
This chapter continues the stepwise process from Chapter 4 that was outlined in Figure 10. It provides a framework for assessing design alternatives and making decisions about how to proceed. It also provides supplemental guidelines on scoping additional studies that may be needed to support decisions. This chapter is intended to support the design team in answering the following questions:
Step 3 is a major decision gate to determine the next steps for the project. As the ultimate outcome of this step, the design team and decision-makers need to reach one of three findings:
The roadmap first introduced in Chapter 3 illustrates this decision gate. Figure 33 shows an excerpt of this roadmap pertaining to Step 3 and 4, and the potential outcomes of the decision-making process.
The previous section defines the decisions that need to be made. It does not define how decisions should be made. This section presents a framework for making these decisions, including the following three sub-steps:
Following bridge characterization (Chapter 2) and in Chapter 4 (Step 1), checks for likely fatal flaws were performed when assessing whether any locations could support a BMP.
A similar fatal flaw screening is relevant at this decision gate as well. To avoid unnecessary complexity, design teams can use a simple screening of options in the first phase to determine if multiple alternatives are viable. If all options have clear or likely fatal flaws, further complexity in decision-making is not needed. Or, if one option is a clear favorite due to serious issues with other options, further complexity is not needed. In either case, it may be adequate to simply document the basis for these findings and skip the following steps.
If there are two or more options that appear to be potentially feasible and there is not a clear favorite based on simpler methods, then the design team should proceed to the following sub-steps.
Defining a decision-making framework is important before performing the design evaluation as the framework will define the specific metrics that need to be calculated and the parties that need to contribute to this evaluation.
Most highway projects involve complex decisions that require multiple objectives to be considered and balanced. Where existing DOT decision-making processes can be adapted to serve the decisions needed for on-bridge stormwater treatment, this is likely the most efficient and effective as it builds on familiarity and past experience.
If existing decision-making frameworks are not adequate to support the decisions presented in this step, various modern decision-making practices can be reviewed and adapted. The following decision-making frameworks may be applicable:
Elements of each approach would be applicable to determining how well each alternative meets the objectives defined in Chapter 2.
One viable option is the MCDA approach, with risk assessment and lifecycle cost being two major inputs to the MCDA. Yannis et al. (2020) provides a review of the state of the practice of MCDA for transportation projects. While various sophisticated methods can be used, an MCDA can be as simple as a weighted scoring matrix. Most MCDA processes involve the following:
In order to apply the selected framework, the preliminary design alternatives will need to be quantified and scored based on the evaluation objectives and criteria. The inputs to this process will likely be a mix of qualitative ratings and quantitative calculations.
Examples of design objectives with qualitative ratings could include:
Examples of quantitative inputs include:
To account for uncertainty, inputs can be expressed as a range to enable sensitivity analysis and robustness testing.
Once these inputs are developed for each alternative, the design and decision-making team can apply the selected decision-making framework to compute weighted scores (or ranges of scores) for each option. The results of this analysis can be interpreted to determine if clear decisions are supported.
The results of Step 3b may indicate that certain issues have a greater influence on decisions and are not quantified well enough to allow distinction between alternatives (i.e., scoring ranges of alternatives overlap). If these issues are identified, they should be scoped and performed as part of Step 4, and the findings should feed back into Step 3c above to improve decision-making power.
The checklist in Table 17 is intended as a simple tool to organize decision-making steps. This builds on the guidelines provided in Chapters 2, 3 and 4. This checklist is not intended to be comprehensive or apply to all types of projects. It is intended to serve as an efficient reference.
This step should be performed based on the prioritized information needs identified in Step 3. Examples of potential supplemental studies that may be needed to help support alternatives analyses and/or feasibility assessments include:
Table 17. Quick reference feasibility checklist.
