Previous Chapter: 1 Background
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
  • Chapter 4 identifies and describes a methodology framework and components that owners can use to integrate risk analysis into their project development, procurement and execution processes to effectively allocate, communicate and manage project risks.
  • Chapter 5 presents practitioner feedback on the proposed methodology framework and components.
  • Chapter 6 presents the team’s overall conclusions and recommendations regarding further research.

This report also includes appendices consisting of reference documents, survey and interview results, glossaries of key methodology components, and sample contract language addressing key project risks.

A standalone Guide deliverable presents the final methodology and tools and practices to promote competition and effectively manage or mitigate risks across the full project lifecycle.

The final research products include a Memorandum discussing an implementation plan. Presentation Slides will document the overall Research Effort.

2 Literature Review

This chapter presents a summary of the pertinent documents collected as part of the literature review. As the literature in area of risk assessment, allocation, and management is vast, the team focused its review on the following general categories of documents:

  1. Reports and guidance related to APD methods, including:
    1. Documents published by US Federal Highway Administration (FHWA), state Departments of Transportation (DOTs), and industry organizations such as DBIA,
    2. Relevant research reports published by NCHRP and other academic sources, and
    3. Reports and articles addressing insurance and surety issues, particularly for large, complex projects using APD methods.
  2. Procurement and contract documents from projects using APD methods in the US, as well as term sheets and standard template contracts available from state DOTs and professional organizations (e.g., AIA, Consensus Docs, DBIA, etc.)

The following subsections identify and discuss the key documents that directly informed the team’s subsequent identification and development of the methodology components.

2.1 Reports and Guidance Documents

2.1.1 Reports and Guidance related to APD Methods published by FHWA and State DOTs

Over roughly the last decade, FHWA has collected a variety of information and published various reports related to “innovative” project delivery with an emphasis on P3s. FHWA’s Center for Innovative Finance has produced a suite of reports and model contract guides that have some relevance to this project:

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
  1. The FHWA Center for Innovative Finance’s suite of primers and reports are focused on various aspects of P3s. These cover the fundamentals of P3s and serve as an important resource for individuals or organizations lacking experience in this project delivery approach. For instance, those without knowledge of Value for Money (VfM) assessments and concepts can use the primer on this topic to enhance their understanding. The primer on risk assessment in P3s serves the same purpose and provides guidance on risk allocation. (FHWA 2013)
  2. The model contract guides cover a number of issues and risks prevalent in P3s. Moreover, they supply example contract language for treating these issues and risks. Accordingly, they serve as a baseline for contractual design and language that public agencies can reference for P3 term sheets or template contracts; if desired, public agencies could modify these model provisions to suit their own context. (FHWA 2014, FHWA 2015)
  3. The Contracting Alternatives Suitability Evaluator (CASE) webtool (ICF 2021; D’Angelo et al. 2018) is a resource developed by FHWA to support the selection of the most appropriate APD method with consideration of a project’s risk profile, goals, and characteristics among other considerations.

Overall, this body of literature provides resources and guidance for the implementation of P3s.

2.1.2 NCHRP Reports

Strategies and tools to identify and mitigate geotechnical risks are thoroughly addressed in NCHRP Report 884 Guidelines for Managing Geotechnical Risks. (Gransberg et al. 2018) For example, the report recommends including, as part of the procurement documents, an initial Geotechnical Baseline Report (GBR), which will then evolve through procurement and award to a final GBR and the inclusion of a Differing Site Conditions (DSC) clause in contractual provisions. The GBR together with the DSC provides a mechanism for cost and time relief to the Contractor if actual conditions differ materially from those shown in the GBR. Further, the strategies proposed can be generalized to more overarching ones such as:

  • Early identification and assessment of project risks,
  • Consideration of APD methods as a means to address and mitigate project risks, and
  • Incorporation of enhanced contractual provisions or mechanisms to more effectively address project risks.

Contractual provisions from actual projects and recommendations for addressing specific risks were reported in NCHRP Legal Research Digest 86: Managing Enhanced Risk in the Mega Project Era. (Gad 2022) The report includes various provisions and recommendations regarding risks and risk allocation. For example, one finding related to environmental approvals was that if an Environmental Impact Statement (EIS) is required for the project because environmental impacts are expected to be significant, contractors may be hesitant to participate in construction projects, particularly if the project will require an EIS, due to the uncertainties associated with the NEPA process until the Record of Decision (ROD) is issued. An EIS requires a higher level of design and may take more than two years to complete on average.

The risk management framework presented in NCHRP Research Report 658: Guidebook on Risk Analysis Tools and Management Practices to Control Transportation Project Costs (Molenaar 2010) discusses several risk management tools such as Delivery Decision Support, risk registers, and “risk maps” that were

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

considered by the 23-22 research team as it developed the recommended methodology components discussed in Chapter 4.

NCHRP Research Report 939 Guidebooks for Post-Award Contract Administration for Highway Projects Delivered Using Alternative Contracting Methods recommends various practices and tools to address risks during the planning and implementation of projects using DB (Molenaar et al. 2020a) and CM/GC (Molenaar 2020b). The report recommendations expand the typical scope of risk management tools to include organizational and administrative practices.

Table 2.1 lists the top 12 risks that impact transportation cost estimates as identified in NCHRP Research Report 1025 Contingency Factors to Account for Risk in Early Construction Cost Estimates for

Transportation Infrastructure Projects (Jeong et al. 2022). This risk ranking is instructive as it is very recent, and it largely correlates with the key risks identified through the subsequent survey effort conducted as part of this NCHRP 23-22 research effort (as discussed further in Chapter 3). Exceptions included environmental permitting and ROW acquisition, both of which were rated among the top 5 risks by respondents to the NCHRP 23-22 survey but are not identified in NCHRP Report 1025.

Table 2.1: Risks Impacting Transportation Cost Estimates from NCHRP Research Report 1025 (Jeong et al. 2022)

Ranking Risk Description
1 Utility issues (e.g., utility conflicts and relocation of identified utilities)
2 Poor or incomplete project scope definition during the scoping phase
3 Unexpected geotechnical issues (e.g., inadequate geotechnical investigation results, poor soil conditions, unsound subgrade conditions, large boulders contained in existing soils, or adverse groundwater conditions)
4 Design changes (e.g., changes in a bridge foundation type or redesign of a drainage facility, changes in design standards, exceptions to design standards, or inaccurate design assumptions)
5 Constructability issues (e.g., problems with construction sequencing, staging, or phasing)
6 Contractor availability and competition (e.g., lack of competition due to project size)
7 Railroad involvement (additional requirements because of proximity to a railroad)
8 Market conditions (e.g., a shortage of local contractors, labor, or material)
9 Late changes requested by stakeholders
10 Project duration-related issues (e.g., scheduling errors, inaccurate contract time estimates, restricted working windows for some activities, or issues with aggressive schedules)
11 Errors in cost estimating
12 Funding availability

Current research project NCHRP 10-115 is underway to develop a Guide on Progressive DB for Transportation Projects to assist DOTs with project planning and selection, project implementation, procurement, pricing procedures, and contract administration.

