Los Angeles World Airports (LAWA) has constructed several major projects over the past decade as part of its Los Angeles International Airport (LAX) Capital Improvements Program (Program). The Program was designed to ensure LAX’s ability to continue to accommodate new generations of aircraft and improve the overall passenger experience at LAX. At the time the Program was initiated in 2007, it was the largest collection of public works projects in the history of the City of Los Angeles. Many of the projects were executed through some form of alternative project delivery.
The focus of this case study is the LAX Bradley West International Terminal (Bradley West) project, the first major project delivered by LAWA under the Program. The Bradley West project provides valuable insights for many reasons. Aside from being the first major project developed by LAWA since the 1984 Olympics, it was the first major project delivered by the City of Los Angeles under the construction manager at risk (CMAR) process. As a result, the Bradley West project provides important lessons for aviation agencies that are interested in using an alternative to their traditional capital project delivery approaches. The project also provides some excellent perspectives about what an aviation agency (large or small) might consider as it embarks on a new capital project, particularly if it has not undertaken a major capital project for a long period of time.
The information used as the basis of this case study was largely derived from the “Bradley West Development Program Lessons-Learned Report” (Lessons-Learned Report or Report) developed by LAWA following completion and closeout of the Bradley West Terminal project. LAWA commissioned the lessons-learned exercise to improve the performance of the other projects in the Program. The exercise had the participation of more than 30 individuals to evaluate project performance on: (a) procurement, contracts, and project controls; (b) project and design management; (c) construction management and inspections; and (d) stakeholder involvement, including facilities management, commercial development, and airport operations. The participants evaluated the areas that they thought “worked well” and those areas that needed improvement or “did not work well.”
The Bradley West project involved construction of two concourse facilities for the Tom Bradley International Terminal (TBIT). The project comprised approximately 1.3 million square feet of new construction at a capital cost of approximately $1.5 billion, with the following features:
For contracting purposes, LAWA broke the Bradley West project into two components:
Several factors influenced the development of the Bradley West project. As noted earlier, LAWA had not undertaken a capital program of similar size since the work performed in support of the 1984 Olympics. As a result, LAWA did not have the necessary management organization or systems in place to implement this substantial program. Moreover, because of delays caused by community opposition to the Program and the pressing need to accommodate new Airbus A380 planes, LAWA did not have time to use a traditional design–bid–build delivery process. Speed of delivery was the driving reason LAWA decided to use a CMAR delivery process. This approach enabled construction to proceed on a phased basis, with early packages being awarded while the design process continued for the balance of the project.
LAWA started soliciting program management services at the same time it began the solicitation for engineering and architectural services in November 2007. As noted in the Lessons-Learned Report, this is different from how public agencies traditionally establish their program management office, where program management policies and procedures are developed before the procurement of engineering and architectural services is begun. Award of the program management, architect, and engineering contracts occurred in March and April 2008. In February 2009, after the design had advanced somewhat, LAWA started the procurement for the CMAR contractor. LAWA awarded the CMAR contract for the gates component to the Walsh/Austin Joint Venture in April 2009. In October 2009, it awarded the CMAR contract for the core component to the Walsh/Austin Joint Venture. The contracts were cost-plus contracts with guaranteed maximum prices (GMPs). Construction on both components was underway by August 2010 and completed in July 2013.
The Lessons-Learned Report identified several areas that worked well in the development of the Bradley West project. The report concluded that these areas were a byproduct of LAWA’s need to establish a robust project management organization in a short period of time, which led to management systems and organizational processes that had to meet the demands not only of this project, but also of the other projects that were to be undertaken in the program. The areas noted in the report are as follows:
The “What Did Not Work Well” section of the Lessons-Learned Report offers many useful insights into the challenges of building a major capital project with a new delivery process, particularly after having little experience in doing so for many years. In fact, the report concluded that most of the challenges could be traced to (a) the aggressive schedule required to complete the project, (b) the lack of institutional experience in the implementation of a large capital program, and (c) this being the first CMAR delivery project implemented by the City of Los Angeles. A summary of the issues identified in the report is presented below.
Despite starting this time-sensitive project with virtually no management systems or organization in place, LAWA still accomplished the delivery of a successful project. The Bradley West Terminal won multiple awards and, as noted in the Lessons-Learned Report, compares favorably in terms of price and delivery schedule with some of the best international airport terminals constructed during the same period of time. Project executives interviewed on this project attribute this not only to the “what went right” elements in the Lessons-Learned Report, but also to the alignment of the political, executive management, and program management teams. This alignment recognized that LAWA was embarking on an ambitious project using a delivery method that had not been used by the City of Los Angeles. Problems were anticipated and addressed with a focus on solutions, and a “no blame attitude” in a collaborative effort to get to the finish line.
There are several other important takeaways from the LAWA Bradley West experience:
Finally, readers should note an important element of the LAWA experience that was not directly addressed in the Lessons-Learned Report. Limitations on authority can often be a major issue on a project, particularly when a new project delivery method is being used. This can have a major impact not only on project execution, but also marketability, as contractors may shy away from projects that have a cumbersome approval process, particularly for change orders. When the LAWA Bradley West contracts were issued to the CMAR contractor, the LAWA governance board granted broad change order authority to the executive director. Prior to the award of these contracts, the executive director’s change order authority was limited to $150,000. The LAWA governance authority (the Board of Airport Commissioners) extended that authority to $1 million, with the proviso that the executive director inform the board within 24-hours of approving any change order between $150,000 and $1 million. LAWA staff interviewed for this guide specifically noted that this change had a significant positive impact on LAWA’s ability to manage changes.
Abbreviations and acronyms used without definitions in TRB publications:
| A4A | Airlines for America |
| AAAE | American Association of Airport Executives |
| AASHO | American Association of State Highway Officials |
| AASHTO | American Association of State Highway and Transportation Officials |
| ACI–NA | Airports Council International–North America |
| ACRP | Airport Cooperative Research Program |
| ADA | Americans with Disabilities Act |
| APTA | American Public Transportation Association |
| ASCE | American Society of Civil Engineers |
| ASME | American Society of Mechanical Engineers |
| ASTM | American Society for Testing and Materials |
| ATA | American Trucking Associations |
| CTAA | Community Transportation Association of America |
| CTBSSP | Commercial Truck and Bus Safety Synthesis Program |
| DHS | Department of Homeland Security |
| DOE | Department of Energy |
| EPA | Environmental Protection Agency |
| FAA | Federal Aviation Administration |
| FAST | Fixing America’s Surface Transportation Act (2015) |
| FHWA | Federal Highway Administration |
| FMCSA | Federal Motor Carrier Safety Administration |
| FRA | Federal Railroad Administration |
| FTA | Federal Transit Administration |
| GHSA | Governors Highway Safety Association |
| HMCRP | Hazardous Materials Cooperative Research Program |
| IEEE | Institute of Electrical and Electronics Engineers |
| ISTEA | Intermodal Surface Transportation Efficiency Act of 1991 |
| ITE | Institute of Transportation Engineers |
| MAP-21 | Moving Ahead for Progress in the 21st Century Act (2012) |
| NASA | National Aeronautics and Space Administration |
| NASAO | National Association of State Aviation Officials |
| NCFRP | National Cooperative Freight Research Program |
| NCHRP | National Cooperative Highway Research Program |
| NHTSA | National Highway Traffic Safety Administration |
| NTSB | National Transportation Safety Board |
| PHMSA | Pipeline and Hazardous Materials Safety Administration |
| RITA | Research and Innovative Technology Administration |
| SAE | Society of Automotive Engineers |
| SAFETEA-LU | Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (2005) |
| TCRP | Transit Cooperative Research Program |
| TEA-21 | Transportation Equity Act for the 21st Century (1998) |
| TRB | Transportation Research Board |
| TSA | Transportation Security Administration |
| U.S. DOT | United States Department of Transportation |
