When the appropriate project delivery strategy for a given project is being devised, it must be acknowledged that the conduct and behavior of the contracting parties can be heavily influenced by what they perceive to be their best interests. Project delivery goals and practices aimed at promoting collaboration and modifying traditional roles and responsibilities are thus most effective if complemented by a commercial structure that rewards, or at least aligns with, the desired behavior. After the optimum delivery method and procurement approach for a given project have been selected, the next step is to determine the appropriate payment terms to include in the associated contract.
In contrast to the project delivery systems and procurement methods discussed in Chapters 2 and 3, respectively, the range of available contracting methods is rather broad, and often any number of the methods discussed herein can be combined under a single contract to achieve desired goals.
To help owners align payment terms with project goals and objectives, this chapter discusses the potential benefits and limitations of common payment mechanisms and performance incentive strategies used in airport construction.
Designers and builders are typically compensated for their services on the basis of cost reimbursement (with or without a guaranteed maximum or not-to-exceed price), unit rates, or firm fixed or lump-sum pricing. Each of these contracting methods takes a different approach to the allocation of cost risk. As illustrated in Figure 4-1, these contract types can be placed along a continuum of increasing industry responsibility for construction cost performance. At one end of the continuum are cost-reimbursable contracts, under which the owner assumes most cost (and schedule) risk. At the other end of the spectrum are fixed-price or lump-sum contracts, under which the contractor bears such risk. Each of these contract types is discussed in this section, including its perceived advantages and disadvantages and the conditions under which its use can be most effective.
Cost-reimbursable contracting models generally require owners to provide payment for all the contractor’s allowable, allocable, and reasonably incurred costs on the project plus a fee. Final construction costs remain unknown until the project is completed.
To effectively implement a reimbursable payment model requires clear contractual provisions that define
Regarding establishing the contractor’s fee, there are two general approaches, of which the cost-plus-fixed-fee arrangement is the more common (and typically the only method allowed under most procurement rules):
To help align the owner’s and contractor’s commercial interests toward minimizing construction costs, the fixed-fee approach, in which the contractor’s profit or fee is set on the basis of the estimated cost of the work prior to contract performance, is preferable. Under a fixed-fee arrangement, the actual profit percentage that the contractor may earn will fall or erode as actual construction costs increase. The contractor is thus incentivized to deliver the project as diligently as possible to avoid erosion of its fee.
Under the cost-plus-fixed-fee approach, the actual profit percentage that the contractor may earn falls or erodes as actual construction costs increase. Such an approach helps align the owner’s and contractor’s commercial interests toward minimizing construction costs.
Reimbursable contracts present two primary disadvantages:
These disadvantages, however, can also work in the owner’s favor. For example, compensating the contractor for all its reasonably incurred actual costs should help
The transparency of open-book accounting
The higher level of administration associated with reimbursable contracts largely stems from the open-book nature of the project, which typically requires project cost and progress records to be maintained and shared at a far more granular level than would be expected under a lump sum or fixed-price arrangement. Owner preapproval of certain expenditures and costs (e.g., overtime, material requisitions and subcontracts over a certain dollar threshold, travel, miscellaneous costs) is also generally required.
In Procurement Routes for Partnering: A Practical Guide, author Jon Broome compares attributes of cost-reimbursable payment mechanisms with those of fixed-price methods (Broome 2002). As
Table 4-1. Advantages of reimbursable versus fixed-price payment mechanisms.
| Attribute | Payment Mechanism | |
|---|---|---|
| Cost Reimbursable | Fixed Price | |
| Cost visibility | Transparent | Little transparency to owner |
| Risk | Contingencies can be separated from basic cost of construction and made more visible to the owner | Hidden |
| Design | Design to cost | Cost the design |
| Monitoring/forecasting | More up to date | Wait for claim |
| Management approach | Proactive cost reduction | Reactive cost containment |
| Change order negotiation | High transparency, so relatively easy to agree to adjustment | Little transparency for owner, so negotiation of a fair and reasonable price can be challenging |
Source: Broome (2002, Chapter 7).
shown in Table 4-1, many of the advantages of cost-reimbursable methods stem from the transparency associated with open-book cost accounting. As Broome notes, a key advantage of such transparency and the more up-to-date monitoring and forecasting that it allows is that “as soon as a deviation is detected, the cause can be investigated, and steps instigated to bring forecast and actual costs back in line.” This proactive management approach is in stark contrast to the more reactive and confrontational “wait for claim” tactics associated with fixed-price contracts.
