commissioned a test hole during the design phase to confirm the X-Y-Z coordinates of the facility. High-priority facilities include:

Page 117
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
  • Natural gas pipelines larger than 15 cm (6 in) in diameter or with an operating pressure greater than 414 kPa (60 psi).
  • Petroleum pipelines.
  • Pressurized sanitary sewer pipelines.
  • High-voltage electric supply lines, conductors, or cables of at least 60 kV.
  • Pipelines transporting hazardous materials.

Other utility facilities are not high-priority facilities and, therefore, the probability of having a test hole to confirm their coordinate would have been low. The DOT normally does not use quality level B (QLB) utility investigations during the design phase. This means that for low-priority facilities, the level of uncertainty regarding their location is high (or at least higher compared to the level of uncertainty associated with high-priority facilities). Consequently, the research team assumed that change orders that involved low-priority facilities (unless the change order already pointed to another reason) would be labeled as inaccurate or incomplete data about existing or relocated utility facilities.

The research team also conducted an analysis of the frequency of single-word terms and two-word terms. Because the research team did not receive a complete database of change orders, it was not possible to calculate the relative usage of UR terms. Table 46 shows the 15 most frequently used one-word terms and the 15 most frequently used two-word terms.

Table 46. Case1: Most Frequent UR Change Order Terms.

One-Word Term Number of Records Two-Word Terms Number of Records
Line 260 Water line 256
Water 231 Utility conflict 230
Utility 137 Sewer line 137
Sewer 115 Gas line 115
Waterline 76 Relocate water 76
Relocate 74 Water meter 74
Conflict 53 Sanitary sewer 53
Pipe 50 Existing line 48
Relocation 45 Fiber optic 45
Manhole 43 Relocation water 43
Valve 38 Utility location 38
Repair 28 Water valve 28
Abandon 26 Line relocation 26
Meter 26 Sewer system 26
Adjustment 21 Sewer manhole 21

CASE 2

The change order database included 4,225 records from 2010 to 2022. The change order database had a brief description column (on average, 12 words per change order, with a range of 1–36 and

Page 118
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

a standard deviation of 3). The DOT uses change order reasons such as DSCs, utility delays, plan or specification errors, plan or specification differing interpretations, time or schedule, right-of-way, and urgent need. The data includes several other change order reasons (e.g., added work, added funds available, alterations to contract, change basis of payment, conformity to the contract, and contract issues) as well as variations of the same reasons (e.g., utility delay, utility delays, and delays).

For the analysis, the research team used both the description and change order reason columns to examine each record in the database. Of the 4,225 records in the database, the result was 197 (4.7 percent) UR records, 3,044 (72.0 percent) NUR records, 81 (1.9 percent) URS records, and 903 (21.4 percent) NURS records. The number of URS and NURS records was high because the description column was too short to enable a reliable classification of those records as UR or NUR.

Using the change order reasons in the database, the research team prepared Table 47, which shows the number and percentage of UR change orders. Because of variations in change order reason naming conventions and spelling, the research team grouped the results into five meaningful categories of change order reasons.

Table 47. Case 2: UR Change Order Classification.

Grouped Change Order Reasons Number of Change Orders %
Delays, utility delays, or time or schedule 64 32.5%
Differing site conditions 59 29.9%
Plan or specification errors, design errors and omissions, or material changes/out of specifications 44 22.3%
Other, urgent need, alterations to the contract, phasing plan, or contract issued 19 9.6%
Local agency request 11 5.6%
Total 197 100%

Using the list of disaggregated change order reasons in Table 44, the research team also prepared Table 48. Although the numbers and percentages changed, using disaggregated reasons did not really help to uncover more information compared to what the DOT’s list of change order reasons already provided. The small number of words in the change order descriptions (four words on average) precluded a more detailed analysis.

Page 119
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

Table 48. Case 2: Disaggregated Reasons for UR Change Orders.

Disaggregated Change Order Reason Number of Change Orders %
Differing site conditions 66 33.5%
Delays getting utility owners to schedule utility relocations 63 32.0%
Errors and omissions in PS&E 51 25.9%
Changes initiated by project owner, contractor, or utility owner 14 7.1%
Inaccurate or incomplete data about existing or relocated utility facilities 2 1.0%
Other 1 0.5%
Total 197 100%

The research team also conducted an analysis of the relative usage of single-word terms and two-word terms. Table 49 shows the one-word terms that had the highest relative usage. Two-word terms were not particularly effective because of the small number of words in the change order description column. Some two-word terms were mentioned a few times, including fiber optic, line relocation, water relocation, utility relocation, and water line. Utility delay was the most common UR two-word term (although this term was already one of the standard change order reasons the DOT uses).

Table 49. Case 2: Strongest UR Change Orders Predictors.

One-Word Term Relative Usage
Conflict 100%
Ductile 100%
Phone 100%
Valve 100%
Waterline 100%
Utility 93%
Optic 89%
Relocation 79%
Fiber 78%
Power 70%
Relocate 63%
Delay 57%
Sanitary 56%
Manhole 55%
Sewer 52%

CASE 5

The change order database included 11,659 records from 2007 to 2021. It includes contract number, change order number, dollar amount, description, and remarks. The DOT does not use reason codes. The change order database had detailed description and remarks columns

Page 120
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

(combined on average, 130 words per change order, with a range of 4–1,825 and a standard deviation of 112). The remarks column usually included the list of modified items and the reason for that change.

For the analysis, the research team used both the description and remarks columns to examine each record in the database. Of the 11,659 records in the database, the result was 460 (3.9 percent) UR records, 10,199 (87.5 percent) NUR records, 21 (0.2 percent) URS records, and 979 (8.4 percent) NURS records. The percentage of records classified as NURS was high compared to other states. Most of the records grouped as NURS included a list of items with final quantities (i.e., quantities that were measured during construction), which made it difficult to decide whether the change order was UR.

Using the list of disaggregated change order reasons in Table 44, the research team prepared Table 50, which shows the number and percentage of UR change orders for each disaggregated change order reason.

Table 50. Case 5: Reasons for UR Change Orders.

Disaggregated Change Order Reason Number of Change Orders %
Errors and omissions in PS&E 231 50.2%
Inaccurate or incomplete data about existing or relocated utility facilities 65 14.1%
Changes initiated by project owner, contractor, or utility owner 44 9.6%
Differing site conditions 29 6.3%
Delays getting utility owners to schedule utility relocations 20 4.3%
Difficult or inadequate constructability of highway work or utility relocation 18 3.9%
Inaccurate or deficient utility relocation work 7 1.5%
Delays acquiring or clearing right-of-way or utility relocation sites 3 0.7%
Other 43 9.4%
Total 460 100%

In most cases, the description and remarks columns were sufficient to decide whether a change order was UR. However, several records lacked clear information to enable a reliable classification. In other cases, the change order did not mention the reason, but listed the modified items, which enabled the research team to make a reasonable assumption about the proper classification for those change orders. Several change orders showed a list of items adjusted to final quantities in the description, but the description did not include more information. For those change orders, the research team decided to classify them as errors and omissions in PS&E, but it is possible that in some cases the actual reason might have been different.

In an effort to speed up the classification process, the research team filtered change orders using the list of one-word terms and two-word terms (Table 43). However, this approach was not particularly effective because change orders often included different terms to name the same structure or feature.

Page 121
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

The research team also conducted an analysis of the relative usage of single-word terms and two-word terms. Table 51 shows the one-word terms and two-word terms that had the highest relative usage.

Table 51. Case 5: Strongest UR Change Orders Predictors.