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

2.1.3 State DOT Guidelines and Reference Documents

Selected guidelines or manuals from state DOTs were examined to understand the activities that DOTs follow in planning, developing, procuring, and executing projects using APD methods. Specifically, the review of the guidelines/manuals focused on the extent to which risk management practices and tools for APD methods were addressed. Risk management practices and tools in the following 11 broad areas were examined:

  1. Process for project delivery selection
  2. Process for risk identification, analysis and assessment
  3. Development and utilization of a risk register
  4. Identification of baseline activities or responsibilities for typical risks in transportation projects such as site conditions, utilities, etc.
  5. Identification of pre-procurement industry forums or meetings
  6. Issuing RFP for industry review and feedback during procurement
  7. Identification of baseline RFP components such as instructions to proposers (ITP), reference information documents (RIDs).
  8. Identification of industry one-on-one meetings for input and feedback during procurement
  9. Identification of an alternate technical concept (ATC) process
  10. Identification of project implementation/execution processes such contract administration, and
  11. Identification of relational contracting methods such as partnering during project implementation

A search of all state DOT websites (as well as the Territory of Puerto Rico) for readily available guidelines or manuals related to CM/GC, DB and P3 was conducted. Twenty-two DB, nine CM/GC and six P3 guidelines/manuals were found during this search. A listing of these manuals including website links is provided in Appendix A.

DB Guidelines and Manuals

The majority of the guidelines/manuals included a description or overview of practices and tools. Interestingly, the CDOT manual (2016a) included a comparison of DBB, DB and CM/GC for “primary evaluation factors” and “project risks”, which provide high-level considerations for these APD methods while illustrating CDOT’s perspectives of how certain risks should be addressed for each method. CDOT also employs a “Project Delivery Selection Matrix” for selecting among DBB, DB and CM/GC.

Most guidelines/manuals also included baseline activities or responsibilities for typical risks in transportation projects. GDOT’s manual (2022a) addressed multiple pre-procurement activities for a project such as: (a) Concept Layout and Concept Report, (b) Costing Plans, (c) Value Engineering Study, and (d) Environmental Document and Permits; it also addressed actions related to typical risks such as contaminated materials, ROW, and utilities. For example, GDOT addresses “Geotechnical Investigation” as follows:

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

GDOT typically obtains as much geotechnical investigation data as possible prior to the RFP advertisement and provide this data as information only to Proposers in order to minimize risk(s) associated with subsurface conditions. GDOT will also typically provide to Proposers as information only all existing and readily available soils reports, [Bridge Foundation Investigations] or [Wall Foundation Investigations] from prior projects that were in the Design-Build project’s vicinity. GDOT will not typically provide interpretive reports except for the final pavement design. If feasible, Proposers may be allowed to perform additional borings during procurement to further minimize risk.

This describes what type of geotechnical data GDOT will provide as well as its purpose (i.e., it is NOT interpretive) in its DB RFPs. Consequently, this establishes a baseline for geotechnical investigations for all involved parties.

Some manuals were less explicit about particular practices or tools. For instance, the manuals from MNDOT (2019), TxDOT (2017) and VDOT (2022) mention practices related to risk identification, analysis, and assessment, but these are not described in detail. The two areas with the least coverage were project implementation practices and relational contracting methods; generally, these areas were beyond the scope of the associated manuals (i.e., the manuals did not go beyond the procurement and award phase of a project).

Overall, the DB manuals reviewed provide a good depiction of the project preparation and procurement activities that state DOTs will follow for fixed price DB. In doing so, they signal to the industry in general and to prospective proposers specifically how they will typically conduct their affairs and business for DB projects, which assists in establishing protocols and expectations for all involved parties.

CM/GC Guidelines and Manuals

While CM/GC guidelines/manuals were less prevalent, the CDOT (2016b) and GDOT (2023) manuals were examined to contrast the information provided with that found in their DB manuals. In both states, certain areas of the DB and CM/GC manuals are comparable. They all address processes for project delivery selection and risk identification, analysis, and assessment in a similar fashion.

However, the CM/GC manuals have a different trajectory beyond these initial project preparation activities. Both the CDOT and GDOT CM/GC manuals then describe how they will conduct procurements for a CM/GC project; GDOT’s manual describes procurement activities for a Designer of Record (DOR), CM/GC and Independent Cost Estimator (ICE) while CDOT’s focuses on the procurement of a CM/GC; CDOT’s manual identifies and describes roles and responsibilities of a Design Consultant and ICE, but it does not include details about procurement of their services. Both manuals also describe practices for industry engagement during procurement such as pre-proposal meetings/industry forums and one-onone meetings with prospective proposers.

The balance of the CDOT and GDOT CM/GC manuals focus on these principal areas: (1) preconstruction phase services and responsibilities, (2) project cost processes and establishing the construction price, and (3) construction phase services and responsibilities. These sections of the manuals describe roles and responsibilities, activities and processes in each area, details about developing the price for the project – the “Negotiated Construction Price (NCP)” for GDOT and the “Agreed Contract Price (ACP)” for CDOT – and other details such as DBE participation and dispute resolution.

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

Notably, both manuals discuss employing “risk pools”. The GDOT Manual describes risk pool items identified in the executed risk register; for risk pool items, the CM/GC is not at risk for increases in the Negotiated Construction Price (NCP). The CDOT Manual gives more attention to risk pools and describes three separate risk areas: (1) Contractor Risk, (2) CDOT Risk Pool, and (3) Shared Risk Contingency Pool. Risks that are identified in a project’s risk register are ultimately allocated to one of these three risk areas.

For risks allocated as Contractor Risk, CDOT and the ICE will review contingencies that the CM/GC has assigned to items of work; if any contingencies are considered too high, then the parties can consider means to reduce risks contributing toward the contingencies or mitigate the risk by shifting it to either the Shared Contingency Risk Pool or the CDOT Risk Pool. The risks that are allocated to the CDOT Risk Pool are ones where CDOT is better positioned to manage the risk, the risk is beyond the control of the CM/GC, or the contingency assigned is too high.

The Shared Risk Contingency Pool are risks that “have a high amount of uncertainty, along with a high likelihood of occurring, but still have the potential for the Contractor to control.” The CM/GC proposes risks for inclusion in the shared pool along with the potential amount and a payment specification. If approved by CDOT, this becomes a “Project Special Provision”, and the CM/GC is paid per the payment specification if the risk is encountered. If the entire estimated amount for the risk is not recognized, then CDOT and the CM/GC share the savings as outlined in the special provision. The CDOT Manual further explains that the “Risk Register and Risk Pools is integral to the preparation of the Contractor’s Opinion of Probable Construction Cost (OPCC) and the [Contract Agree Price] Proposal. The Contractor and ICE are better able to prepare accurate estimates as project risks are identified and mitigated, and defining and establishing the Risk Pools allows the Contractor and ICE to remove contingencies from the bid items.”

P3 Guidelines and Manuals

Few DOTs currently maintain P3 Guidelines and Manuals on their websites. Manuals from Arizona DOT (2022), the Colorado High-Performance Transportation Enterprise (2020), GDOT (2022b) and PennDOT (2022) were examined to determine their content. (Note that the Colorado High-Performance Transportation Enterprise is now the Colorado Transportation Investment Office (CTIO)).

The overall structure of all four manuals was similar, although the level of detail provided varied. Each described:

  • Administration and general authority of the P3 unit,
  • Processes for the identification and selection of P3 projects,
  • Pre-procurement/project preparation activities,
  • Typical procurement processes, and
  • Evaluation and award processes.

Some of the features found in DB fixed price manuals were also present in the P3 Manuals. However, some issues specific to P3s were addressed. The process for handling unsolicited proposals was addressed in the ADOT, CTIO and PennDOT. GDOT does not have statutory authority to receive unsolicited proposals; therefore, it is not addressed in its manual. Additionally, ADOT, CTIO and PennDOT describe the use of Value for Money Analysis (VfM) as part of the assessment and selection process for a P3 project; VfM analyses are a common tool employed for this purpose, and FHWA has published a primer (FHWA 2014) about VfM assessments, which was previously discussed in Section 2.1.1 of this report. GDOT’s manual does not address VfM analysis, although it does consider the value added by the private sector in its P3 screening process.

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

Finally, ADOT and PennDOT address Pre-Development Agreements (PDAs), which is an approach for delivering a P3 where a public agency and a private developer enter into an agreement to shape and scope a P3 project (PDAs for P3s are also call “Progressive P3s”).

The balance of the manuals in each jurisdiction has comparable elements with those in the DB manuals reviewed such as descriptions of risk management processes, industry engagement pre-procurement and during procurement, and project implementation actions. The CTIO and GDOT manuals provide greater detail about their risk identification, analysis and assessment methods.

2.1.4 Additional DOT and Industry Documents

Term Sheets

Some DOTs provide term sheets that summarize key items for a typical or pending contract. TxDOT has published such a term sheet for its DB contracts, which it typically includes in its RFQs. The TxDOT DesignBuild Contract Term Sheet (TxDOT 2023a) organizes information into the following categories:

  • Contract Overview
  • Price, Security & Payments
  • Completion Deadlines, Schedule and Delay
  • Contract Rights & Responsibilities
  • Environmental & Performance Risks
  • Contract Changes & Costs Outside the Contract
  • Business Risks
  • Other Contract Provisions

Specific items are then addressed within each category. For example, “Contract Changes & Costs Outside the Contract” includes:

  • Differing Site Conditions
  • Supply Chain Disruptions
  • Third-Party Agreements
  • Railroads
  • Hazardous Materials
  • Utilities
  • Force Majeure Events
  • Other Relief Events

Within these categories, 66 items are addressed. For example, the “Third-Party Agreements” item states:

DB Contractor is entitled to a Change Order (a) to compensate DB Contractor for certain additional costs incurred and (b) to extend the applicable Completion Deadlines as the result of any delay in a Critical Path, directly caused by modifications to DB Contractor’s obligations resulting from new third-party agreements or modifications to existing third-party agreements. DB Contractor shall not be entitled to any relief for any new third-party agreements or modifications to existing third-party agreements unless the delays and the effects of such delays are beyond the control of the DB Contractor-Related Entities.

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

Except for project overhead to be calculated in accordance with the [Design-Build Contract] for each day that a Completion Deadline is extended, delay and disruption damages are not recoverable.

(See Other Relief Events section below for relief for modifications to draft third-party agreements included in the [Reference Information Documents] as of the proposal due date.)

To prospective DB contractors, this description provides a baseline understanding of how TxDOT intends to handle relief as a consequence of new third-party agreements or modifications to existing third-party agreements.

The Association for the Improvement of American Infrastructure (AIAI) has published “First Principals of Risk Allocation” (2024), which is essentially a risk allocation term sheet for P3s. This term sheet addresses issues such as “Undisclosed Geotechnical Conditions”, “Right-of-Way”, “Change in Law” and “Utilities”. The working document is described as a “consensus document” among private sector and public sector participants in P3s on key commercial terms that are broadly applicable to major P3 projects. It can serve as a guideline with recommendations for structuring contractual provisions to equitably allocate risks.

Template Contracts

Many state DOTs also publish template contracts. Like term sheets, these template contracts include the baseline provisions for prospective projects that a public agency will modify and adjust for a specific project. As is, they provide an indication of how particular issues and risks will be specified.

TxDOT has published such a template (TxDOT 2023b) that establishes the general conditions for a variety of issues and potential risks. For example, the provisions related to “Utilities” define multiple terms such as “Unidentified Utilities Deductible”, “Unidentified Utilities Deductible Cap” and “Utility Adjustment” while “Section 6.4 Utilities” addresses this item directly with multiple subsections: (a) 6.4.1 Unidentified Utilities, (b) 6.4.2 Public Utility Owner Delays, (c) 6.4.3 Pre-Proposal Commitments, and (d) 6.4.4 Advance Utility Relocations. The “Unidentified Utilities” (Section 6.4.1) states:

The “Unidentified Utilities Deductible” for the Project is, for each facility, the first $[•] of Basic Costs for the Utility Adjustment due to an Unidentified Utility.

The “Unidentified Utilities Deductible Cap” for the Project is an aggregate $[•] for all Unidentified Utilities Deductibles borne by DB Contractor.

[Applicable deductible and cap to be determined on a project-by-project basis. Such deductible and cap could each be “0”, if so determined by TxDOT.]

DB Contractor shall be entitled to a Change Order with respect to certain additional Direct Costs and delays relating to Utility Adjustments, as specified in Section 4.5 of the General Conditions and subject to the restrictions and limitations set forth in Section 4.5 of the General Conditions and in Section 4.6 of the General Conditions, unless otherwise specified in this Section 6.4.

[insert any deviations from the standard terms of the relevant General Conditions sections]

This provision uses a deductible scheme with a cap for adjustment of unidentified utilities although TxDOT may elect for both the deductible and cap to be zero.

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

VDOT also has published standard template documents for RFPs (VDOT 2016), which includes Part 3 – Lump Sum Agreement, Part 4 – General Conditions of Contract, and Part 5 – Division I Amendments to the Standard Specifications. These parts also establish baseline conditions and terms for DB projects. Part 4 includes VDOT’s “Scope Validation” provisions (Section 2.2 Scope Validation and Identification of Scope Issues); Section 2.2.1 Scope Validation Period states:

The term “Scope Validation Period” is the period of time that begins on Design-Builder’s receipt of Department’s Notice to Proceed and extends for one hundred twenty (120) days from such date of receipt, unless otherwise stated in Exhibit 1. During the Scope Validation Period, Design-Builder shall thoroughly review and compare all of the then-existing Contract Documents, including without limitation the RFP Documents and the Proposal, to verify and validate Design-Builder’s proposed design concept and identify any defects, errors, or inconsistencies in the RFP Documents that affect Design-Builder’s ability to complete its proposed design concept within the Contract Price and/or Contract Time(s) (collectively referred to as “Scope Issues”). The term “Scope Issue” shall not be deemed to include items that Design-Builder should have reasonably discovered prior to the Agreement Date.

Subsequent provisions in Section 2.2 describe requirements for seeking relief for any “Scope Issues” as well as how scope validation applies to non-accessible areas of the site during the validation period.

2.1.5 Insurance and Surety Industry Perspectives

Contracts for APD projects often shift greater risk to the private sector than do contracts on DBB projects. Sureties ultimately take on these risks if there is a default, and they pay attention to the contract risks—particularly on large and complex projects.