| Quick Reference Checklist | ||
|---|---|---|
| Part A: Need for On-Bridge BMPs | ||
| Are on-land or other alternative treatment or compliance options available? | These options should be evaluated before considering on-bridge BMPs. |
Continue to evaluate on-bridge design. |
| Part B: Initial Fatal Flaw Assessment Do conditions exist that likely render on-bridge BMPs infeasible? See Chapter 2, “Screening of Potential Fatal Flaws,” and Chapter 4, “Step 1: Screen Potential BMP Locations,” for additional rationales. If one or more of the following conditions apply, this may be a fatal flaw for on-bridge treatment. |
||
| Conditions require the BMPs to be located underneath the footprint of the bridge deck and below the lower strand. | ||
| Bridge deck drains are located between girders, making it infeasible to convey water to a treatment location. | ||
| Edge barriers with crash test ratings of TL-4 or lower and no option for BMP support from girders or piers, making it highly unlikely for placement of BMPs on edge barriers without major modifications. | ||
| The bridge is classified as poor structural condition or is posted for load. | ||
| Unacceptable traffic interruptions to emergency services or other critical functions. | ||
| Other fatal flaws are identified in the site investigation. | ||
| Enter explanatory notes for fatal flaws. | ||
| Part C: Core Design Criteria Can the design be configured to meet the project-specific objectives defined in Chapter 2? If the design cannot meet each of these criteria, then it is likely not acceptable. This is a generic checklist only. Development of project-specific objectives and feasibility thresholds are suggested. |
||
| Provides adequate stormwater treatment to meet regulatory requirements, including level of treatment provided, amount of water treated, portion of the bridge treated. | ||
| Avoids unacceptable traffic safety hazards from lateral spread by maintaining the design drainage capacity and avoiding increased risk of drainage system clogging. | ||
| Avoids unacceptable increase in structural risk by adhering to the findings of a bridge-specific structural analysis. | ||
| Minimizes traffic impacts to acceptable levels during construction and O&M by locating BMPs where they can be readily constructed and maintained. | ||
| Quick Reference Checklist | ||
|---|---|---|
| Protects worker safety during construction and O&M activities by designing systems that can be reasonably constructed and maintained. | ||
| Complies with material procurement policies for both the construction phase and the O&M phase. | ||
| Avoids damage to BMP from cold climates or excessive O&M burden due to cold weather operations. | ||
| For design criteria that cannot be met, provide explanation to justify infeasibility of design. | ||
| Part D: Cost and Financial Feasibility Is the project financially feasible? |
||
| Is the required capital and O&M cost needed to meet the design criteria above feasible? | ||
| How does the cost compare to other alternatives or DOT-specific feasibility benchmarks? | ||
| Could phasing the project with other planned construction or rehabilitation activities improve the cost? | ||
| Provide a summary of findings on cost and financial feasibility below: | ||
The following sections provide supplemental guidelines for scoping two of these studies that are likely to be broadly applicable.
Each part of a bridge serves a structural purpose. Modifications to any part of a bridge, such as adding new weight and attachments, nearly always require structural assessment by a structural engineer. This assessment could find that (1) the added weight can be supported as is, (2) structural reinforcements are needed to support the added weight, or (3) there are no reasonable modifications that could be made to support the added weight.
The purpose of this section is to provide general guidelines for scoping structural analyses to determine the feasibility of attaching new stormwater treatment and conveyance systems to a bridge.
The primary focus of the information presented here is attachment to edge barriers. As described in Step 1, attaching stormwater treatment systems to edge barriers may be advantageous to allow construction and maintenance access without in-water or under-bridge work. However, compared to other bridge components, the edge barrier has the most points of potential failure (i.e., the edge barrier, the top slab overhang, the supporting girders, and the supporting piers) and generally has less structural resistance compared to girders or piers.
Due to differences in structural methods used by different DOTs and the large variability in bridge and edge barrier types, this section does not provide structural analysis guidance. This section is intended to help DOT design teams understand the general structural analysis framework for on-bridge retrofits in order to scope the appropriate structural analyses by qualified professionals.
The general framework presented in this section is based on the LRFD [Load-and-Resistance Factor Design] Bridge Design Specifications, 9th Edition (AASHTO 2021). The primary steps include:
Several factors should be considered in applying this framework:
For edge barriers specifically, the following notes apply:
The weight of stormwater treatment systems is a key input to structural analyses. When estimating the added weight, the design team should consider the following components:
For the prototype system described in Chapter 3, the estimated design weight of a 4-ft × 6-ft treatment unit is approximately 14,550 lbs of load. Approximately 9,850 lbs of this load would be at the point of attachment and approximately 4,700 lbs would be distributed over the 100 ft span of the collection system. See the section titled “Weight Estimates” in Chapter 3 for additional detail about this calculation.
These hypothetical estimates are intended as an example only. Design teams should consider the proposed project-specific design of conveyance, mounting, and stormwater treatment systems when estimating weights for structural analysis.
Roadside hardware, such as barriers, are commonly used to reduce the potential severity of crashes on the roadside. Three general classes of bridge barriers are traffic barriers, pedestrian or bicycle barriers, and combination barriers. This section assumes that stormwater retrofits would be suspended from traffic barriers or combination barriers, as these are the only types of barriers that may have adequate resisting forces.
Traffic barriers, also known as railings, are generally made of reinforced concrete, metal, and/or timber; however, the majority of traffic barriers are reinforced concrete or metal. Bridges with timber decks on low volume secondary roads may have timber barriers. Figure 34 shows a typical range of traffic barrier design, illustrating the variability that will need to be considered during structural analysis. Appendix A of the Bridge Railing Manual prepared by Texas Department of Transportation (TxDOT 2020) is a good resource for the types of edge barriers that may be encountered in the bridge environment and is indicative of the variability, even within a single state.
According to Roadside Safety Hardware (FHWA 2015), FHWA policy holds that roadside safety hardware installed on the National Highway System (NHS) should be in compliance with the crash testing and evaluation criteria contained in the Manual for Assessing Safety Hardware (MASH) (AASHTO 2016) or its predecessor, NCHRP Report 350 (Ross et al. 1993). In addition to NCHRP Report 350 and MASH, AASHTO provides other guidance related to the design and installation specifications of roadside hardware and safety hardware such as bridge barriers in section 13 of the LRFD Bridge Design Specifications (AASHTO 2021). Currently, most states have developed a bridge barrier design manual by incorporating guidance offered by MASH, the Roadside Design Guide (AASHTO 2011), LRFD Bridge Design Specifications, NCHRP Report 350, and other national publications and available research (Griffith 2010).
Design of edge barriers is a complicated process that requires a deep understanding of the principles of mechanics, including structural loadings, static and dynamic testing as well as design using computer simulations. Computer simulation tools such as LS-DYNA are widely used to evaluate the performance of roadside barriers against environmental and structural loads. Bridge edge barriers must have sufficient structural capacity to resist the lateral impact loads from a crashing vehicle as well as support for any additional loading such as signs, lights, or potential stormwater treatment retrofits.
MASH currently defines six different crash test levels (TL) for longitudinal barriers (AASHTO 2016). A given TL provides a certain level of protection against failure in the event of vehicle impacts. NCHRP Report 350 provides guidance for selecting the target TL rating for a given bridge. The selection of a TL is primarily based on the capacity of the bridge (vehicle size and speed) and the criticality of the bridge. The information regarding these tests for longitudinal barriers can be found in Table 18.
The LRFD Bridge Design Specifications (AASHTO 2021) provides additional information on selecting the appropriate test-level criteria for bridge barriers:
Table 18. Test Levels (AASHTO 2016; the detailed description of each test vehicle can be found in Appendix H of MASH).
Test Level |
Test Vehicle Designation and Type |
Test Conditions | |
|---|---|---|---|
| Speed, mph (km/h) | Angle, degrees | ||
| 1 | 1100C (Passenger Car) 2270P (Pickup Truck) |
31 (50) 31 (50) |
25 25 |
| 2 | 1100C (Passenger Car) 2270P (Pickup Truck) |
44 (70) 44 (70) |
25 25 |
| 3 | 1100C (Passenger Car) 2270P (Pickup Truck) |
62 (100) 62 (100) |
25 25 |
| 4 | 1100C (Passenger Car) 2270P (Pickup Truck) 10000S (Single-Unit Truck) |
62 (100) 62 (100) 56 (90) |
25 25 15 |
| 5 | 1100C (Passenger Car) 2270P (Pickup Truck) 36000V (Tractor-Van Trailer) |
62 (100) 62 (100) 50 (80) |
25 25 15 |
| 6 | 1100C (Passenger Car) 2270P (Pickup Truck) 36000T (Tractor-Tank Trailer) |
62 (100) 62 (100) 50 (80) |
25 25 15 |
It should be noted that these are the generally acceptable TLs, and states might have additional requirements as well.
After determining the target TL rating for a bridge, the user can determine the design loads that edge barriers need to be designed to resist. Table 19 summarizes the standard design loads associated with each TL based on LRFD Bridge Design Specifications Section 13 (AASHTO 2021), and Figure 35 illustrates the variables presented in Table 19. Additional state-level criteria may apply.
LRFD specification requires that deck overhang should have sufficient strength to withstand the loads received from a vehicle crash to barrier and resistance to force the yield line failure pattern to remain within the barrier. It is recommended by LRFD specifications that the concrete deck overhang should not fail in a crash event before the barrier. This means the overhang should also be capable of resisting the reaction forces received from the barrier during a crash. According to Chang et al. (2012) the reinforcement of the overhang is usually designed based on the maximum bending moment (and ignoring the associated tensile force) among the different load combinations, including the extreme and seismic events. More information regarding deck overhang design can be found in Appendix 13.4 of the LRFD Bridge Design Specifications (AASHTO 2021).
