To obtain feedback on the proposed methodology components, the team conducted additional interviews and focus groups with owner and industry practitioners.
The research team invited 18 DOT representatives to participate in an owner focus group addressing project risks and strategies to promote competition. Five owner representatives were able to coordinate their schedules to participate in the roundtable discussion. All had significant APDM experience as shown in Table 5.1.
Table 5.1: Owner Representatives
| Name/DOT | Fixed Price DB | APD Experience | P3 | |
|---|---|---|---|---|
| Progressive DB | CM/GC | |||
| Eric Kahlig, Ohio DOT | ✓ | ✓ | ✓ | |
| Jeff Folden, Maryland DOT | ✓ | ✓ | ✓ | |
| Ryan Mitchell, Michigan DOT | ✓ | ✓ | ✓ | ✓ |
| Shailendra Patel, Virginia DOT | ✓ | ✓ | ||
| Art McClusky, Washington DOT | ✓ | ✓ | ✓ | |
In facilitating the roundtable discussion, the research team shared the methodology components discussed in Chapter 4, and asked each of the owner representatives to identify:
Feedback and findings from this owner roundtable are summarized in Section 5.2 of this memorandum; notes from the focus group are included in Appendix H.
As discussed below, two forms of industry outreach took place:
At the Interim Meeting held on February 27, 2024, the team agreed to conduct additional outreach to contractors who pursue more “bread and butter” DOT projects to ensure the Guide captures the conditions and concerns facing local and regional contractors as well as the larger, national and international contractors/developers whose perspectives were previously obtained as part of the Phase I research. Following the discussion at the Interim Meeting, the Panel provided the team with additional regional industry contacts. The team conducted one-on-one interviews with seven industry representatives recommended by members of the Panel. Five were contractors and two provided engineering / design services.
Findings from these interviews are discussed in Section 5.3.1.
The team facilitated a roundtable discussion with the industry stakeholders. In addition to presenting the proposed methodology components, the team also posed the following questions to the group, which were designed to determine if their perceptions regarding risk allocation by owners had changed or evolved during the months that had elapsed since their original Phase 1 interviews, and if they continued to see progressive APD methods as the path forward, despite some concerns regarding the track record of such methods from owners and local/regional contractors:
Feedback and findings from this owner roundtable are summarized in Section 5.3.2; notes from the focus group are included in Appendix H.
As discussed in Section 5.1.1, the research team facilitated a roundtable discussion with five owner practitioners to discuss and validate the proposed methodology components and obtain feedback on the desired content for the associated Guide. A summary of key discussion items is provided below.
For each stage in the project delivery lifecycle, the research team sought feedback regarding:
Table 5.2 summarizes the feedback provided by the owner practitioners regarding practices and tools that can be used during each stage of the project lifecycle.
Table 5.2: Practices and Tools
| Practices/Tools Proposed by the Research Team | Additional Practices/Tools Identified by Owners |
| Stages 0,1 – Initiation & Planning and Development | |
Participants agreed with the practices/tools proposed by the team, which included:
|
|
| Stage 2 – Procurement | |
Participants agreed with the practices/tools proposed by the team, which included:
|
|
| Stage 3 – Execution | |
Participants agreed with the practices/tools proposed by the team, which included:
|
|
| Stage 4 – Operations | |
Participants agreed with the practices/tools proposed by the team, which included:
|
N/A (participants had no additional practices to share; discussions focused on lessons learned regarding warranty use) |
Throughout the discussion of the project stages, the owners also shared their thoughts regarding the use of progressive delivery methods such as PDB and CM/GC. Although they felt that such methods represented a valuable tool to help derisk large and complex projects, they had concerns regarding the lack of competitive tension and the ability to arrive at a fair construction price when using these methods. Observations from these discussions include the following:
As a final topic of discussion during the Owner forum, the team sought feedback on the desired content for the Guide to be developed under the research. As summarized below, the guidebook preferences primarily focused on guidance related to negotiating construction costs for CM/GC and PDB projects:
As a post focus group activity, the research team asked the participants to identify how their agency typically allocates risks in fixed price contracts. Three participants provided feedback, as summarized in Table 5.3.