These observations are consistent with those included in the Construction Industry Institute’s Guide to Reimbursable Contracting (CII 2011), which recognizes that a reimbursable contracting strategy typically allows owners
Table 4-2 summarizes the advantages and disadvantages of cost-reimbursable contracts.
Table 4-2. Advantages and disadvantages of cost-reimbursable contracts.
| Advantages | Disadvantages |
|---|---|
|
|
Reimbursable contracts provide a good option for addressing projects that face a high degree of uncertainty, for which the owner would otherwise pay a high-risk premium to engage a contractor under a lump-sum or fixed-price arrangement. This would include situations in which
The considerations that would drive one to use a cost-reimbursable contracting model are similar to those that support a more collaborative project delivery approach, such as construction manager at risk and progressive design–build.
Reimbursable contracts are also appropriate when
Finally, projects in which time or quality objectives outweigh the relative cost tend to favor a reimbursable contracting approach. As the owner will be responsible for paying all the contractor’s reasonably incurred costs, the contractor will be more inclined to provide the necessary resources and workmanship to meet the owner’s performance objectives. If the contractor were instead working under a fixed price, it could be motivated to limit resources or compromise quality to protect its profit margin.
A guaranteed maximum price (GMP) contract is a type of reimbursable contracting method in which the contractor commits to constructing a project in full accordance with the approved plans and specifications for a price that will not exceed a certain guaranteed maximum (i.e., the contractor assumes responsibility for cost overruns).
The cost-plus contracts discussed in Section 4.1.1 can be combined with a GMP to provide an upper limit on the total construction costs and fees for which the owner is responsible.
The contractor’s GMP generally comprises the following elements:
Under a GMP contract, the contractor is entitled to receive the maximum price amount only if its actual project costs, including direct costs, indirect costs, and fees, equal or exceed the negotiated GMP amount (as amended by any subsequent change orders to cover scope adjustments or quantity changes that were not reasonably inferable at the time the GMP was established).
If the actual cost is less than the maximum amount, the contractor only receives its actual costs. An incentive for the contractor to keep costs below the GMP is sometimes provided by incorporating a shared savings clause that allocates the savings between the contractor and the owner.
In comparison to the cost-reimbursable contracts discussed in Section 4.1.1, the GMP method provides owners with more certainty regarding their maximum cost exposure. When coupled with a shared savings clause, the method can incentivize both the owner and the contractor to work together as efficiently as possible. However, as a trade-off for assuming the risk of potential cost overruns, the contractor may overstate the GMP or insist upon a large contingency to cover any uncertainties or incomplete design elements still present at the time the GMP is negotiated and set.
The timing of the GMP affects the level of risk retained by the owner: The earlier the GMP is set, the more risk is transferred to the contractor.
Holding a contractor to its GMP may also lead to a more adversarial project culture and disputes over the completeness of the design, what is included in the GMP, and what constitutes a change to the contract. Table 4-3 summarizes the advantages and disadvantages of using GMPs.
GMP arrangements, while commonly referenced in the literature in association with the use of construction manager at risk (CMAR) and progressive design–build (PDB) project delivery, do not appear to be as prevalent in airport construction. Most airports interviewed as part of the development of this guide indicated they were subject to legislative constraints or policy preferences that required competitive bidding of construction trade work. A GMP would, therefore, have to be set very late (typically at 100 percent design and following complete buyout of the construction work packages), which would minimize the ability to transfer much cost risk to industry and, hence, most of the benefits of GMP contracting.
Another option is for the GMP to be developed incrementally, for discrete portions of the work, on a package-by-package basis (which can be developed to the level of design detail needed to support a bidding process). Box 4-1 presents sample contract language from the Nashville International Airport addressing the progressive establishment of a GMP.