One-Word Term Relative Usage Two-Word Term Relative Usage
Waterline 98% Abandon utility 100%
Sanitary 95% Bore jack 100%
Sewer 92% Encasement pipe 100%
Relocating 71% Existing waterline 100%
Valve 70% Gravity sewer 100%
Manhole 70% Guy wire 100%
Utility 69% Installation waterline 100%
Underground 65% Iron sewer 100%
Vault 60% Iron waterline 100%
Relocation 57% New waterline 100%
Conflict 54% PVC sewer 100%
Asbestos 53% Relocation waterline 100%
Pipeline 50% Sewer lateral 100%
Relocate 48% Sewer manhole 100%
Optic 42% Sewer service 100%

CASE 6

The research team received a supplemental agreement database, which included 19,912 records, and a claim database, which included 9,151 records (of which 6,613 records corresponded to approved claims). Both databases included records from 2007 to 2022. The DOT uses supplemental agreements to amend the contract in situations where there are changes such as work requirements, unit prices, additional work items, or contract times. The DOT uses claims in situations where the contractor requests additional compensation or a time extension. Contractors can submit claims either during the life of the contract or after the construction ends. A review of records from both databases revealed that most records corresponded to situations that other DOTs would handle by using change orders. For completeness, the research team processed each database separately but then combined the results to enable an aggregated comparison with other cases.

The supplemental agreement database had a high-level of detail in the description and justification columns (combined on average, 199 words per supplemental agreement, although the range was 3–4,937 words and the standard deviation was 171). This database did not include change order reason codes. The claim database also had detailed descriptions, although the number of words per claim was lower than the number of words for supplemental agreements (43 words per claim on average, range of 3–337, and standard deviation of 23).

Page 122
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

For the supplemental agreement database, the research team used both the description and justification columns to examine each record in the database. Of the 19,912 records in the database, the result was 2,624 (13.2 percent) UR records, 17,256 (86.7 percent) NUR records, 27 (0.1 percent) URS records, and 0 (0.0 percent) NURS records. The number of URS and NURS records was low (and the percentage was lower than for Case 2) because the description column was sufficiently long to enable a reliable classification of change order records as UR or NUR.

For the approved claim database, the research team used both the claim description and the issue description columns. Of the 6,613 records in the database, the result was 884 (13.4 percent) UR records, 5,729 (86.6 percent) NUR records, 0 (0.0 percent) URS records, and 0 (0.0 percent) NURS records.

Using the list of disaggregated change order reasons in Table 44, the research team prepared Table 52, which shows the number and percentage of UR supplemental agreements, Table 53, which shows the number and percentage of UR claims, and Table 54, which shows the combined results, for each disaggregated change order reason.

Table 52. Case 6: Reasons for UR Supplemental Agreements.

Disaggregated Change Order Reason Number of Supplemental Agreements %
Errors and omissions in PS&E 978 37.3%
Changes initiated by project owner, contractor, or utility owner 622 23.7%
Inaccurate or incomplete data about existing or relocated utility facilities 461 17.6%
Differing site conditions 141 5.4%
Difficult or inadequate constructability of highway work or utility relocation 137 5.2%
Delays getting utility owners to schedule utility relocations 92 3.5%
Inaccurate or deficient utility relocation work 73 2.8%
Delays acquiring or clearing right-of-way or utility relocation sites 36 1.3%
Other 84 3.2%
Total 2,624 100%

Table 53. Case 6: Reasons for UR Claims.

Disaggregated Change Order Reason Number of Claims %
Delays getting utility owners to schedule utility relocations 295 33.4%
Errors and omissions in PS&E 182 20.6%
Inaccurate or incomplete data about existing or relocated utility facilities 115 13.0%
Difficult or inadequate constructability of highway work or utility relocation 49 5.5%
Changes initiated by project owner, contractor, or utility owner 40 4.5%
Differing site conditions 32 3.6%
Delays acquiring or clearing right-of-way or utility relocation sites 23 2.6%
Inaccurate or deficient utility relocation work 14 1.6%
Other 134 15.2%
Total 884 100%
Page 123
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

Table 54. Case 6: Reasons for Combined UR Supplemental Agreements and Claims.