Table 19. Minimum required design loads and dimension for barriers (1kip 5 = 4.45kN, 1ft = 0.31 m) (AASHTO 2021).
| Design Loads and Dimensions | TL-1 | TL-2 | TL-3 | TL-4 | TL-5A | TL-5 | TL-6 |
|---|---|---|---|---|---|---|---|
| Ft, transverse (kip) | 13.5 | 27.0 | 54.0 | 54.0 | 116.0 | 124.0 | 175.0 |
| FL, longitudinal (kip) | 4.5 | 9.0 | 18.0 | 18.0 | 39.0 | 41.0 | 58.0 |
| Fv, vertical (kip) down | 4.5 | 4.5 | 4.5 | 18.0 | 50.0 | 80.0 | 80.0 |
| Lt and LL (ft) | 4.0 | 4.0 | 4.0 | 3.5 | 8.0 | 8.0 | 8.0 |
| Lv (ft) | 18.0 | 18.0 | 18.0 | 18.0 | 40.0 | 40.0 | 40.0 |
| He (min) (in) | 18.0 | 20.0 | 24.0 | 32.0 | 40.0 | 42.0 | 56.0 |
| Hrail (min) (in) | 27.0 | 27.0 | 27.0 | 32.0 | 40.0 | 54.0 | 90.0 |
Ft = transverse vehicle impact force distributed over a length Lt at a height He above bridge deck
FL = longitudinal friction force along barrier
Fv = vertical force of vehicle laying on top of barrier
LL = longitudinal length of distribution of friction force FL
Lt = longitudinal length of distribution of impact force Ft along the barrier located a height of the He above the deck
Lv = longitudinal distribution of vertical force Fv on top of barrier
He = effective height of vehicle rollover force
Hrail = height of rail
The primary purpose of traffic barriers is to contain and redirect crashing vehicles. The load applied to the edge barrier associated with a stormwater retrofit can be significantly increased compared to the forces associated with the selected crash test level. Therefore, when attaching a stormwater treatment unit to an edge barrier, the loads and moments should be carefully recalculated, and reinforcements should be updated using adequate structural analysis techniques. Figure 36 shows an example forced diagram for a prototype BMP attached to a TL-4 edge barrier and braced from a girder to resist overturning moment. The primary new force exerted is the vertical weight of the stormwater treatment unit.
According to Table 19, for a TL-4 barrier, the minimum design forces that need to be resisted are as follows:
| Ft, transverse (kip) | 54.0 |
| FL, longitudinal (kip) | 18.0 |
| Fv, vertical (kip) down | 18.0 |
The Lv (length over which the vertical force is applied) is 18 ft.
The stormwater treatment unit plus 18 ft of conveyance would increase the vertical force at the point of attachment by an additional 10 kips. In addition, the weight of conveyance elements would increase the vertical force along the conveyance span by about 0.85 kips for each 18 ft of length.
The added weight at the point of stormwater treatment system attachment (10 kips) represents an increase of about 55% compared to the vertical design load associated with TL-4 (18 kips). In comparison, TL-5 has a vertical design load of 50 kips over 40 ft. For a TL-5 edge barrier, the added weight of the stormwater treatment unit plus 40 ft of conveyance (12 kips) would represent an increase of about 24% compared to the vertical design load.
Stormwater treatment units would not typically contribute to transverse or longitudinal loading. However, depending on configurations and reinforcements, stormwater treatment units could contribute to the overturning moment on the edge barrier or fracture of the top slab.
Each part of a bridge has a design load and a certain level of resistance. By determining the required design load for normal bridge operations, adding the new load associated with the stormwater treatment unit, and comparing this to the resistance provided by the bridge components, a structural engineer can assess whether a certain proposed modification is feasible and acceptable.
For the example presented in the previous section, a typical stormwater treatment unit could add about 24 to 55 percent to the ordinary design load of a modern edge barrier, depending on the test level rating of the edge barrier. While the information and examples provided in this section focus on edge barrier attachment, similar principles of calculating an existing load and recalculating potential future load with the addition of a stormwater treatment system and its associated infrastructure can be performed for alternative attachment locations, such as mounting to beams or piers.
