Selecting, Procuring, and Implementing Airport Capital Project Delivery Methods (2024)

Chapter: Appendix A: Project Delivery Method Summary Tables

Previous Chapter: Bibliography
Page 97
Suggested Citation: "Appendix A: Project Delivery Method Summary Tables." National Academies of Sciences, Engineering, and Medicine. 2024. Selecting, Procuring, and Implementing Airport Capital Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/27951.
Page 98
Suggested Citation: "Appendix A: Project Delivery Method Summary Tables." National Academies of Sciences, Engineering, and Medicine. 2024. Selecting, Procuring, and Implementing Airport Capital Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/27951.

Table A-1. Design–bid–build (DBB).

Contractual Structure Key Attributes Typical Procurement Methods Used
  • Clear separation between design and construction
    • Designer (may be internal staff or third-party consultant) prepares construction documents
    • Contractor bids on 100% complete plans and specifications
    • Award is typically to the lowest responsible and responsive bidder
  • Design and construction are performed in sequence and do not overlap
  • Owner has full control over design and bears design risk
  • Contractor has little opportunity to offer input into the design process
  • Low bid
  • Best value (less commonly used)
Typical Payment Methods Used
  • Unit price
  • Cost reimbursable
Perceived Advantages Potential Challenges When Is Using This PDM advantageous?
  • Traditional delivery method that is well-understood and well-accepted by owners and industry
  • Provides owner with maximum design control
  • Promotes high competition among contractors
  • Offers the lowest initial price that responsible, competitive bidders can offer
  • Extensive litigation has resulted in well-established legal precedents
  • Separation of design and construction contracts can create adversarial relationships between the parties (different agendas and objectives)
  • Owner bears risk of design adequacy/errors
  • No contractor involvement in design or planning
  • Designers may have limited knowledge of the true cost and scheduling and phasing ramifications of design decisions
  • No opportunities for time savings by fast-tracking construction
  • Greater potential for errors and omissions, change orders, delays, and other adverse outcomes
  • Tends to yield base level quality
  • Projects requiring a high degree of owner control that can be designed to or near 100% completion
  • Projects that lack schedule sensitivity
  • Lowest initial cost is the primary driver
  • Third-party risks and unknowns are best managed by the owner

Note: PDM = project delivery method.

Page 99
Suggested Citation: "Appendix A: Project Delivery Method Summary Tables." National Academies of Sciences, Engineering, and Medicine. 2024. Selecting, Procuring, and Implementing Airport Capital Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/27951.

Table A-2. Construction manager at risk (CMAR).

Contractual Structure Key Attributes Typical Procurement Methods Used
  • Owner engages a construction manager (CM) early in the design phase (e.g., at 15%–30% design)
  • The designer and the CM hold separate contracts with the owner (alternatively, design services may be provided by the owner’s internal staff)
  • CM acts as a construction advisor during the design phase and as a general contractor during the construction phase
    • CM performs “preconstruction services,” including cost estimating, scheduling, and constructability reviews
    • CM contracts directly with trades and assumes performance risk for cost and schedule
  • Design and construction phases may overlap, allowing for the completion of early work packages
  • Qualifications-based selection
  • Best value (considering the CM’s qualifications and proposed fees)
Typical Payment Methods Used
  • Cost reimbursable
  • Guaranteed maximum price
Perceived Advantages Potential Challenges When Is Using This PDM Advantageous?
  • Enables early CM input into design and constructability issues
  • Allows owner to retain significant control and influence over design, phasing, and buyout decisions while allowing for CM to provide innovation and constructability recommendations during design
  • Enhances understanding and transparency of risks related to cost and schedule
  • Provides opportunities to complete design-enabling or early work packages, potentially compressing the overall project schedule
  • Two contracts to manage:
    • Disagreements between designer and contractor flow through the owner
    • Potential for adversarial relationships
  • Owner bears risk of design adequacy
  • Added costs for CM fees during preconstruction (though potentially offset by savings via early collaboration)
  • Deriving value from a CM’s participation during the design/preconstruction phase can be challenging to first-time users
  • Project price is negotiated and not competitively bid (with the possible exception of trade and subcontracts)
  • Projects having a high potential for unknown or poorly defined risks that would benefit from the collaborative involvement of the owner, designer, and CM to mitigate risks
  • Projects entailing complex phasing or staging, with the possibility of impacting operations or the traveling public
  • Projects in which the design is complex, difficult to define, and subject to change
Page 100
Suggested Citation: "Appendix A: Project Delivery Method Summary Tables." National Academies of Sciences, Engineering, and Medicine. 2024. Selecting, Procuring, and Implementing Airport Capital Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/27951.