A recent 2021 study from insurance company Travelers examined 224 heavy civil building projects completed between 2004 and 2020 that had contract values between $250 million and $2 billion (Travelers 2021; Steele 2021). The projects encompassed bridge, highway, rail, tunnel and other large-scale civil work, and most were projects on which Travelers had been the surety or co-surety. For fixed-price DB or P3 contracts with bids based on approximate 30% designs, the Travelers study found that design-builders often underestimated the quantity risk and design risk they were assuming. These projects were not very successful for the DB or P3 consortiums, and in many cases, contractors did not even make back costs. Over the past 15 years, infrastructure projects greater than $250 million in contract value – especially bridge, highway, and transit work – have been the public construction industry’s worst performing segment for contractors, the study reported. One conclusion was that contractual risk transfer is an important driver of project performance for owners and contractors and certain risks must be shared and not simply shifted. It also concluded that CM/GC and/or Progressive DB models where the contractor and designer collaborate over an extended period of time to determine the final design and construction budget have produced the most consistent and best results for both the contractor and the owner.

The TCRP Legal Digest Issues Involving Surety for Public Transportation Projects (Loulakis 2012) provides insight into the significant role the surety industry plays for both owners addressing project packaging, delivery method, and risk allocation decisions, and industry’s capacity and risk appetite when deciding whether or not to pursue a large, complex project.

As discussed in the digest, a key factor influencing the surety underwriting process is the risk-shifting provisions of the bonded contract. Contractors are now working more closely with sureties in the initial

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

phases of a project (e.g., after publication of the RFP and during contract negotiation), which is the time sureties prefer to be brought in to review and negotiate key contract terms. As a signal of the sureties’ heightened contractual involvement and awareness of contractual risk, Zurich North America Surety recently developed a risk management department based upon the company’s perception that the majority of its losses in recent years could have been mitigated by more favorable contractual clauses. The surety will often focus on the following contractual provisions:

Table 2.2: Surety Perspectives on Contractual Provisions from TCRP Project J-5, Legal Research Digest 40 (Loulakis et al. 2012)

Provision Considerations
Payment
  • Are there any unique funding concerns that will raise issues for the contractor or JV’s cash flow?
Retention
  • Is there a corresponding decrease in the retainage withheld as the work in place increases?
  • Is the percentage of retention equitable?
Liquidated Damages
  • Is the proposed stipulated sum commensurate with the actual or projected damages the owner may incur?
  • Is there a cap on liquidated damages or some other provision that would act as a stop to prevent extended delays?
Limitation of Liability
  • Does the bonded contract contain an enforceable clause that clearly defines the maximum exposure that the contractor will be responsible for in the event of continuing defaults?
Hazardous Materials
  • Does the hazardous materials provision require the contractor to assume cleanup obligations and be considered a generator of pollution under federal hazards waste law?
  • If so, is the clause fair and reasonable so that the owner indemnifies for hazardous materials that are unknown?
Differing Site Conditions
  • If the bonded contractor encounters unforeseen soil conditions, does the owner assume the risk or does the contract make it difficult for the contractor to recover on such a claim? Typically, the means for reducing the risk of unforeseen conditions is through test borings. When an owner generates data and guarantees the accuracy of the interpretations, contractors encountering changed conditions will seek to have the owner liable for the representations.
Construction Specifications
  • Are the specifications performance or design specifications?
  • How does the bonded contractor view the level of detail and quality of the design documents—regardless of whether the project is delivered through DBB or DB?
Insurance
  • Do the requisite insurance provisions address the design component of a DB contract? In other words, is the surety adequately protected from design problems on a DB contract with the requisite design professional liability insurance?
  • Does the insurance provision adequately insure the contractor teams involved in the project?
Warranties / Performance Guarantees
  • What is the length and duration of the warranty period?
  • Is the warranty a standard 1 to 3 years (i.e., workmanship and materials), or does the warranty clause impose performance guarantees (i.e., 15 to 20 years)?
  • If it is a performance-type warranty, how is performance success measured and quantified?
  • Who are the parties contractually responsible for the performance guarantees if the contractor is a DB JV team?
  • Is the performance guarantee clause specific to the contractor or designer, assuming it is a DB project delivery method?

Other key provisions that the surety industry will be concerned with include substantial completion and closeout, default provisions, indemnification provisions, and bonding forms and provisions.

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

Another consideration for sureties, particularly with very large DB projects, is the lack of bonding capacity to cover the full value of mega-projects. Surety practices have historically been based on the conventional DBB method, where design and construction are performed by separate companies and where sureties have detailed designs completed for which they can more accurately assess the performance risks. On a DB project, the lack of detailed designs desired by sureties to evaluate project risk may make it difficult for sureties to offer performance bonds for the full value of the contract. This has led to decisions on several very large projects to allow for less than 100% bond amounts (in some cases 50% for performance bonds), alternative forms of security, or in some cases owners have descoped large contracts into smaller packages. Strategic contract packaging is done not only on DB or P3 projects, but also on conventional DBB projects.

In lieu of performance bonds, alternative forms of performance security used for P3s or mega-projects have included parent company guarantees (PCG), a Letter of Credit (LOC) from a financial institution or a combination of bonds for construction obligations and other forms of security for non-construction obligations (e.g., extended warranty/performance guarantees, design obligations, major equipment, and O&M obligations). LOC are bank instruments requiring payment on demand, and similar to bonds require payment of a fee as well as security to assure the bank that it will be repaid in the event of a call on the letter of credit. Due to the nature of LOC, it is a much simpler process to make a demand on a LOC than to enforce a surety bond.

A guarantee is a promise by a third party, typically a parent company or other affiliated entity, that the contractor will perform its obligations. In some cases, a performance guarantee is provided, giving the owner the right to require the guarantor to take over the contract. However, in most cases the guarantee does not include an agreement that the guarantor will in fact perform the work, but instead gives the owner the right to collect damages from the guarantor if the contractor fails to perform. One important difference between guarantees and bonds is that guarantees are provided by an affiliated entity for little or no additional cost to the owner, while bond premiums can be a significant project expense. One potential issue with guarantees is that, if the contractor has failed, there is also a likelihood that the guarantor will be in financial difficulty (Gad et al. 2022).

2.2 Procurement and Contract Documents

To complement the review of FHWA reports, NCHRP reports, and DOT guidelines and documents, procurement documents and contracts from active and completed DB, PDB, CM/GC and P3 projects were examined. These documents provided actual examples of how key risks are characterized, allocated and managed in ongoing projects, which is more direct evidence of whether processes or baseline conditions reported in guidelines and term sheets as well as recent research are being followed.

The review of the procurement documents and contracts from active APD projects enabled us to:

  • Assess how well procurement processes aligned with certain practices identified in APD manuals reviewed previously, and
  • Examine contemporary practices for handling and allocating risks in APD projects.
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

2.2.1 Design-Build (Fixed Price) Procurement Documents

Procurement documents for a variety of DB projects were collected and inventoried. Specifically, the RFPs for over 40 DB (fixed price) transportation projects with issue dates from 2000 through 2022 were collected. To qualify for further review, the RFPs had to include at least the Instructions to Proposers (ITP) and a draft contract/agreement that included the general conditions. From this subset, 20 DB projects from states that have been active in DB delivery were examined in two areas: (a) the extent to which particular practices found in DB manuals were followed, and (b) how 10 selected risks were treated. Significant findings are discussed in the following subsections.

Practices for Early Industry Engagement during Procurement

DB RFPs included practices for industry engagement during procurement, although some included more extensive interaction than others. Nearly half included a pre-proposal industry forum (9/20), but many relied primarily on the conventional RFI process for input and feedback. Most (16/20) included one-onone meetings during procurement although several only reserved the right to hold such meetings. A little more than half (12/20) included an ATC process. Notably, more recent RFPs were generally more inclusive compared to those issued earlier, incorporating most or all of these practices. These results suggest that industry engagement varies, perhaps depending on project size, and the transaction costs involved with such industry engagements may exceed their benefits for smaller projects.