In a unit price contract, the contractor agrees to perform each item of work stipulated in the contract at a fixed price per unit of work, and payment to the contractor is made on the basis of actual quantities of work accomplished.
Table 4-3. Advantages and disadvantages of GMP contracts.
| Advantages | Disadvantages |
|---|---|
| In addition to the advantages cited for cost-reimbursable contracts in Table 4-2, the GMP provides an upper limit on the total construction costs and fees for which an owner will be held responsible. |
|
The RFP documents for Nashville International Airport’s Concourse D and Terminal Wings PDB project contemplated an incrementally established GMP, as discussed in the following draft contract language:
§ 4.4.3.4 Component Guaranteed Maximum Price (CGMP) for development of the Guaranteed Maximum Price (GMP)
§ 4.4.3.4.1 Owner will require a GMP for the Project no later than the 60% Design stage. However, Owner may authorize the Design-Builder to proceed with some early packages in order to meet the Project Schedule. If early packages are issued, the CGMP process will be followed. In the event a CGMP is initially established, it is intended that the CGMP will cover the initial Work of the Project. As design for the Project is further developed, it is planned that the additional work will be added to the contract and the GMP adjusted accordingly. The Contract shall be amended with each CGMP. At any given time during the Contract, the GMP will equal the sum of the approved CGMPs. When plans are no more than sixty percent (60%) complete the CGMP will be converted to a GMP, establishing the Guaranteed Maximum price for the project.
§ 4.4.3.4.2 Owner will issue a request to the Design-Builder to establish the GMP or CGMP Proposal for the complete Project or for the Work Package(s). Design-Builder shall deliver to Owner a proposed GMP or CGMP Proposal, with a detailed estimate prepared by the Design-Builder which shall be reviewed by Owner before being deemed to be adequately supported. Each GMP or CGMP proposal shall also include the following sections:
Section 1: Summary of Work, including a list of all construction documents.
Section 2: GMP or CGMP Price Summary with Line Item Schedule of Values.
Section 3: Scope Clarifications and Assumptions.
Section 4: Procurement Plan.
Section 5: GMP or CGMP Construction Schedule.
Section 6: Analysis of CGMP on the Total Construction Budget and Project Schedule.
Section 7: SMWBE Participation, including a total to date participation status report.
Section 8: Permitting Plan.
Section 9: Risk Plan.
Section 10: Construction Work Plan.
Section 11: Commissioning Plan and Activation Plan.
Section 12: Project Manuals.
§ 4.4.3.4.3 In addition to the Cost of the Work, a GMP or CGMP may include agreed to allowances needed to complete the scope of work that can’t be defined in a bid package and an agreed upon Design-Builder Contingency per the Contract Documents.
§ 4.4.3.4.4 The Design-Builder’s Fee as proposed by the Design-Builder. That fee includes home office and off-site overhead and profit.
§ 4.4.3.4.5 For the GMP or each CGMP, the Design-Builder shall develop a corresponding Schedule of Values.
§ 4.4.3.4.6 For the GMP or each CGMP will be subject to modification for changes as allowed by the Contract Documents.
§ 4.4.3.4.7 The Design-Builder shall submit its proposed GMP or CGMP to Owner. Owner will meet with the Design-Builder to review and analyze the GMP or CGMP proposal and, negotiate a GMP or CGMP.
§ 4.4.3.4.8 The following step in the development of the GMP or CGMP shall not occur unless and until the Project has been approved by Owner. If agreed upon, the GMP or CGMP will be submitted to the Board, and if approved by the Board, the GMP or CGMP shall be signed by Owner and issued to the Design-Builder, which shall constitute authorization for the Design-Builder to proceed with procurement and construction of the approved GMP or CGMP Work.
§ 4.4.3.4.9 If Owner rejects the GMP or CGMP proposal, the GMP or CGMP proposal shall be deemed withdrawn and of no effect. In such event, Owner and the Design-Builder shall meet and confer as to how the Project or Work Package(s) will proceed, with Owner having the following options:
The key advantage to unit price contracts is that the owner must only pay for actual quantities installed or supplied for the project. The owner thus retains the quantity risk, but, otherwise, prices are fixed, with the contractor bearing the risk of escalation of material or labor costs. Table 4-4 summarizes the advantages and disadvantages of unit pricing.
Although not widely used for airport capital construction projects, unit price contracts have some application for
It is more common to see unit prices as part of an overall lump-sum or cost-reimbursable contracting strategy applied to select elements of the work that are well-defined but for which the total required quantities cannot be accurately forecast at the time of contracting. Locking in
Table 4-4. Advantages and disadvantages of unit pricing.
| Advantages | Disadvantages |
|---|---|
|
|
a contractor’s unit prices in such circumstances can minimize the owner’s risk related to rising material or labor costs.
Fixed-price contracts are those in which the contractor provides a fixed price (or lump sum) for the whole of the work (or, alternatively, a series of lump sums for discrete portions of the work). The contractor bears the risk of cost overruns, rather than the owner.
The amount of the fixed price is typically quoted by the contractor, who will estimate its direct and indirect costs to perform the required scope and then add a fee commensurate with its perceived financial risk for entering a lump-sum contract for the work. (Alternatively, some owners may implement DB by stipulating a fixed price that the contractor must design and build to.)
When a contractor works under a lump-sum arrangement, it assumes the risk and responsibility for cost overruns. Although this risk transfer can be advantageous on certain projects, it can also lead to some downsides. For example, to cover its exposure, the contractor may include hidden contingencies in its lump-sum price to account for potential risks and uncertainties. The owner must pay this premium regardless of whether any risks materialize. Likewise, the owner must pay the total lump sum, even if quantities underrun the estimated amounts.
Working under a fixed price can also motivate the contractor to maximize profit by minimizing the cost of performing the work. Actions taken in pursuit of such financial motivations (e.g., compromising on quality or safety) may conflict with the objectives of other project participants or of the project as a whole. Such misalignment of commercial interests can act as a source of discord and disputes that discourage the collaboration needed to efficiently advance a project’s goals.
A commonly cited advantage of fixed-price contracts, particularly when viewed in contrast to reimbursable payment mechanisms, is that they provide the owner with early cost and schedule certainty. However, if the contractor begins to adopt a more commercially aggressive stance to protect its profit margin, the benefit of any perceived cost and schedule certainty may largely be negated by an uptick in change orders or claims.
Lastly, because costs are not open book, fixed-price contracts generally require less owner administration. The contractor will typically receive regular monthly progress payments based on validated estimates of the percentage of work performed or in place. Because prices are fixed at contract award, the contractor does not need to provide evidence of the actual costs incurred in performing this work. This lack of cost transparency can make pricing changes to the work
Table 4-5. Advantages and disadvantages of fixed-price contracts.
| Advantages | Disadvantages |
|---|---|
With regard to reimbursable payment mechanisms, fixed-price contracts
|
|
challenging. For this reason, fixed-price contracting is generally undesirable if the owner is either unsure of what it wants or is likely to change its preferences over the course of the project. Table 4-5 summarizes the advantages and disadvantages of fixed-price contracts.
Lump-sum contracts are generally well suited to design–bid–build (DBB) or DB projects that have a well-defined scope of services, a stable design, and mature specifications that contractors can use to develop estimates and pricing with a high degree of confidence. Any conditions or characteristics that could lead to uncertainty in cost estimates, such as market volatility, industry inexperience in meeting the project requirements, or potential delays (e.g., due to utility or other third-party coordination issues), could lead to unacceptable risk premiums that would suggest a reimbursable strategy could be more appropriate.
When there is some uncertainty or urgency to meet a particular project objective, incentive mechanisms can be used to more closely align the motivations of the contractor with those of the owner. Some approaches used by airports to commercially incentivize contractors to complete the work as quickly as possible or to meet other performance objectives are discussed in this section.
Incentives or bonuses for early completion provide payments to contractors for completing work on or ahead of schedule. Projects that would benefit from such an incentive strategy include
For early completion bonuses to be effective, an appropriate target completion date must be established and the owner must have the ability to estimate an appropriate bonus based on expedited production rates for similar work, historical records, or critical path method (CPM) scheduling. The bonus amount should result in a favorable cost–benefit ratio (i.e., the benefit to the owner exceeds the bonus amount, and this amount is high enough to motivate a contractor to accelerate).
In highway construction (in which the use of time incentives is more prevalent) some agencies have expressed concerns that the frequent payment of incentives is the result of agency time
estimates that are based on the performance of the average contractor. In such cases, a more time-efficient contractor may complete the work and earn an incentive without expending any extra effort.
It should also be noted that if reducing the duration of a project is a particularly important objective, the selection of project delivery methods (PDMs) that allow fast-tracking of design and construction (e.g., DB) would likely be more effective than simply applying a time incentive to a DBB project. The advantages and disadvantages of early completion bonuses are listed in Table 4-6.
Hartsfield–Jackson Atlanta International Airport (ATL) provides an example of using an early completion bonus. ATL implemented a completion incentive strategy on a project involving a 500-foot extension of its longest runway. The contractor received notice to proceed in June for substantial completion the following year on the Thursday before Memorial Day.
The project scope included the electrical and pavement section, blast pad, final dressing of approach, and markings. The work required shortening the runway 1,000 feet to provide a safe area to work. The runway shortening was implemented in March, so the duration for most of the construction was about 85 days.
The contract set forth the following incentive strategy:
The results were as follows:
Table 4-6. Advantages and disadvantages of early completion bonuses.
| Advantages | Disadvantages |
|---|---|
|
|
Construction area rental provisions assess contractors a rental fee for occupying an area (e.g., aprons or shoulders) to perform contract work. The fee is based on the estimated cost of delay or inconvenience to users during the rental period. The fees for each rented area can vary according to the time of day and the amount of traffic.
In contrast to an early completion bonus, the intent of a rental provision is not to reduce overall time for completion, but rather to reduce the time of user impact.
Rental provisions encourage contractors to devise innovative project execution and phasing plans to minimize user impacts during construction. They also allow the costs associated with closures, detours, and accidents to be considered in the contract price.
Rental fees are typically established per unit of time that reflects the cost of the impact to the airport and users. The owner estimates a reasonable duration to execute the work at no rental cost, after which an hourly or daily rate of rental is charged to keep the area closed. An allowance is included in the project to cover the rental duration. If the contractor opens the phase for airport operations in less time than the rental duration, the remainder of the allowance is its to keep. Table 4-7 summarizes the advantages and disadvantages of rental provisions.
Although rental provisions have been more commonly applied by highway agencies (as “lane rentals”), the experience of two airports—ATL and Phoenix Sky Harbor International Airport (PHX)—suggests that such provisions can also be of benefit to airports, particularly for areas where closures would represent a severe impact to airport operations and schedule is critical.
ATL applied the concept of rental provisions to the replacement of the pavement of a critical taxiway used to stage aircraft for runway access:
The contractor completed the work within the allotted rental time and liquidated damages were not assessed.
Table 4-7. Advantages and disadvantages of construction area rental provisions.
| Advantages | Disadvantages |
|---|---|
|
|
ATL was motivated to apply the rental concept after learning of its use on a project at PHX that entailed closing half of the apron throat, which severely restricted the size and number of aircraft.
As with PDMs and procurement methods, there is no one-size-fits-all approach when it comes to developing a contract payment strategy. The approach that best suits a particular project will depend on the owner’s project delivery goals, project characteristics, the PDM selected for the project, and market considerations.
Tables 4-8 and 4-9 assist owners with aligning project goals, project characteristics, and PDMs with an appropriate payment strategy. Table 4-8 summarizes the attributes of and challenges to implementation associated with the most common payment methods used in airport construction (i.e., cost reimbursable, GMP, unit price, and fixed price) and the PDMs with which they are commonly used. Table 4-9 presents typical factors that may drive the payment method selection decision, along with the perceived applicability of different methods in the context of these considerations.
When an approach is being considered, it is important to note that, in practice, many projects ultimately adopt a hybrid contracting method in which multiple payment methods and incentive strategies may be used in combination. For example, large projects may be broken into several phases, with reimbursable contracts being used to execute earlier work packages, while later phases, which can benefit from a more defined scope of work and mature design, may see increased use of fixed pricing or the conversion of the entire project scope to a lump sum.
Table 4-8. Comparison of payment methods.
| Cost Reimbursable | Guaranteed Maximum Price | Unit Price | Fixed Price |
|---|---|---|---|
| Key Attributes | |||
|
|
|
|
| Challenges/Risks | |||
|
|
|
|
| When to Use? | |||
|
|
|
|
Table 4-9. Considerations in selecting payment methods.
| Consideration | Payment Method | |||
|---|---|---|---|---|
| Reimbursable | GMP | Unit Price | Fixed Price | |
| Level of Project Uncertainty and Risk | ||||
|
Scope is evolving and/or lacks definition
Reimbursable contracts provide a good option for addressing projects with an incomplete or evolving design, for which the owner would otherwise pay a high-risk premium to engage a contractor under a fixed-price arrangement. If required performance is generally well understood and it is only quantities that remain uncertain, unit pricing could also provide a reasonable approach. |
||||
|
Changes are likely to occur
The more transparent, open-book nature of reimbursable contracts facilitates the negotiation of changes and thus can provide an attractive mitigation strategy for managing the risk of anticipated scope changes and owner delays. In contrast, fixed-price contracts, in which the owner may have little insight into the contractor’s original basis of estimate and actual cost of the work, are generally less accommodating of changes. |
||||
|
Market volatility
When prices are volatile, contractors will be unable to price the work with any accuracy, which leads to high-risk premiums if a fixed-price contract is used. In such situations, owners may be best positioned to assume the risk through the reimbursable approach. |
||||
| Timing of Contract Award and Level of Design | ||||
|
Award made early in the project cycle
Because a reimbursable contract does not require a complete design, it can be entered into much earlier than would otherwise be possible under a fixed-price contract. In contrast, fixed-price contracts require relatively well-developed scopes or specifications, or both, meaning that the procurement and award process are better left until later in the project cycle. The same holds true for GMP contracts, though to a lesser degree, due to the increased use of allowances and contingencies for uncertain items. |
||||
| Owner Involvement | ||||
|
Owner desires a collaborative, team approach to project decisions
If the owner desires a high level of involvement in project decisions regarding materials, work sequencing, productivity, and similar matters that would otherwise be the sole domain of the contractor, a reimbursable approach is generally preferable, given the increased transparency and project insight provided through open-book accounting. In addition, a reimbursable approach largely avoids disputes over cost recovery, thus allowing the project participants to work toward joint resolution of issues. |
||||
|
Owner desires minimal involvement or has limited staff oversight capabilities
If the owner would have difficulty committing the resources needed to actively oversee the project and would like to transfer more execution risk to the contractor, a fixed-price approach would be more appropriate. Effective oversight of a reimbursable contract (with or without a GMP) requires having staff with experience in administering such contracts, including verifying and authorizing payment requests and change order requests and monitoring productivity and progress to minimize overpayments. |
||||
| Project Goals | ||||
|
Time or quality objectives outweigh cost concerns
Projects in which time or quality objectives outweigh cost concerns tend to favor a reimbursable contracting approach. As the owner will be responsible for paying all reasonably incurred costs, the contractor will be more inclined to provide the necessary resources and workmanship to meet the owner’s performance objectives. A contractor working instead under a fixed-price arrangement could be motivated to economize on resources or quality to protect its profit margin. |
||||
| Consideration | Payment Method | |||
|---|---|---|---|---|
| Reimbursable | GMP | Unit Price | Fixed Price | |
|
Cost control is the key owner concern
Generally, fixed-price and GMP contracts provide greater price certainty and incentivize the contractor to work within the budget awarded (however, unreasonable risk transfer could lead to high contingencies and risk premiums). Fixed-price contracts can also be appropriate for regulatory environments or owner cultures that prefer knowing the construction price at the time of contractor selection. |
||||