As discussed earlier, regardless of the selected location, each mode of failure should be assessed by a licensed structural engineer using proper methods and tools to determine the eligibility of attaching a stormwater treatment unit to any bridge component.
A preliminary design alternative (per Steps 1 and 2) typically provides enough information to serve as the foundation for lifecycle cost analysis. Using lifecycle costing methods is particularly important for maintenance intensive BMPs such as high-rate media filters as the costs of capital design and construction are combined with the net present value of O&M activities to provide a single combined estimate. This can be used to evaluate the total cost of ownership compared to alternative scenarios. In some cases, higher upfront costs could reduce long-term O&M costs, resulting in a more favorable cost of ownership.
A whole lifecycle cost framework for stormwater BMPs is described in detail in NCHRP Report 792: Long-Term Performance and Life-Cycle Costs of Stormwater Best Management Practices (Taylor et al. 2014b). The main components of this framework are:
Note that if inflation is higher than the discount rate, future costs will have increasing NPV further into the future. On the other hand, if the discount rate is higher than the inflation rate, future costs will have a lower NPV further into the future. On a long-term basis, the discount rate tends to be higher than the inflation rate.
NCHRP Report 792 provides additional information on the foundational basis of whole lifecycle cost estimating (Taylor et al. 2014b).
Table 20 summarizes the primary components of a whole lifecycle cost estimate. This can serve as a checklist for project-specific cost estimating.
Cost drivers will vary by project depending on bridge characteristics and preliminary design alternatives; however, several factors have the potential to be consistent drivers of elevated costs in comparison to a traditional on-land highway stormwater treatment approach.
Complexity of site characterization and design process, including the likely need to obtain detailed survey, perform a full structural reanalysis of substantial parts of the bridge to support design, and evaluate multiple alternatives. In general, stormwater retrofits tend to be much more expensive than stormwater features designed as part of new construction due to the need to work around the existing infrastructure.
Table 20. Checklist of primary inputs for whole lifecycle cost estimating.
| Phase | Primary Inputs |
|---|---|
| Capital Costs |
|
| Routine O&M Costs |
|
| Rehabilitative Maintenance Costs |
|
Extensive use of specialized materials and special specifications. Specialized elements will be unavoidable in developing a workable design within the site-specific constraints of a bridge. These elements require greater cost to design and specify and often result in higher construction bids than standard components. High costs are expected for capture and conveyance systems, structural support systems, and custom BMPs.
Design elements to support O&M activities, including elements like ladders, maintenance platforms, fall protection, and hoists to enable maintenance. This equipment is typically simpler or non-existent in on-land BMPs.
Construction complexity. Retrofit stormwater management projects tend to be more costly than new construction in any environment, primarily because of the need to engineer and construct connections to existing infrastructure. Additionally, bridge projects will require specialized equipment, potentially including major expenses such as temporary work platforms or barge rental. Traffic control and worker safety also tend to be elevated compared to traditional on-land stormwater treatment projects.
Special equipment and materials, safety requirements, and traffic control for O&M. On-bridge BMPs will nearly always require special training, special equipment, and traffic control compared to on-land BMPs.
Frequency of O&M and replacement activities. Driven by the need to reduce size and design weight, BMPs will tend to have a much smaller footprint per area treated than on-land BMPs. This increases the loading per unit of BMP footprint, requiring more frequent routine O&M and replacement activities.
Several recent studies have summarized the typical costs of stormwater BMPs for highway runoff. Caltrans (2021) uses budgetary estimates of $176,000 to $350,000 capital cost per acre of right of way (ROW) treated for BMPs retrofits within the ROW. This is based on BMPs to meet TMDL requirements. This estimate is lower for BMP retrofits that are out of the ROWs. Price et al. (2021) summarized actual BMP implementation costs in the Chesapeake Bay region and found that implementation costs are typically between $50,000 and $300,000 per impervious acre treated. San Mateo County (2022) estimated that street-level green infrastructure projects cost about $300,000 per acre treated, while regional projects cost about $70,000 per acre treated.
There are no known cases of on-bridge stormwater treatment where costs are available. However, from the case studies presented in the Appendix, the cost to retrofit existing bridges with on-bridge stormwater treatment is between $2.2M and $4.5M per acre of bridge treated at the low range of cost estimates and from $3.6M to $10M per acre at the high end.
If the cost of off-bridge treatment is conservatively estimated as $300,000 per acre treated, then the lower range cost of on-bridge BMPs is estimated to be well more than five times higher and often more than ten times higher than this conservative estimate for off-bridge BMPs.