Disaggregated Change Order Reason Number of Claims %
Errors and omissions in PS&E 1,160 33.1%
Changes initiated by project owner, contractor, or utility owner 662 18.9%
Inaccurate or incomplete data about existing or relocated utility facilities 576 16.4%
Delays getting utility owners to schedule utility relocations 387 11.0%
Difficult or inadequate constructability of highway work or utility relocation 186 5.3%
Differing site conditions 173 4.9%
Inaccurate or deficient utility relocation work 87 2.5%
Delays acquiring or clearing right-of-way or utility relocation sites 59 1.7%
Other 218 6.2%
Total 3,508 100%

In most cases, the description and justification columns were adequate to decide whether a supplemental agreement or claim was UR. Nevertheless, the process was tedious and time consuming. Despite using single-word terms and two-word terms to accelerate the process, it was necessary to read the description and justification columns carefully in search of the one sentence in the middle of the description and/or justification entries that included the critical piece of information.

The description and/or justification columns for some supplemental agreements was particularly challenging, which needed further discussions within the research team. A typical example of this type of situation was the following:

[The] waterline is not in conflict with construction but was disturbed by nearby pavement removal operations. The City requested the relocation of a new waterline and encasement pipe to safeguard against future maintenance issues.

In this case, the waterline was not in direct conflict with the highway construction, but it was affected by pavement removal operations nearby. At first, it appeared that the pavement removal occurred outside of the construction area or the project limits (maybe as part of a local project). The city’s request to relocate the existing waterline and encasement pipe would mean the supplemental agreement would be classified as changes initiated by project owner, contractor, or utility owner. However, it is also possible the pavement removal occurred elsewhere within the project limits, in which case the waterline would have been in conflict with the project (although not in conflict at the specific location where the city requested to relocate the waterline and encasement pipe). If so, a more appropriate reason would have been inaccurate or incomplete data about existing or relocated utility facilities.

The research team also conducted an analysis of the relative usage of single-word terms and two-word terms. Table 55 shows the one-word terms and two-word terms that had the highest relative usage.

Page 124
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

Table 55. Case 6: Strongest UR Supplemental Agreement Predictors.

One-Word Term Relative Usage Two-Word Term Relative Usage
Sewerline 100% Insertion valve 100%
Sanitary 98% Sewer lateral 100%
Waterline 97% Gravity sewer 99%
Sewer 97% Relocation waterline 99%
Betterment 94% Waterline relocation 99%
Manhole 92% Sanitary gravity 99%
Valve 92% Sanitary sewer 99%
Ductile 88% PVC sewer 99%
Abandonment 86% Existing sanitary 99%
Exploratory 85% Sewer relocation 98%
Utility 82% Sewer manhole 98%
Vault 76% Waterline conflict 98%
Trenchless 74% Inch waterline 98%
Abandon 71% Iron waterline 97%
Water 70% Existing sewer 95%

CASE 8

The change order database included 237 records from 2011 to 2021. It included item description, approval date, dollar amount, and explanation. The 237 records received correspond to change orders that included references to utility delays in the description or explanation columns (i.e., records having one of the following keywords: “*UTILITY DELAY*,” “*Utility Delay*,” or “*utility delay*”). The description and explanation columns included a detailed description of the change orders (combined on average, 247 words per change order, although the range was 29–1,203 words and the standard deviation was 30).

For the analysis, the research team used the item description and explanation columns to evaluate each record. Using the list of disaggregated change order reasons in Table 44, the research team prepared Table 56, which shows the number and percentage of UR change orders for each disaggregated change order reason.

Page 125
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

Table 56. Case 8: Reasons for UR Change Orders.

Disaggregated Change Order Reason Number of Change Orders %
Delays getting utility owners to schedule utility relocations 99 41.8%
Changes initiated by project owner, contractor, or utility owner 42 17.7%
Errors and omissions in PS&E 31 13.1%
Inaccurate or incomplete data about existing or relocated utility facilities 23 9.7%
Differing site conditions 14 5.9%
Difficult or inadequate constructability of highway work or utility relocation 13 5.5%
Inaccurate or deficient utility relocation work 3 1.3%
Delays acquiring or clearing right-of-way or utility relocation sites 2 0.8%
Other 10 4.2%
Total 237 100%

It is not surprising that the highest number of records was associated with delays getting utility owners to schedule utility relocations. The reason is that all records received from the DOT were already filtered since they included the term “utility delay.” In most cases, the explanation column included a detailed description of activities, as well as the party responsible for decreasing the impact of the delay. Many of the records described other necessary activities because the delay triggered additional winter-related delays or stoppages.

Although all the records had a utility delay filter, a substantial number of records had content in the description column that pointed to a different reason, suggesting in those cases that utility delay was an effect, not a cause. An example was a change order in which the contractor found that the vertical clearance of some existing aerial electrical cables would be insufficient during the construction of a bridge. The contractor could not proceed until the issue was resolved. In the end, it became necessary for the utility owner to re-route electrical circuits and deenergize the line in question. Although there was a delay, the issue that caused the delay during construction was not identified during the design phase.

In other cases, utility delay was not even an effect. An example was a change order in which the contractor found a utility facility that was not mapped during design, causing a redesign of parts of the drainage system. In this case, it was not necessary to relocate the utility facility.

The research team also conducted an analysis of the frequency of single-word terms and two-word terms. Because the research team did not receive a complete database of change orders, it was not possible to calculate the usage of UR terms. Table 57 shows the 15 most frequently used one-word terms and the 15 most frequently used two-word terms.

Page 126
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

Table 57. Case 8: Most Frequent UR Change Order Terms.

One-Word Term Number of Records Two-Word Terms Number of Records
Utility 237 Utility delay 237
Delay 237 Utility plan 237
Pipe 79 Utility work 208
Water 72 Due utility 169
Line 71 Utility construction 94
Removal 66 Utility department 92
Relocate 39 Existing utility 67
Relocation 28 Remove utility 66
Installation 22 Utility line 48
Pole 21 Utility location 42
Adjustment 20 Existing line 39
Sewer 16 Utility pipe 28
Cable 14 Water line 27
Conflict 14 Existing water 25
Service 12 New water 23

CASE 9

The change order database included 104,540 records from 2000 to 2023. It included project number, change order number, approval date, change order amount, reason codes, description, and remarks. Users can assign up to three reason codes per change order (primary, secondary, and tertiary) depending on the number of changes included in the change order. The change order database had a high-level of detail in the description and remarks columns (combined on average, 242 words per change order, although the range was 1–5,123 words and the standard deviation was 181).

For the analysis, the research team used the reason codes and the description and remarks columns. The procedure to classify records as UR or NUR consisted of two phases. First, the research team extracted 2,790 change orders with right-of-way or UR reason codes and then added change orders that had reason codes associated with incorrect PS&E, third party requests for additional work, and additional work desired by the DOT. The reason for adding these change orders was that a preliminary analysis showed a considerable number of them were UR. The result of the first phase was a subset of 19,100 change orders. For each record, the research team reviewed the description and remarks columns to decide whether the change order was UR or NUR. At the end of this first phase, 3,945 records were classified as UR.

Second, the research team used AI models to accelerate the review of the remaining 85,440 change order records in the database. The process to review every single record manually in the 19,100-record subset was tedious and time consuming, and completing the classification of the remaining records by hand would have taken several months. Chapter 6 describes the process to select, train, and validate the AI models. This pre-classification enabled the research team to

Page 127
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

review the description and remarks columns faster. For the 85,440 change orders, the result after the review was 3,512 UR records and 81,928 NUR records.

In total, of the 104,540 records in the database, the result was 7,457 (7.1 percent) UR records and 97,083 (92.9 percent) NUR records. The amount of information was sufficient to classify the change orders, which made it unnecessary to use the URS or NURS labels.

Using the list of disaggregated change order reasons in Table 44, the research team prepared Table 58, which shows the number and percentage of UR change orders for each disaggregated change order reason. Table 58 shows results for 6,037 of the 7,457 UR change orders.

Table 58. Case 9: Reasons for UR Change Orders.

Disaggregated Change Order Reason Number of Change Orders %
Errors and omissions in PS&E 1,929 32.0%
Inaccurate or incomplete data about existing or relocated utility facilities 1,696 28.1%
Delays getting utility owners to schedule utility relocations 732 12.1%
Changes initiated by project owner, contractor, or utility owner 554 9.2%
Difficult or inadequate constructability of highway work or utility relocation 180 3.0%
Differing site conditions 165 2.7%
Delays acquiring or clearing right-of-way or utility relocation sites 129 2.1%
Inaccurate or deficient utility relocation work 128 2.1%
Other 524 8.7%
Total 6,037 100%

The description and remarks columns were usually sufficient to classify change orders. However, some change orders included just a short sentence without any further explanation. In these cases, the research team used the reason codes (and their definition) to classify the change order. If this information did not provide enough context, the research team classified the change order as other.

The research team also conducted an analysis of the relative usage of single-word terms and two-word terms. Table 59 shows the one-word terms and two-word terms that had the highest relative usage.

Page 128
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

Table 59. Case 9: Strongest UR Change Orders Predictors.

One-Word Term Relative Usage Two-Word Term Relative Usage
Waterline 94% Insertion valve 100%
Sanitary 92% Sanitary gravity 100%
Ductile 86% Waterline conflict 94%
Utility 84% Hydrant relocation 94%
Valve 81% Sleeve valve 92%
Abandonment 75% Abandon utility 92%
Pipeline 75% Gas line 90%
Vault 74% Utility conflict 90%
Conflict 57% Utility delay 89%
Exploratory 56% Installation waterline 88%
Abandon 55% Waterline installation 88%
Abandoned 54% Inch waterline 88%
Betterment 54% Existing waterline 87%
Casing 52% Encasement pipe 87%
Sewerline 50% Fire hydrant 87%

GENERAL TRENDS

The total number of UR change orders for the six cases was 11,803. For each case, Table 60 shows the percentage of UR change orders per disaggregated change order reason. The table also shows the overall average for all cases.

Table 60. Percentage of UR Change Orders per Disaggregated Change Order Reason.

Disaggregated Change Order Reason Case 1 Case 2 Case 5 Case 6 Case 8 Case 9 Average1
Errors and omissions in PS&E 33.6% 25.9% 50.2% 33.1% 13.1% 32.0% 32.7%
Inaccurate or incomplete data about existing or relocated utility facilities 24.5% 1.0% 14.1% 16.4% 9.7% 28.1% 22.8%
Changes initiated by project owner, contractor, or utility owner 10.5% 7.1% 9.6% 18.9% 17.7% 9.2% 12.4%
Delays getting utility owners to schedule utility relocations 1.4% 32.0% 4.3% 11.0% 41.8% 12.1% 11.2%
DSCs 3.3% 33.5% 6.3% 4.9% 5.9% 2.7% 4.2%
Difficult or inadequate constructability of highway work or utility relocation 3.3% 0% 3.9% 5.3% 5.5% 3.0% 3.7%
Inaccurate or deficient utility relocation work 2.2% 0% 1.5% 2.5% 1.3% 2.1% 2.2%
Delays acquiring or clearing right-of-way or utility relocation sites 2.0% 0% 0.7% 1.7% 0.8% 2.1% 1.9%
Other 19.2% 0.5% 9.3% 6.2% 4.2% 8.7% 9.0%
Total 100% 100% 100% 100% 100% 100% 100%

1 Average percentage was calculated using the total number of UR change orders for each disaggregated change order with respect to the overall total of UR change orders.

Page 129
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

The results in Table 60 point to two major groups of reasons behind UR change orders:

  • Reasons behind a substantial number of UR change orders (79 percent in total):
    • Errors and omissions in PS&E (33 percent).
    • Inaccurate or incomplete data about existing or relocated utility facilities (23 percent).
    • Changes initiated by project owner, contractor, or utility owner (12 percent).
    • Delays getting utility owners to schedule utility relocations (11 percent).
  • Reasons behind a small number of UR change orders (21 percent in total):
    • DSCs (4 percent).
    • Difficult or inadequate constructability of highway work or utility relocation (4 percent).
    • Inaccurate or deficient utility relocation work (2 percent).
    • Delays acquiring or clearing right-of-way or utility relocation sites (2 percent).
    • Other (9 percent).

This differentiation has significant ramifications for the identification of potential strategies for implementation. First, except for utility relocation delays caused by utility owners (12 percent of UR change orders), most reasons that cause a substantial number of UR change orders are reasons that a DOT can control, specifically, errors and omissions in PS&E (33 percent) and inaccurate or incomplete data about utility facilities (23 percent). These two reasons account for 56 percent of UR change orders.

Second, most reasons behind a substantial number of UR change orders are reasons that a DOT could address prior to letting, which highlights the importance of conducting utility investigations and identifying and resolving utility conflicts during the preliminary design and design phases. Overall, the results in Table 60 show that pursuing these two strategies systematically could have a positive impact on 60–80 percent of UR change orders.

As expected, for DOTs where the change order description was sufficient (i.e., Cases 1, 5, 6, 8, and 9), the number of UR change orders the research team classified as DSCs was low. For those states, the research team could determine the actual reason behind the change order (even if the DOT had originally classified the change order as a DSC). This result is significant because it could point to many cases in which a change order might be classified as a DSC for convenience or because the official in charge did not have more meaningful categories to choose from, but the actual reason was completely different.

Other reasons listed in Table 60 also had a small number of UR change orders. One of those reasons was difficult or inadequate constructability of highway work or utility relocation. It is likely that one of the main reasons is that the number of complex utility relocations is low in most projects and that highway contractors are often able to predict complex situations while preparing the bid for the project. Likewise, the number of UR change orders attributed to delays acquiring or clearing right-of-way or utility relocation sites was low. Reasons include that DOTs often acquire all the necessary parcels before the project is let and that highway contractors know about the pending parcels while preparing the bid and plan their sequence of work accordingly.

Page 130
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.

The number of UR change orders under the category of inaccurate or deficient utility relocation work was low. Most change orders under this category were the result of damage the utility contractor caused to new or existing highway infrastructure or situations in which the utility contractor placed a utility facility at a location different from what the approved plans showed. It is worth noting that change orders do not reflect the case where a utility facility was placed incorrectly but the resulting impact did not translate into a change order.

The research team also examined yearly variations in the number and percentage of UR change orders. As expected, trends varied from state to state. Unfortunately, it was not possible to draw meaningful conclusions from these observations. In some cases, the data the research team received included estimated project costs, but not letting dates. In addition, critical relevant information was not available to the research team, such as potential changes in change order recording practices or potential changes in utility process management practices.

Readers should be aware of caveats associated with individual databases, which makes the comparison among databases more challenging. For example:

  • Case 1: The 1,364 records correspond to change orders for which the primary cause was a utility issue. The database did not include a change order code.
  • Case 2: The change order database contained 4,225 records, including UR and NUR records. However, change order descriptions were too short to enable a reliable classification.
  • Case 5: The change order database contained 11,659 records that included short descriptions and long remarks. However, the remarks column included mainly a list of modified items.
  • Case 6: The change order database contained 19,912 records with a high-level of detail in the description and justification columns. This database did not include change order reason codes.
  • Case 8: The change order database contained 237 records that included references to utility delays in the description or explanation columns.
  • Case 9: The change order database contained 104,540 records with highly detailed descriptions and reason codes. Change orders included up to three reason codes.
Page 111
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 111
Page 112
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 112
Page 113
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 113
Page 114
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 114
Page 115
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 115
Page 116
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 116
Page 117
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 117
Page 118
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 118
Page 119
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 119
Page 120
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 120
Page 121
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 121
Page 122
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 122
Page 123
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 123
Page 124
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 124
Page 125
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 125
Page 126
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 126
Page 127
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 127
Page 128
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 128
Page 129
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 129
Page 130
Suggested Citation: "5 CHANGE ORDER ANALYSIS." National Academies of Sciences, Engineering, and Medicine. 2024. Strategies to Address Utility Issues During Highway Construction. Washington, DC: The National Academies Press. doi: 10.17226/27859.
Page 130
Next Chapter: 6 CHANGE ORDER CLASSIFICATION USING AI
Subscribe to Email from the National Academies
Keep up with all of the activities, publications, and events by subscribing to free updates by email.