Identification and Allocation of Key Risks

Based on input from the research team’s SMEs as well as the findings from the research reports and guidelines reviewed, the RFP documents from twenty DB projects were reviewed to identify key risk issues common to all projects and examine how the contract documents allocated these risks. The following key recurring risk areas were examined:

  • Geotechnical conditions
  • Differing site conditions (DSC)
  • Archeology or Protected Species
  • Utilities
  • Right-of-Way
  • Railroads
  • Hazardous Materials
  • Design
  • Warranties
  • Force Majeure

Key observations regarding risk allocation are summarized below.

Geotechnical Conditions: DOTs include geotechnical reports and data in RFP reference information. This information is provided in most of the RFPs for DB contractors to reference and use during proposal preparation. The DB Contractor must make its own investigation/interpretation of site conditions and geotechnical reference information, and not rely on accuracy or completeness of the reference information in preparing its proposal.

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

This practice does not align with recent recommendations from NCHRP Report 884 that recommends the public agency provide an initial Geotechnical Baseline Report (GBR) in the RFP that evolves through procurement and contract award to a final GBR as a reliance document. For one RFP reviewed (I405/SR167 Interchange Project, WSDOT 2015), the GBR was provided as the baseline defining “…geotechnical conditions against which actual geotechnical conditions encountered are compared for the purpose of determining if a Differing Site Condition exists” Alternatively, DOTs have compensated shortlisted proposers for performing additional pre-award site/geotechnical investigations or supplemental borings in contractor designated locations in return for waiving the rights to claim for a DSC. Similarly, VDOT has implemented a post-award Scope Validation Period where the selected DB contractor is provided a 120-day period to perform additional subsurface investigations, identify any defects, errors, and inconsistencies in documents, or changed subsurface conditions, which may result in a DSC with adjustments to the scope and budget. In return, the DB contractor is not entitled to any adjustment in the Contract Price and/or Contract Time(s) due to Differing Site Conditions identified after the Scope Validation Period.

Differing Site Conditions (DSC): Projects with federal funding are mandated to include a DSC clause. It is therefore unsurprising that 16 out of the 20 RFPs reviewed included DSC provisions.

DSCs generally address unforeseen subsurface conditions or concealed conditions that were not discovered during project development or preconstruction site investigations. Typical DSC clauses require several steps including timely notice to the owner, proof that a DSC exists, and that DSC could not have reasonably been avoided or mitigated. The owner will then determine whether a DSC is eligible for a change order or ask for additional information, and if eligible, will initiate a change order.

Several projects have implemented deductible schemes where the DB contractor is responsible for DSC costs up to a cap or deductible limit above which the owner compensates it for change orders for eligible DSCs. A shared deductible has been used where the DB contractor is responsible for DSCs up to a dollar limit, above which the owner and DB contractor share 50/50 in DSC costs to a specified limit. Alternatively, some DOTs are considering using an allowance scheme, whereby the owner may reimburse the DB contractor up to an allowance cap, above which, DSC costs and time are shared, or the owner compensates the DB contractor for eligible DSCs.

Archeology or Protected Species and Hazardous Materials: DOTs predominantly do not conduct survey investigations for archeology/protected species or hazardous materials and include these in the RFPs as Reference Information Documents (RIDs). This is likely because such conditions were not anticipated in most of these projects. In some cases, the DOT contract provisions require that the DB contractor perform a site investigation to determine the existence of these conditions. With appropriate notice and justification for impacts, they are generally treated as relief events, force majeure events, or DSCs.

Utilities: Less than half of the RFPs reviewed clearly indicated DOTs had completed or conducted prior coordination or agreements with utilities. Most RFPs required DB contractors to coordinate with utility owners regarding relocation although some made this a joint effort between the DB contractor and DOT. Generally, the costs for relocation fall to DB contractors, but for some “non-prior rights” utilities, particularly energy and telecom utilities, relocation responsibility was retained by the utility owner. Utility coordination and relocation was rated as a top risk in the recent NCHRP Report 1025. Overall, provisions related to utilities either transfer the coordination and relocation responsibilities to the DB contractor or share the coordination and relocation responsibilities in some way. One agency specified a shared risk

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

allowance in the contract for the relocation of public utilities (water and sewer) incentivizing the DB contractor to share in any unused allowance savings.

ROW: Responsibility for ROW acquisition varied in the contract documents. In half the project RFPs, DOTs were entirely responsible for ROW acquisition. This may entail the owner committing to a schedule for obtaining ROW parcels that would entitle the DB contractor to additional time or compensation for critical delay impacts. In three cases, ROW acquisition responsibilities including surveys, developing ROW plans, legal costs for condemnation, appraisals, and negotiations were transferred to the DB contractor to include in its price proposal. In seven project RFPs, ROW acquisition responsibilities and costs were shared in various ways between the DOT and DB contractor. Several documents specified that DB was responsible for acquisition and payment for additional ROW for its convenience/design changes.

Railroads: The risk of coordinating with railroads (RR) is retained by the DOT through prior owner coordination or agreements with the RR. The DB contractor has a duty to coordinate with RRs but has limited influence. RRs often will not commit to anything until they get final plans. Impacts related to late RR approvals or delayed work in the vicinity of a RR are typically treated as a relief event.

Design: The risk for design errors and omissions is transferred to the DB contractor; however, design reviews or lack of coordination of approvals by owner, third parties, or permitting agencies can delay advancement of the design.

Warranties: If a performance warranty is for a specified duration for items (i.e., pavement, bridge components, mechanical equipment, lighting, etc.), the DB contractor carries the risk that its warranty bond will be sufficient to cover the cost of annual routine and preventative maintenance or repairing or replacing any defective work during the warranty period.

Force Majeure: All the contracts reviewed included Force Majeure provisions for unusual events that cause temporary interruption or irrecoverable impacts on a project. Types of events are typically described as Acts of God or public enemies, Acts of war, rebellion or sabotage or damages resulting from, fires, floods, epidemics, explosions, riots or strikes. Force Majeure provisions generally provide relief in the form of a time extension (excusable, non-compensable delay) where neither the owner nor Contractor bears responsibility for event causing impacts. In theory, the risks are shared (i.e., a time extension provides relief from liquidated damages). In practice, the contractor’s actual damages may not be insured or recoverable. More recent contracts addressing Covid 19 have included both time impacts and recovery of certain delay-related costs up to a cap.

2.2.2 Progressive Design-Build Procurement Documents

Two recent PDB procurement documents were reviewed to examine their content. The RFQ/RFP for the I-10 Mobile River Bridge Project (ALDOT 2022) and the RFQ for the I-95 and Route 123 Interchange Improvements Project (VDOT 2022) were examined.

RFQ/RFP for the I-10 Mobile River Bridge Project preconstruction phase: A key objective was to select the DB contractor to work with ALDOT through a PDB arrangement in the preconstruction phase where the DB contractor “will work collaboratively with ALDOT to produce final designs and provide preconstruction services, including Subcontractor bidding and cost proposal development for the Construction Phase.” At the conclusion of the preconstruction phase, the DB contractor will submit a GMP proposal for construction

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

of the project. If ALDOT and the DB contractor reach agreement on the GMP proposal, then an amendment will be issued to proceed with construction.

Risks were managed as follows:

  • Geotechnical. The DB contractor is responsible for “determining geotechnical data and testing, performing geotechnical investigations, and performing tests, analyses, and calculations.” The RFQ/RFP includes Geotechnical Data Reports (GDRs) in the Reference Information Documents (RIDs), but the DOT does not expect proposers to conduct additional geotechnical explorations in order to submit a proposal.
  • Archeological: Investigations are underway by the DOT, but results are not expected to impact the project’s design or construction phases.
  • ROW: ROW acquisition is also underway, and the DOT has acquired most of the necessary parcels. It anticipates retaining responsibility for any remaining acquisitions; however, the DB contractor will be responsible for any additional ROW needed for its design solution.
  • Utilities: The DOT is responsible for utility coordination efforts/agreements, and the DB contractor will be responsible for utility relocations according to approved utility relocation agreements.
  • Hazardous Materials: A hazardous materials investigation report by the DOT is included in RIDs for the DB contractor to use to prepare its cost proposal.

In summary, ALDOT has begun various project preparation activities, disclosed certain reference information and the DB agreement term sheet, and provided expectations for the DB contractor for proposal submission and after execution of the agreement. The intent of preconstruction is to flesh out the anticipated risk issues and develop risk management and allocation strategies before the GMP proposal is made.

The I-95 and Route 123 Interchange Improvements Project: As part of VDOT’s first PDB project, the first step in a two-phase procurement; VDOT plans to short-list three DB contractors to receive the RFP for the project. The project will proceed in three phases – Phase 1A, Phase 1B and Phase 2. The RFQ describes the scope of work for the entire project for the DB contractor to include:

… all work required to support the design and construction of the following elements: (a) roadway, including alternatives development; (b) supplemental survey and utility test pits; (c) structure and/or bridge; (d) environmental, including NEPA Document support; (e) geotechnical; (f) hydraulics; (g) traffic engineering, including data collection, forecasting and analysis, including Intelligent Transportation System components (e.g., coordination with the Express Lanes systems); (h) transportation management plan; (i) right-of-way, including possible limited access line changes; (j) utilities, including coordination, adjustments, and relocations; (k) public involvement/stakeholder coordination; (l) quality assurance and quality control; (m) construction engineering and inspection; (n) project controls; and (o) overall Project management.

The RFQ explains that a detailed scope of work for Phase 1A would be identified in the RFP while the scope of work for Phase 1B will be jointly developed by VDOT and the DB contractor; and the DB contractor will submit a proposal near the end of Phase 1A. Phase 2 technical information and requirements will be developed by the DB contractor in consultation with VDOT. As noted above in the scope of work statement, the DB contractor will collaborate and assist VDOT with geotechnical investigations, NEPA, ROW and utilities among other aspects.

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

2.2.3 Construction Manager/General Contractor (CM/GC) Procurement Documents

Two recent CM/GC project procurement documents were examined for their content: the RFP for the I70 Floyd Hill to Veterans Memorial Tunnel Project (CDOT 2021) and the RFQ for the US-31 over Pine River Bascule Bridge Rehabilitation (MDOT 2022).

The RFP for CDOT’s I-70 project includes three main sections: (1) Scope of Work and Project Information, (2) CM Proposal Requirements and Instructions, and (3) Proposal Content and Evaluation Criteria. Several appendices are listed. Overall, the RFP is typical for such procurements. However, Appendix A to the RFP includes a “Preconstruction Roles and Responsibilities Matrix” that indicates that the CM will work with the Design Team to finalize. This matrix identifies tasks where the Contractor, the Design Consultant and CDOT/Others have primary responsibility, secondary responsibility or collaborative responsibility. For example, CDOT/Others has primary responsibility for ROW, specialty and local clearances while the Design Consultant has secondary responsibility; CDOT/Others has primary responsibility for utility coordination while both the Design Consultant and CM have secondary responsibilities. This matrix demarcates the initial plan for preconstruction responsibilities and coordination among the parties.

The RFQ for MDOT’s US-31 Bascule Bridge Rehabilitation includes seven main sections: (1) Introduction, (2) Background Information; RFQ Process, (3) Scope of Services, (4) Content of Statement of Qualifications, (5) Evaluation Process, (6) SOQ Submittal Requirements, and (7) Preconstruction Services Fee and Termination. Several attachments are listed. The RFQ is fairly typical. The Scope of Services section is instructive since it: (a) identifies a range of preconstruction services (including identification of constructability issues and provision of alternate design concepts); (b) describes the process for submission of a construction services cost proposal (CSCP) with three possible payment method areas: GMP, adjustable work and possibly contingency items; and (3) construction services that include construction responsibilities, quality control and bonding and insurance requirements. Areas such as utilities, geotechnical investigations, and ROW are not addressed; perhaps, this is a consequence of the scope of the project (bridge rehabilitation).

2.2.4 P3 Procurement Documents

Over roughly the last 15 years, several state agencies in the US have planned and implemented P3 arrangements for transportation projects that include various practices for risk allocation and sharing. Some of these practices have become market precedents while others have remained tailored to project characteristics or local conditions.

Recently, risk allocation practices were examined in multiple highway P3 projects where the principal source of data was the project contracts. A systematic methodology for analyzing the content of the contracts was developed; the results and methodology employed are described in Nguyen et al. (2018).

Table 2.3 summarizes how the risks identified were predominantly allocated in the contracts of the 26 P3 projects. The investigation uncovered whether these risks were: (a) retained by the public sector, (b) transferred to the private sector or (c) shared in some fashion between the parties; a risk was classified as being predominantly allocated if more than 80% of the contracts allocated it in the same way. Those without a predominant allocation were found to be mixed among the three classifications or roughly split between two classifications (as indicated in the table’s “Comments” column).

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

Table 2.3: Predominant Risk Allocation in Sample of US P3 Highway and Transit Projects

Risk Public Private Shared Comments
General
Financing X
Socio-political opposition and protesters X
Change in law X
Refinancing X
Inflation No Predominant Allocation Mixed among all three
Force majeure X
Interest rates pre-financial close No Predominant Allocation Public or shared
Construction
Design X
Right-of-Way & easements No Predominant Allocation Mixed among all three
Additional properties No Predominant Allocation Mixed among all three
Site geology/conditions X
Environmental risks X
Archaeology, fossils, or protected species X Recent contracts retained by public
Access and adjustment to utilities No Predominant Allocation Private or shared
Permits X
Environmental permits X
Commodity prices No Predominant Allocation Mixed among all three
Changes by the Public Authority No Predominant Allocation Public or shared
Performance X
Operations
Usage/demand risk X Retained by public in AP arrangements
Changes in transportation network X Retained by public in AP arrangements
Risk Public Private Shared Comments
Payment for services X
Availability and service X
Operation expenses X
Maintenance X
Latent defects No Predominant Allocation Private or shared
Changes in project ownership or structure X
Project Company default X
Termination by the Public Authority X
Hand-back X
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Risks Predominantly Retained by Public Sector

The public sector solely retained risks for usage/demand and network risks in availability payment P3s due to the characteristics of these arrangements. Most project risks related to financing, design, construction, and operation/maintenance were either shared or transferred to the private sector. This result confirms the overall risk transfer tenet of P3s.

The risks most frequently retained by the public sector are changes directed by the public authority. In these cases, the public agency assumed the impacts of adjustments after financial close in project scope or conditions that it directs.