Table 5.3: Example DOT Risk Allocation Strategies
| Risk | Maryland | Virginia | Washington |
|---|---|---|---|
|
Share: State completes initial utility coordination pre-procurement to develop relocation requirements and concepts. Design-Builder is responsible for final design and construction coordination with third party utility relocation and design/construction of utility work in contract. | Transfer (except for high risks utilities): DB is incentivized to avoid utilities relocation through design solutions. This also results in cost and schedule savings in most cases. | Transfer: Design-Builder has ability to avoid utility conflicts through design effort. Owner delegates limited authority to Design-Builder and provides contractually binding agreements as part of RFP documents |
|
Retain (except for Design-Builder driven changes): State completes plats and acquisitions based on concept design prior to construction. ROW schedule provided to Design-Builder. If Design-Builder requires additional ROW (such as for an ATC), DesignBuilder would retain risk for any schedule delays. | Transfer (schedule risk only): DB is in better position to manage schedule risks. VDOT pays for the acquisition cost. | Share: Usually completed by owner, but in some cases competed by Design-Builder. In all cases, Owner pays for acquisition cost |
|
Share: Certain permits (404, wetlands) are acquired by the State with the DesignBuilder responsible for receiving plan approvals and modifications approvals. Other permits (SWM/ESC), the State completes a concept, but the Design-Builder is responsible to complete final design/construction and acquire permit. | Share: Construction Permits are DB’s responsibilities due to control of design allowing them to minimize impacts. NEPA is retained by the owner. PJD, BO, Interagency Coordination initiated or completed by the Owner prior to an award. | Share: Other than construction permits, all other permits are initiated and completed by Owner |
|
Retain: Scope definition and requirements must be retained by owner – Design-Builder cannot provide fixed-price and schedule with incomplete scope. Note – Can use fixed-price, best design where more or less scope may be delivered by Design-Builder under fixed-price. | Retain: Owner is responsible for the scope definition to ensure that DB is able to appropriately determine cost and schedule for successful delivery. | Retain: Owner provides Conceptual Design indicating that the project can be constructed and provides “must have” elements via listing of Basic Configuration items |
| Risk | Maryland | Virginia | Washington |
|---|---|---|---|
|
Share: Initial coordination completed by State before procurement to ensure contract requirements are defined. Design-Builder responsible for final design and construction coordination and approvals as needed. | Share: Owner needs to initiate coordination with respective gov’t agencies prior to submittal of proposal. If coordination with stakeholders is anticipated to significantly impact cost and schedule, the owner needs to patriciate in sharing the risk. | Retain: Owner provides coordination prior to publication of RFP, which includes contractual binding agreements developed with the other stakeholders |
|
Share (Same general strategy as utilities) | Share: Agreement should be obtained by the owner. The flagging operation efforts need to be identified in the RFP. The coordination and design efforts are DB’s responsibilities. | Share: Agreement (Construction and Maintenance Agreement and amendments) obtained by Owner. Protective services identified in RFP, with design and construction coordination the Design-Builder responsibility |
|
Share: State retains risk for geotechnical conditions at points it has taken and provided boring to Design-Builder. Designer–Builder is responsible to complete additional borings and investigations for final design and construction and assumes interpretation risk between borings provided by State. | Retain until Scope Validation Period ends | Share: Owner shares in Differing Site Conditions claims up to a set amount that varies by project |
As discussed in Section 5.1.2, the team conducted interviews with seven regional/local contractors. Four interviewees represented firms operating in the Midwest and Mountain States: the remaining three represented firms working in the mid-Atlantic region. All had significant experience with fixed price DB projects. Some also had experience with CM/GC and PDB. Their so-called “sweet spot” for serving as a prime contractor on an APD method project are contracts valued between $100M to $250M. For projects greater than $500M, the interviewees generally have pursued joint venture arrangements with other firms.