Table A-3. Design–build (fixed price).

Contractual Structure Key Attributes Typical Procurement Methods Used
  • Owner contracts with a single legal entity to complete the design and construction of a project
  • Several design-related risks shift to the design–builder
  • Design and construction phases may overlap
  • In contrast to progressive DB:
    • Owner must fully define project scope of work and performance criteria to support procurement process
    • Design–builder typically commits to a fixed price (lump sum) at the time of selection (i.e., before final design is complete)
    • Typically, a single contract is executed for design and construction phase services
  • Best value (with selection based on qualifications/technical merit and fixed price to deliver the DB scope)
  • Low bid (used for noncomplex, standardized designs for which innovation is not sought)
Typical Payment Methods Used
  • Lump sum (possibly with allowances or unit cost items to address risk)
Perceived Advantages Potential Challenges When Is Using This PDM Advantageous?
  • Provides single point of responsibility for design and construction
    • Minimizes adversarial disputes between designer and contractor
    • Creates opportunities for efficient risk transfer
    • Reduces change orders and claims related to errors and omissions
    • Requires less management and coordination by owner
  • Enables accelerated delivery by fast-tracking design and construction
  • Promotes enhanced constructability—design can be optimized to contractor’s strengths, potentially leading to time and/or cost savings
  • Provides earlier schedule and cost certainty (fixed-price DB)
  • Locking in lump-sum prices early may result in higher contingency or risk pricing
  • Limited collaboration occurs between owner and design–builder during development of design and cost proposal
  • Owner incurs additional costs for project criteria development and possibly stipends for unsuccessful proposers
  • Ability to fast-track construction may be limited by permitting agencies requiring more complete designs
  • Potential to reduce opportunities for smaller, local construction firms
  • Coordination can be challenging for owners unaccustomed to the fast-paced nature of a DB project
  • Owner and stakeholder interests may be underrepresented
  • Projects that would benefit from an expedited or compressed schedule
  • Early cost certainty is desirable
  • Projects that do not entail complex phasing or operational considerations
  • Projects where the design and construction are tied to proprietary equipment or systems (such as with baggage screening and handling systems)
  • Project scope can be adequately defined without 100% complete plans, specifications, and estimates
  • Minimal third-party risks exist or can be effectively managed by the design–builder
Page 101
Suggested Citation: "Appendix A: Project Delivery Method Summary Tables." National Academies of Sciences, Engineering, and Medicine. 2024. Selecting, Procuring, and Implementing Airport Capital Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/27951.

Table A-4. Progressive design–build (PDB).

Contractual Structure Key Attributes Typical Procurement Methods Used
  • Design–builder is engaged very early in the life of the project (e.g., during programming phase)
  • Final project cost and schedule commitment is not fixed at the time of the design–builder’s selection
  • Design–builder and owner work collaboratively to validate basis of design and advance, or progress, toward a final design and associated contract price
  • Design–builder delivers the project in two phases (for which two separate contracts may be executed):
    • Phase 1 (preliminary or preconstruction services), including pricing level design development, preconstruction services, and negotiation of a firm contract price for Phase 2
    • Phase 2, including final design, construction, and commissioning
  • Qualifications-based selection
  • Best value (with selection based on qualifications and design–builder’s fees)
Typical Payment Methods Used
  • Guaranteed maximum price
  • Cost reimbursable
Perceived Advantages Potential Challenges When Is Using This PDM Advantageous?
In addition to the advantages listed for design–build (fixed price), PDB:
  • Enables the owner to bring the design–builder into the project very early in the programming or design phase, without having a fully validated basis of design
  • Avoids the time and expense of the owner developing a set of baseline design documents to the level needed to obtain a fixed construction price from a design–builder during the procurement stage
  • Allows the owner to collaborate with the design–builder as part of the design development process
  • Reduces risk pricing and promotes more realistic pricing assumptions through a collaborative design development and open-book pricing process
  • No cost certainty at the time of the design–builder’s selection
  • Project price is negotiated and not competitively bid (construction price is negotiated following Phase 1 design development and preconstruction activities)
  • Cost-estimating expertise needed during final cost negotiations to ensure a fair price is received
  • Projects having a high potential for unknown or poorly defined risks that would benefit from the collaborative involvement of the owner and design–builder
  • Projects entailing complex phasing and/or operational or stakeholder impacts that would benefit from ongoing owner/stakeholder input
  • Major project risks can be mitigated by having the contractor and designer in a direct contractual relationship (in contrast to CMAR)
Page 102
Suggested Citation: "Appendix A: Project Delivery Method Summary Tables." National Academies of Sciences, Engineering, and Medicine. 2024. Selecting, Procuring, and Implementing Airport Capital Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/27951.