Risks Predominantly Transferred to Private Sector

The principal risks over the life of a P3 project are transferred to the private sector: construction (design, performance), finance (financing, refinancing), operation (availability and service, operation expenses, maintenance), project company ownership (transfer) and hand-back (hand-back). Further, if the private entity elects to refinance the project, then it must bear this effort and cost; most contracts also required the private entity to share any refinancing gains with the public sector as illustrated by this provision from the Transform 66 contract in Virginia:

The Developer will pay to the Department 50% of any Refinancing Gain from a Refinancing that is not an Exempt Refinancing. The Refinancing Gain will be calculated after deducting payment of (i) the Department’s Allocable Costs under Section 7.08(e) and (ii) the Developer’s Allocable Costs directly associated with the Refinancing (Section 7.08d)

Project company ownership was also treated similarly across the contracts. Public agency scrutiny of the controlling stakes was made clear in the contractual transfer provisions. Although the Maryland I-495 contract is one of the earliest in the contract set, its provisions here were representative of the vast majority of the contracts:

From time to time during the term of this Agreement, the Concessionaire has the right, at its sole cost and expense, to pledge, sell or otherwise transfer solely the Toll Revenues available for Distribution in connection with a Permitted Securitization.

However, this right was limited by the public agency (Maryland I-495, Section 20.01):

The Concessionaire shall not Transfer, or otherwise permit the Transfer of, any or all of the Concessionaire’s Interest to or in favor of any Person (a ‘Transferee’) during the Lockup Period [the 10-year period commencing on the concession’s closing date and ending on the 10th anniversary of the closing date] and following the Lockup Period, the Concessionaire shall not Transfer, or otherwise permit the Transfer of, any or all of the Concessionaire’s Interest to or in favor of a Transferee, unless the Department has approved.

Risks Predominantly Shared

Many risks were predominantly shared between the public and private sectors as illustrated in Table 2.3. Several risks in the Construction category (site geology/conditions; environmental; archeology, fossils, or protected species; permits; environmental permits) were shared in some manner while some risks in the

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

General (sociopolitical opposition, change in law, force majeure) and Operations (network, project company default) categories were also shared.

By far, the most prevalent sharing approach was the event mechanism: relief events, delay events and compensation events (which some contracts referred to as “supervening events”). Relief or delay events usually extend a project’s construction schedule or its operations period, while compensation events typically involve monetary payment for damages incurred by a party. These event mechanisms are considered a sharing strategy since their relevant contractual provisions outline a process that the parties will follow once a qualifying event occurs to determine whether and what type of relief will be granted. In other words, once a risk materializes the parties will follow the relevant relief provisions in the contract to determine whether compensation and/or additional time will be granted; neither party knows at the time of contract formation (ex-ante) whether the related risk will surface, or which party will bear it. It could wind up being either (or both). Article 15 of the Ohio DOT’s Portsmouth Bypass contract stipulated a representative Relief Event procedure, which is long and complex but is summarized as follows:

  • The concessionaire must: develop a “time impact analysis”, prove that the event affected the project’s critical path, prove that the event could not be avoided by reasonable efforts, and provide evidence of the causes of the event.
  • The government then reviews the information and decides whether and how to grant relief.
  • If the concessionaire agrees with the government’s decision, then the decision is followed; if the concessionaire disagrees with the government, then the provision indicates:

    If the Parties cannot agree on the extent of any delay incurred or relief from Developer’s obligations under this Agreement, or the Department disagrees that a Relief Event has occurred (or as to its consequences), or that Developer is entitled to relief under this Article 15, the Parties shall resolve the matter in accordance with the Dispute Resolution Procedures. (ODOT, Portsmouth Bypass, Section 15.3).

While characteristic relief provisions have a variety of stipulations, these are procedural rather than categorical; hence, the parties will expend considerable effort ex-post to address and remedy the situation.

Another frequently used sharing approach was the deductible. A deductible is a specified quantity that a party must bear before it can ask for compensation or damages from the counterparty. For example, the Colorado Central 70 contract stated:

With respect to any Compensable Costs incurred by Developer in respect of any Relevant Event (other than any No-deductible Event, to which this Section 15.7.1 shall not apply) that occurs during the Construction Period, if the aggregate amount of such Compensable Costs directly resulting from the occurrence of such event is greater than $20,000 (any such event, a “Compensable Construction Period Event”), then, subject to Section 15.7.3, the Enterprises shall compensate Developer... (Section 15.7.1)

Other sharing methods were identified including indexing/escalating prices or rates, negotiation, and proportion/proration. For example, the Michigan I-75 Modernization contract provides an example of the proportion/proration sharing method that was employed for interest rates pre-financial close:

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

If Developer has complied with the submittal requirements under Section 5.7.4 of the ITP, MDOT will adjust the Base MAP to offset a portion of the impact of fluctuations (increases and decreases) in the Baseline Credit Spreads that have occurred during the Interest Rate Protection Period. Subject to the limitations described in Section 5.7.4 of the ITP and Schedule 18 (Update to the Base MAP), the credit spread risk/benefit sharing between MDOT and Developer will be implemented on an 85:15 basis, with MDOT assuming 85% of the fluctuation in Baseline Credit Spreads and Developer assuming 15%. (Section 3.7.2)

2.2.5 Summary of Common Contractual Risk Allocation Strategies

Table 2.4 below summarizes typical project risks and related risk allocation strategies (i.e., retain, transfer, share) that apply to large APD projects. The optimal risk allocation strategy will vary depending on a project risk assessment, the APD selected, the DOT’s ability to mitigate project risk in advance of execution, and industry’s risk appetite.

Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.

Table 2.4: Typical Project Risks and Allocation Strategies

Risk Contractual Risk Allocation/Sharing Strategies
Owner Retains Responsibility DB Contractor is Assigned Responsibility Shared Responsibility
Site Conditions (Geotech)
  • Unexpected geotechnical site issues
  • Inaccurate or incomplete geotechnical data and reference information (e.g., site surveys, soil samples, boring data, hydrological studies)
  • Owners obtain as much geotechnical information as possible in advance of advertising to minimize geotechnical risks.
  • Differing Site Conditions (DSC) provisions are universally used to address unforeseen subsurface or concealed conditions that were not discovered during project development or preconstruction site investigations. Typical DSC clauses require several steps including the contractor providing:
    • Timely notice to the owner, and
    • Proof that a DSC exists and could not have reasonably been avoided or mitigated by the contractor.
  • To determine the contractor’s entitlement to a change order, the owner may ask for additional information and will compensate the contractor for additional costs and time through the change order process as appropriate.
  • Current risk transfer practice is to include geotechnical reports and data in RFPs as reference information only. The information is provided for DB contractors to reference but the contractor must make its own investigation and interpretation of site conditions and geotechnical reference information and not rely on the accuracy or completeness of the reference information in preparing its proposal.
  • Some Owners have compensated shortlisted proposers for additional site/geotechnical investigations during procurement in return for waiving the contractor’s right to claim for a Type 1 DSC.
  • Owners have used deductible schemes where the DB contractor is responsible for costs up to a DSC deductible limit incurred for each separate DSC occurrence subject to a DSC aggregate deductible cap. Costs may be shared above the deductible cap or DB contractor is eligible for a change order for eligible DSCs above the cap.
  • Some owners are now using or considering using allowances, with the owner covering the allowance, and DB contractor picking up costs over the allowance amount (the inverse of having the contractor responsible for an initial deducible amount and the owner paying for costs above the deductible limit). The intent of such an allowance scheme is to incentivize contractors to be creative, given the potential impact that the DSC risk can have on designs.
  • Other owners (e.g., VDOT) are using or considering use of a post award scope validation period clause with caps to limit the contractor’s bidding risk for DSCs. The DB contractor is provided a period (e.g., 90-120 days) to perform additional subsurface investigations and identify any defects, errors, and inconsistencies in documents, or changed subsurface conditions, which may result in adjustments to the scope and budget.
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Risk Contractual Risk Allocation/Sharing Strategies
Owner Retains Responsibility DB Contractor is Assigned Responsibility Shared Responsibility
Utilities
Utility conflicts, relocation of unidentified utilities, or identified utility relocation impacts
  • To the extent possible, the owner addresses utility relocation early in the project development phase for higher risk projects and completes utility relocation work before procurement.
  • If utilities cannot be relocated in advance of procurement or unknown utilities are discovered or are in a substantially different location than shown on plans, the DB contractor may be eligible to change order due to the extra work or a critical delay. Similarly, the DB contractor is eligible for a change order or a time extension resulting from the failure of a utility to relocate its utility in accordance with an Advance Utility Relocation Agreement with the owner.
  • The DB contractor is required to coordinate with utilities; particularly if a utility was a “non-prior right,” the contractor is responsible for utility agreements, utility adjustment work and whatever costs and time are necessary for relocation.
  • The DB contractor is not entitled to a change order for adjustment work that was initially anticipated to be performed by the utility owner.
  • If not possible to relocate utilities in advance, shared risk strategies are considered where the contractor is responsible for an initial deductible, and the owner pays for utility-related costs above the cap.
  • The DB contractor is entitled to a price increase for an unidentified utility within schematic ROW to the extent the costs increase above a certain dollar value per utility.
  • Along with deductibles, allowances are also being considered for certain utilities including potential incentives for cost sharing if the allowance is not used up. Owners have predefined utility allowances in the contract for certain required utility relocations that incentivize the DB contractor to share equally in any unused allowance.
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Risk Contractual Risk Allocation/Sharing Strategies
Owner Retains Responsibility DB Contractor is Assigned Responsibility Shared Responsibility
Right-of-Way (ROW)
Delays caused by additional ROW acquisition not completed before project execution, or resulting from a need for additional property outside the permit boundary
  • Owners may commit to a milestone schedule for obtaining ROW parcels that would entitle the DB contractor to additional time and/or compensation for critical delay impacts for late ROW acquisition.
  • If ROW acquisition is not completed by contract execution, the DB contractor is responsible for acquiring the remaining project ROW.
    The DB contractor will acquire ROW, including real property within the boundaries included in the NEPA schematics (“Schematic ROW”) and any additional real property needed for the project outside the Schematic ROW. All project ROW must be acquired by the DB contractor in the name of the State. ROW acquisition responsibilities including surveys, developing ROW plans, legal costs for condemnation, appraisals, and negotiations will be included in the price proposal.
  • Several contracts specified that the DB contractor was responsible for additional ROW acquisition and payment needed for its convenience/design changes.
ROW acquisition responsibilities and costs can be shared in various ways between the owner and DB contractor. For example,
  • If ROW acquisition is delayed, the risk of delay following the expiration of a 365-day period approval of a condemnation package, on an individual parcel basis, is borne equally by each party for the first 100 days thereafter (i.e., for each parcel, DB contractor is entitled to one day of time extension for every two days of delay).
  • After expiration of the first 100 days after the initial 365-day period, DB contractor is entitled to one day of time extension for each day of eligible delay.
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Risk Contractual Risk Allocation/Sharing Strategies
Owner Retains Responsibility DB Contractor is Assigned Responsibility Shared Responsibility
Govt. Permits and Approvals
Delays in obtaining required environmental or other permits and approvals
  • Owner will obtain all initial owner-required permits and approvals prior to award or commercial closing date including environmental decision documents approved under NEPA; USACE permits under Section 404 of the Clean Water Act; and local government approvals.
  • Owners will grant relief for critical delays caused by late government permits and approvals.
  • In certain cases, the DB contractor is assigned with obtaining governmental permits and approvals except for those that the contract documents expressly make the responsibility of the owner, particularly if revisions to permits are likely during the procurement process.
  • If the DB contractor’s proposed Alternative Technical Concept or design solution requires changes to existing permits or approvals for any reason other than for an owner-directed change or other relief event, the DB contractor is responsible for all costs and delays related to revised permits and approvals.
The owner and DB contractor collaborate on obtaining agreements or memorandums of understanding with permitting agencies that define approval requirements and processes, jointly develop permit applications, and conduct design reviews with permitting agencies based on a preferred alternative or ATC.
Archeology or Protected Species
Unforeseen archeological sites or protected species
  • Owners predominantly do not conduct survey investigations for archeology/protected species in advance and include this reference information in the contract. Such conditions are not anticipated in most contracts.
  • In a few cases, the contract provisions require that the DB contractor perform a site investigation in advance to determine the existence of these conditions. With appropriate notice and justification for impacts, these are generally treated as relief events, force majeure events, or differing site conditions.
N/A (The owner typically retains this risk) N/A (The owner typically retains this risk)
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Risk Contractual Risk Allocation/Sharing Strategies
Owner Retains Responsibility DB Contractor is Assigned Responsibility Shared Responsibility
Hazardous Materials
Unknown hazardous materials or additional impacts for mitigation of preexisting hazardous materials
  • If hazardous materials were not anticipated on the project, unforeseen hazardous materials mitigations are generally treated as relief events, force majeure events, or DSCs with appropriate notice and justification for impacts.
  • Owner may include an allowance item for hazardous materials in RFP with an agreed upon unit cost for handling, transport, and disposal.
For pre-existing (known) hazardous materials, the DB contractor is responsible for the handling, transport, removal and disposal of a known quantity of pre-existing hazardous materials after completion of the investigation and testing process to determine whether preexisting hazardous materials are present.
  • Pre-existing Contaminated Materials Deductible:
    • The DB contractor responsible for the first $ {•] of extra work costs.
    • The DB contractor compensated for 50% of DB contractor’s reimbursable hazardous materials management costs for pre-existing hazardous materials that exceed the deductible cap up to $[•].
    • Thereafter, the DB contractor is compensated for 100% of reimbursable hazardous materials management costs for pre-existing hazardous materials greater than $[•], and 100% of the reimbursable hazardous materials management costs for pre-existing hazardous materials encountered on additional properties acquired as a result of a necessary basic configuration change or owner-directed change.
  • The DB contractor is responsible for first 30 days of critical delay related to hazardous material management after which the DB contractor is entitled to a time extension.
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 11
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 12
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 13
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 14
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 15
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 16
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 17
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 18
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 19
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 20
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 21
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 22
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 23
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 24
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 25
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 26
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 27
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 28
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 29
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 30
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 31
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 32
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 33
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 34
Suggested Citation: "2 Literature Review." National Academies of Sciences, Engineering, and Medicine. 2025. Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/29285.
Page 35
Next Chapter: 3 Survey and Interview Results
Subscribe to Emails from the National Academies
Stay up to date on activities, publications, and events by subscribing to email updates.