Most interviewees noted that they have generally been more successful pursuing traditional, fixed price DB projects than progressive DB or CM/GC work. Their success with fixed price DB opportunities was attributed to having more intimate knowledge of the area and local market conditions, which allowed them to develop and offer more innovative and lower priced solutions than the larger, national players. They have generally been less successful pursuing progressive CM/GC and PDB work, for which larger, Tier 1 contractors can often demonstrate more experience and stronger qualifications.
The interviews provided the opportunity to compare the perspectives of these regional firms to the larger national players on issues such as the attractiveness of fixed price versus progressive APD methods, and how owners could improve risk allocation and increase competition on APD method projects.
In contrast to the larger firms, the regional contractors were far less enthusiastic of progressive PDMs. All questioned the necessity of strict qualifications criteria that require proponents to demonstrate at least five years of experience on comparable PDB or CM/GC projects, which few firms other than the larger Tier 1 contractors currently possess.
The interviewees generally viewed fixed price DB as providing owners with the highest likelihood of cost and schedule control. However, they also indicated that attracting and retaining staff on such projects is becoming more difficult, as the current workforce dislikes the fast-paced and often more stressful and adversarial nature of such projects.
PDB and CM/GC were seen as being good options for projects with high-risk profiles (e.g., due to underground utilities, railroads, permitting issues, etc.). However, these methods were viewed as providing less incentive for the integrated delivery team (owner, design, contractor) to find cost savings and minimize scope growth. They stressed that the owner team must have a strong project manager to exert the necessary discipline to minimize scope creep by stakeholders.
As summarized in Table 5.4, factors considered as part of the firm’s pursuit decision closely mirrored those heard from larger firms, as discussed in Section 3.5.
Table 5.4: Factors Considered as part of the Pursuit Decision
| Procurement and Contracting Considerations | Technical Risks |
|---|---|
|
|
Table 5.5 summarizes recommendations proposed by interviewees as to how owners could improve risk allocation and competition on fixed price APDM projects. These recommendations are similar to those shared by their larger counterparts, as discussed in Section 3.5.
Table 5.5: Recommendations to Owners
| Project Development and Procurement Practices | Project Execution Practices |
|---|---|
|
|
The regional firms expressed far more support for the use of fixed-price DB than the larger national and international firms interviewed during Phase 1 of the research. Regional contractors and designers know their clients and the market and are confident in their ability to devise innovative solutions under fixed price DB optimized to meet local conditions. The regional contractors all viewed fixed-price DB as providing owners and taxpayers with the highest likelihood of cost and schedule control and perceived progressive methods as providing less incentive for the integrated delivery team (owner, designer, contractor) to pursue innovation and cost and schedule savings. They believed that national firms are advocating for progressive methods because they are less competitive and successful on fixed price procurements (as they are less familiar with local conditions that can drive cost savings). As owners increase project scale and complexity, they will continue to attract national or international players who may not have the same local knowledge and experience as the smaller regional firms.
The research team facilitated a roundtable discussion with five industry practitioners representing large, national and international firms.
In general, the perceptions of these practitioners regarding risk allocation remained unchanged from when the team first interviewed them during Phase 1 of the research. While noting that all delivery methods have a time and place, the participants continued to strongly favor increased use of progressive delivery methods as a means to de-risk large and complex projects and make them more attractive to pursue.
A summary of industry concerns along with key recommendations for owners regarding strategies and tools to align risk perceptions is provided below. Detailed workshop notes are provided in Appendix H.
Particularly for large, fixed-price design-build contracts, the roundtable participants felt that owners in the past attempted to shift too much risk to contractors for things that they cannot control and cannot put a large enough contingency on to make the risk vs. reward tradeoff make sense. This risk imbalance has resulted in reduced competition and high contingency pricing, in addition to disputes and claims.
Although they believe that progressive PDMs provide an answer to this problem, they acknowledged that such methods introduce challenges of their own. For example,
To overcome such challenges, participants proposed the following recommendations: