Historically, airport capital construction projects entailed the almost exclusive use of the design–bid–build (DBB) delivery method involving the separation of design and construction services and the sequential performance of design and construction. However, over the past two decades, airports have increasingly been turning to alternative project delivery methods (PDMs)—including construction manager at risk (CMAR), design–build (DB), public–private partnerships (P3s), and other variants or hybrids of these methods—to improve the speed and efficiency of the project delivery process.
Each of these methods has its own set of risks and rewards. At the time of the PDM selection decision, project sponsors must, therefore, have a clear understanding of the relative costs, benefits, and risks of each method to deliver their projects wisely. Equally important is how the PDM is to be implemented, as procurement and postaward contract administration practices can further maximize the benefits of the chosen PDM, thereby creating an overarching project delivery system.
In the broadest sense, a project delivery system refers to the contractual relationships, procurement methods, commercial and financial terms, and management strategies used to take a project from concept through design, construction, and, in some cases, operations and maintenance. As summarized in Figure 1-1, to develop an overarching delivery strategy for a particular project requires determination of the optimal PDM, procurement approach, and contract type that best meets the project’s goals and constraints.
As used herein, a PDM refers to the comprehensive process used to execute and complete a capital project, including planning, programming, design, construction, and, potentially, operations and maintenance. Commonly used PDMs for delivering major airport capital projects are defined in Table 1-1. (Note that although these definitions are consistent with the prevailing literature, their exact application in practice may vary by owner.)
The airport interviews and surveys conducted in support of the development of this guide revealed the following general themes and observations regarding the PDMs used to deliver airport capital projects:
Note: IDIQ = indefinite delivery, indefinite quantity; QBS = qualifications-based selection.
Most of the airports interviewed expressed strong preferences for using the PDM(s) with which they had the most experience and success. These PDMs essentially serve as their default delivery method unless project circumstances dictate a different PDM be used. CMAR and traditional fixed-price DB were popular alternatives to DBB delivery, particularly for large hub airports with large or complex projects. Some airports were also strong advocates of progressive design–build (PDB). Small and medium hub airports predominantly use DBB delivery but have also begun experimenting with DB and CMAR, particularly for schedule-driven work that does not involve federal funding.
Table 1-1. Commonly used project delivery methods.
| Method | Description |
|---|---|
| Construction manager at risk (CMAR) | A PDM in which the sponsor engages the contractor at the early stages of design to provide preconstruction services. Such services typically entail providing input to the sponsor and design team regarding constructability, scheduling, pricing, and phasing. When the project scope is sufficiently defined, the sponsor and contractor negotiate a price for the construction of the project. Also commonly referred to as “construction manager/general contractor” (CM/GC) and “general contractor/construction manager” (GC/CM). |
| Design–bid–build (DBB) | The traditional PDM in which the sponsor completes its own designs or retains a designer to provide design services and then advertises and awards a separate construction contract based on a completed set of construction documents. |
| Design–build (DB) (fixed-price) | A PDM in which the sponsor procures both design and construction services in the same contract from a single legal entity, referred to as the “design–builder,” that commits to a fixed price for the entirety of the work at the time of selection. |
| Progressive design–build (PDB) | A variation of DB in which the design–builder is engaged early in the project development process (typically through a Phase 1 preconstruction services contract) and then collaborates with the owner to validate the basis of design and advance or “progress” toward a final design, associated contract price, and Phase 2 contract for construction services. |
| Public–private partnership (P3) |
A contractual agreement usually involving a public agency contracting with a private entity to finance; design; and construct, operate, maintain, and/or manage a facility or system. Common P3 structures include the following:
|
Procurement practices are the procedures owners use to evaluate and select designers and contractors. Evaluation and selection can be based solely on price (low bid), solely on technical qualifications (qualifications-based selection), or on a combination of price, technical qualifications, and other factors (best value):
Public-sector construction has historically entailed the almost exclusive use of the DBB delivery method, along with the selection of designers on a QBS basis and construction contractors on a low bid basis.
As owners have increasingly been turning to alternative PDMs, they have also adjusted their views on how to select construction teams. While low bid is still widely used, many owners are also using best value and a variety of other innovative procurement techniques, as discussed in Chapter 3, to improve project performance and the value of construction.
Designers and builders are typically compensated for their services on the basis of
Each of these contracting methods takes a different approach to the allocation of cost and performance risk. As with PDMs and procurement methods, there is no single contract payment strategy that is appropriate for all projects and situations.
The approach that best suits a particular project will depend on the owner’s project delivery goals, project characteristics, the PDM selected for the project, and market considerations. To help owners align payment terms to project goals and characteristics, Chapter 4 discusses the potential benefits and limitations of common payment mechanisms and performance incentive strategies used in airport construction.
As there is no one-size-fits-all project delivery system, tailoring a delivery strategy to a particular project requires a thorough understanding of the unique advantages and disadvantages of the different approaches available and the typical conditions under which they have been effectively applied.
To this end, this guide addresses the following issues:
This guide was developed to assist airports of all sizes with the selection and implementation of the most advantageous PDM, procurement approach, and contracting method for a given project. Whether an airport is using a particular delivery method for the first time or has significant experience with the method, the guide is intended to provide useful strategies and tools to support its implementation.
The target audience for this guide is airport personnel responsible for delivering capital projects, although owner’s representatives, architects, engineers, and contractors may also find the guide beneficial for understanding roles and responsibilities in the delivery process and the tools airports may use to administer projects.
This guide is based on the processes for selecting project delivery systems and the contract administration practices used by a diverse cross section of airports and other public transportation agencies. It was developed through (1) a review of current literature and contract documents and (2) interviews with airport and industry representatives.
Key tasks performed to support the development of this guide included the following:
This guide is structured to allow the user to quickly locate section(s) of particular interest. It is not necessarily written to be read in its entirety or in a particular order. Some information may be repeated in one or more sections so that each individual section may be understood on its own.
Five appendices are included: