| TO: | NCHRP 08-154 Panel |
| FROM: | EBP, in association with High Street Consulting Group, Cincar Consulting (C2G), Michael Baker International, and Redd Engineering |
| DATE: | October 11, 2024 |
| RE: | Testing Peer Exchange Summary |
This appendix summarizes the key points from the NCHRP 08-154 Peer Exchange held on September 30, 2024. The peer exchange was the last element of Task 6, which aimed to test and support refinement of a guide designed to help state DOTs and MPOs integrate uncertainty into long-range transportation planning.
Task 6 proceeded in three steps: 6A) Development of a testing plan, 6B) Agency testing and validation, including workshops and 6C) a web-based peer exchange to share lessons learned from test sites, along with participation and interaction from a wider audience.
The main goals of the peer exchange were to:
Following this peer exchange, the research team is now pivoting to focus on guide refinements, including:
The peer exchange included participation by staff from each test agency, the project panel and program officer, and the research team.
Even when uncertainty has been a topic of discussion and analysis at an agency, it is still a daunting task to effectively and rigorously integrate into planning practice. The test agencies found the framework presented by the guide helpful and provided feedback to increase its utility for practitioners. The following themes emerged from agency presentations and discussion:
While this project’s guide does begin to address these challenges, it must also make a concrete and specific case to agencies about why they should engage with uncertainty, how it will help in what they are already doing, what they should be prepared for, and how doing so will positively impact the communities they serve.
This conversation with practitioners also highlights the need for more extensive implementation efforts to facilitate best practices in integrating uncertainty planning into complex systems. Not only was there significant discussion about how to communicate these ideas to decision makers and the public, but participants also asked questions of their peers about internal communication, data planning, and forecasting of external trends that they have otherwise not engaged with. Some agencies are ready and interested in working on this topic, but many struggle to focus in on useful and targeted activities given limited resources (whether that be staff, data, or time) to do so. Several attendees noted that there have been several attempts made over the years at better understanding uncertainty’s impact, only for them to fall by the wayside after a specific planning effort is completed. Therefore, further work is needed to connect exploration or analysis of uncertainty to how these activities can benefit agencies and support ongoing decision-making and agency management. That is, uncertainty cannot be considered as a “one-and-done” topic for a stand-alone plan, but rather should be considered within an ongoing iterative cycle of planning, learning, implementation, and feedback.
Five agencies - Atlanta Regional Commission (ARC), Iowa DOT, MassDOT, VTrans (Vermont), and Kentucky Transportation Cabinet (KYTC) - shared their experiences and insights from testing the
NCHRP Research Report 1168 guide. The slides presented by each agency and used by the research team in facilitation are included as an appendix to this memo.
ARC concentrated on the “Family of Plans” and “Communications Playbook” components of the NCHRP Research Report 1168 guide. The agency aimed to find ways to better coordinate and connect the diverse array of plans they manage and develop flexible outreach strategies related to uncertainty in transportation planning.
ARC shared several challenges they have faced in prior engagement with uncertainty and in the testing of the guide:
Through their engagement with the guide, ARC gained the following insights:
ARC outlined the following steps for integrating uncertainty into their long-range plans:
The guide provided ARC with a framework to design a more effective scenario planning and uncertainty planning work program, which they plan to use in the development of their next MTP update. ARC also plans to leverage this process as a mechanism to incorporate their emerging climate work with their traditional transportation planning process.
With their next long-range planning cycle approaching, Iowa DOT concentrated on the “Methods for Analyzing Uncertainty” and “Tracking Trends” guidance offered in NCHRP Research Report 1168. The agency’s goal was to explore how to integrate uncertainty considerations into the development of their next State Long-Range Transportation Plan (SLRTP) and Transportation Asset Management Plan (TAMP), both due for updates in 2027.
Iowa DOT highlighted these key challenges:
Iowa DOT found the following takeaways from guide testing particularly insightful:
Building upon their workshop experiences, Iowa DOT plans to:
MassDOT, building on prior work in integrating uncertainty into transportation planning, chose to focus on specific action items related to resiliency outlined in their “Beyond Mobility” long-range plan. In their testing workshop, they specifically homed in on:
MassDOT identified several key challenges in understanding and managing uncertainty:
Implementing “Beyond Mobility” Actions: MassDOT is likely to prioritize the implementation of action items related to resiliency outlined in their “Beyond Mobility” plan including building a future-ready workforce, providing training to enhance their capacity for dealing with uncertainty, and improving data management and sharing practices.
VTrans chose to test the “Self-Evaluation Score Sheet” and “Family of Plans” sections of the guide. These sections aligned with their goals to:
As a smaller agency, VTrans has limited staff resources, making it difficult to dedicate sufficient time and personnel to undertake comprehensive uncertainty planning.
VTrans had several key takeaways from their experience:
VTrans plans to:
Relatively new to incorporating uncertainty into their planning, KYTC focused on their existing Long-Range Statewide Transportation Plan (LRSTP), which was their first foray into scenario planning. They used the workshop as an opportunity to examine this plan through the lens of four key uncertainties:
KYTC engaged with the “tracking trends” and “after action analysis” components of the guide.
KYTC’s testing and analysis brought to light several key challenges:
KYTC highlighted the following takeaways from their experience:
KYTC plans to:
The concluding discussion session provided a platform for open dialogue and reflection. Participants shared feedback on the guide and emphasized the need for clearer policy direction, suggesting strategies for effective public engagement, and highlighting the importance of addressing the financial and logistical constraints faced by smaller agencies.
The “Family of Plans” concept, while well-received, prompted suggestions for improvement. Agencies recommended a more inclusive approach, incorporating a broader range of plans within the worksheet, and a structural overhaul to enhance its user-friendliness. The discussion also highlighted a preference for a concrete-to-abstract learning progression, advocating for the introduction of uncertainty concepts through relatable examples, such as a washed-out road, before venturing into more abstract topics like funding models or emerging technologies.
Participants suggested incorporating more storytelling and practical examples to effectively communicate the importance and relevance of uncertainty planning to a wider audience. The exchange also underscored the importance of sustainable engagement beyond the workshop and project, with suggestions for courses, follow-up initiatives, and even the development of an online platform to showcase “Family of Plans” examples as valuable resources.
Participants emphasized the importance of continued learning in understanding and managing uncertainty. Given the complexity of the topic and its relevance across many areas of planning and implementation, it is important to set expectations on gradually building capacity over time. As agencies work to develop and implement processes related to uncertainty, they would benefit from ongoing mentorship or more opportunities to talk to researchers and peers.