Table A-5. Public–private partnership (P3).

Contractual Structure Key Attributes Typical Procurement Methods Used
  • Combines design and construction responsibilities with operations, maintenance, and financial responsibilities under a single contract
  • Entails greater private-sector participation in the delivery, operation and financing of a project
  • Variants of P3 delivery include:
    • Design–build–operate–maintain (DBOM)
    • Design–build–finance–operate–maintain (DBFOM)
    • Design–build–finance (DBF)
  • Negotiation
Typical Payment Methods Used
  • Postconstruction project revenues (e.g., user fees, parking revenue, rental fees, concession revenues, advertising or other business revenue and lease revenue)
  • Availability payments
  • Management fees
Perceived Advantages Potential Challenges When Is Using This PDM Advantageous?
For P3 projects with operations and maintenance components:
  • Integrating the process of design, construction, operations and maintenance can enhance the maintainability of design solutions and provide a better approximation of life-cycle costs
  • Can motivate the contractor to increase the quality of design and workmanship to help minimize future maintenance issues
  • Can provide specialized expertise to operate and manage ancillary assets that are not part of an owner’s core mission

For P3 projects with a finance component:

  • Allows for implementation of large projects that may otherwise be cost prohibitive
  • Owner may give up control over design details and some aspects of operations and maintenance
  • Procurement process can be time-consuming, costly, and complex
  • Poor risk allocation can reduce cost efficiency and/or dissuade proposers
  • Large or mega projects for which the owner may lack the financial capacity to execute the project
  • Projects that will generate revenue
  • Projects that are outside the owner’s core mission, for which it does not have the staff expertise to operate and maintain (e.g., consolidated rental car facilities, automated people movers)
Page 97
Suggested Citation: "Appendix A: Project Delivery Method Summary Tables." National Academies of Sciences, Engineering, and Medicine. 2024. Selecting, Procuring, and Implementing Airport Capital Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/27951.
Page 97
Page 98
Suggested Citation: "Appendix A: Project Delivery Method Summary Tables." National Academies of Sciences, Engineering, and Medicine. 2024. Selecting, Procuring, and Implementing Airport Capital Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/27951.
Page 98
Page 99
Suggested Citation: "Appendix A: Project Delivery Method Summary Tables." National Academies of Sciences, Engineering, and Medicine. 2024. Selecting, Procuring, and Implementing Airport Capital Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/27951.
Page 99
Page 100
Suggested Citation: "Appendix A: Project Delivery Method Summary Tables." National Academies of Sciences, Engineering, and Medicine. 2024. Selecting, Procuring, and Implementing Airport Capital Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/27951.
Page 100
Page 101
Suggested Citation: "Appendix A: Project Delivery Method Summary Tables." National Academies of Sciences, Engineering, and Medicine. 2024. Selecting, Procuring, and Implementing Airport Capital Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/27951.
Page 101
Page 102
Suggested Citation: "Appendix A: Project Delivery Method Summary Tables." National Academies of Sciences, Engineering, and Medicine. 2024. Selecting, Procuring, and Implementing Airport Capital Project Delivery Methods. Washington, DC: The National Academies Press. doi: 10.17226/27951.
Page 102
Next Chapter: Appendix B: Example Technical and Price Proposal Requirements
Subscribe to Email from the National Academies
Keep up with all of the activities, publications, and events by subscribing to free updates by email.