This appendix documents the responses of survey participants that were summarized in the main body of this report.
Responses from 43 participants include the following:
Responses from 34 participants include the following:
Responses from 40 participants include the following:
Responses from 31 participants include the following:
Responses from 23 participants include the following:
Responses from 21 participants include the following:
Responses from 39 participants include the following:
Responses from 42 participants include the following:
Responses from 45 participants include the following:
Responses from 12 participants include the following:
Responses from eight participants include the following:
Responses from 21 participants include the following:
Responses from 32 participants include the following:
Responses from 34 participants include the following:
Responses from 41 participants include the following:
Responses from 38 participants include the following:
Responses from nine participants include the following:
Responses from 14 participants include the following:
Responses from 32 participants include the following:
Responses from nine participants include the following:
Responses from nine participants include the following:
Responses from three participants include the following:
Responses from three participants include the following:
Responses from seven participants include the following:
Responses from seven participants include the following:
Responses from six participants include the following:
Responses from six participants include the following:
Responses from four participants include the following:
The response from one participant includes the following:
Responses from six participants include the following:
Responses from eight participants include the following:
Responses from nine participants include the following:
Responses from two participants include the following:
The response from one participant includes the following:
Responses from four participants include the following:
The response from one participant includes the following:
Responses from 39 participants are summarized in Table B-1.
Table B-1. Survey Responses to Question 45 by Stakeholder Type.
| Stakeholder Type | Response |
|---|---|
| Contractor | Be cautious when digging. |
| Contractor | If the owner of the utility cannot be identified, then purge the utility if applicable and commence construction, unless it presents such a formidable obstacle that it requires removal. |
| Project Owner |
|
| Project Owner | Ask by letter, meetings, and any other method. |
| Project Owner | Avoidance is best. Abandonment in place with an accurate as-built is preferred over removal. |
| Project Owner | Be cautious until you are 100 percent sure it is in fact abandoned. |
| Project Owner | Better coordination during the design between the DOT, consultant, and utility. |
| Project Owner | Better tracking/records of the OOS facility. Most instances where this occurred and negatively impacted a project, the OOS facility was inherited, and no records were available to document its existence. |
| Project Owner | Call in locates early so that knowledge of utilities can begin early, and potential OOS utilities can be identified to limit delay. |
| Project Owner | Communicate. Understand both sides. Agree on expectations. Communicate. Repeat. |
| Project Owner | Communication between facility owner and the DOT as to when facilities are abandoned. |
| Project Owner | Communication to confirm they are in fact out of service or keeping a schedule of cut over dates when new utilities are being installed to replace old ones. |
| Project Owner | Continued coordination is necessary. |
| Project Owner | Coordination with the utilities. |
| Project Owner | Do not allow them. |
| Project Owner | Early and often communication. Push utilities to be proactive with relocation efforts. |
| Project Owner | Early coordination. |
| Project Owner | Early identification. |
| Stakeholder Type | Response |
|---|---|
| Project Owner | Good recordkeeping for facilities when they change ownership. Communication with utility companies. |
| Project Owner | Have a well-groomed relationship with utilities. |
| Project Owner | Identify early, opt to remove in lieu of abandonment in place when practical. |
| Project Owner | If not being used, then they need to be removed for progress. |
| Project Owner | Keep the utilities responsible for them. |
| Project Owner | Maintain communication with local utility providers so that OOS utilities can be identified more easily. |
| Project Owner | Planning phase diligence can save lots of money if utilities are identified in this phase rather than in construction. |
| Project Owner | Research records, communicate with all potential owners, and document location in an as-built. |
| Project Owner | Start early. |
| Project Owner | They will always be there. Expect them. |
| Project Owner | Unsure. |
| Project Owner | We could definitely use help with identifying a best practice so we could update our processes and permitting. |
| Utility Owner | Designers need to engage utilities earlier in the process. |
| Utility Owner | Locate all underground infrastructure, including abandoned lines, during the planning phase of a project. |
| Utility Owner | There are a lot of abandoned pipelines out there. There needs to be a way for them to show up when someone submits a One Call ticket, so excavators are not surprised when they find them on accident. |
| Utility Owner | Treat all abandoned pipelines as if they contain hazardous liquid or gas products until proved otherwise. It is expensive and slows down the project to stop and tap an unknown pipeline rather than cutting right through it, but it is much safer and will save time and effort in the long run if it is a line that was not properly purged when it was abandoned. |
| Utility Owner | Treat them as if they have not been properly cleaned and abandoned and that they are live and under pressure. Call Miss Dig (811) for locations. It is utterly amazing that the state and federal government agencies do not use Miss Dig (811)! We narrowly diverted disaster by sheer luck when the state wildfire division began plowing without calling in an emergency Miss Dig while fighting a wildfire. They ignored pipeline markers with emergency numbers and were stopped within feet of a crude oil and produced gas line with 600 psi on it. The state DOT does not appear to use Miss Dig either with all of their project requests. |
| Other | Early and often communication is the key to success. |
| Other | Early identification and resolution planning. |
| Stakeholder Type | Response |
|---|---|
| Other | Explained above. Pennsylvania also has 33 regional utility coordination committees that meet regularly and use Coordinate PA to share their projects throughout the process. Pennsylvania’s One Call and the APWA Chapters help to spread the message and facilitate those committees. More information is available on the Pennsylvania One Call website, www.paonecall.org. |
| Other | How to manage the situation when it occurs and the best strategy (or strategies) to implement to minimize the overall impact of the construction project. |
Responses from 16 participants include the following: