
Over the past two to three decades, project delivery has evolved dramatically as public owners developed various alternative project delivery (APD) methods designed to help achieve certain project goals, such as accelerating delivery timelines, incentivizing private-sector innovation, minimizing delays and cost overruns, reducing claims and disputes, attracting and facilitating private financing, and enhancing lifecycle considerations.
These APD methods generally entail strategies by which public owners shift more responsibility, opportunity, and risk to the private sector. While some level of risk-shifting has no doubt been necessary to incentivize private-sector innovation, in many cases public owners have arguably attempted to transfer too much risk to their private-sector partners, often for items or events over which contractors have limited to no control and for which they cannot in practice include a large enough contingency in their pricing proposals to make the risk versus reward tradeoff attractive.
This perceived risk imbalance has caused major issues in the highway construction industry, particularly for large-scale and complex projects for which fixed-price APD methods are frequently used. Such market issues include higher bid/proposal prices, failed solicitations, reduced competition, and market exits. If these issues are not resolved, the potential for APD methods to generate value may go unrealized or may result in major disputes during project execution.
To address these concerns, a research team was engaged under NCHRP Project 23-22 to develop practical guidance to help state departments of transportation (DOTs)/public owners increase the likelihood of a successful solicitation that attracts a suitable number of competitive bids for large projects delivered using APD methods and that ultimately results in positive project performance outcomes. This Guide is an outgrowth of that research effort.
To develop this Guide, the research team conducted a literature review of relevant past research studies, guidance documents, and industry/trade publications related to risk allocation and mitigation strategies, as well as a content analysis of the contract and solicitation documents used on contemporary public-private partnership (P3) and large design-build (DB) projects to identify how risks are being allocated and treated by the contracting parties. The team further prepared and implemented a data collection plan consisting of a survey and structured interviews with owner and industry practitioners to:
To ensure a diverse set of perspectives was considered, survey and interview feedback were obtained from representatives of state DOTs, design firms, construction contractors, and concessionaires/developers.
Building from the insights drawn from the literature review, content analysis of solicitation and contract documents, and practitioner surveys and interviews, the research team developed the methodology presented herein. Various strategies and tools are described that owners may apply to identify, assess, and mitigate or manage risks in projects delivered using APD methods, including DB, construction manager/general contractor (CM/GC), progressive design-build (PDB), and P3. The identified tools represent effective practices that can be applied at different stages of the project lifecycle to manage risk, promote competition, and help achieve project delivery goals.
To facilitate the data collection effort and ensure a common understanding of terms, the research team adopted the following definitions to characterize the different APD methods owners are using to deliver their capital projects/programs (Table 1.1).
This Guide largely distinguishes these APD methods based on how and when the owner and its industry partner agree to the price of the work. For “fixed price” DB and P3 projects, the price is set at the time of contractor selection and contract award. In contrast, “progressive” methods

The PDMs and respective definitions are as follows:
Construction Manager slash General Contractor (CM slash GC): APDM in which the owner engages a contractor at the early stages of design to provide preconstruction services. Such services typically entail providing input to the owner and design team regarding constructability, scheduling, pricing, and phasing. When the project scope is sufficiently defined, the owner and contractor will negotiate a price for the construction of the project. [Also commonly referred to as “Construction Manager at Risk” (CMAR), and “General Contractor/Construction Manager” (GC/CM)]. DB (Fixed Price DB). APDM in which the owner procures both design and construction services in the same contract from a single legal entity referred to as the design-builder, who commits to a fixed price (and schedule) for the entirety of the work at the time of selection. (This method is also commonly referred to as “traditional” DB to contrast it with the newer “progressive” DB variant.)
Progressive DB: A variation of DB in which the design-builder is engaged early in the project development process (often through a Phase 1 Preconstruction Services Contract) and then collaborates with the owner to validate the basis of design and to advance or “progress” towards a final design and associated contract price.
P3: A contractual agreement that centralizes project delivery under a single contract with a developer or concessionaire (which may entail a consortium of multiple firms) to assume design, construction, operations, maintenance, and/or financing responsibilities of a public facility. Common P3 structures include design-build-finance-operate-maintain and design-build-finance.
(Although the P3 financial model has traditionally been fixed at the time of concessionaire selection and award, P3 agreements are increasingly being implemented using progressive processes by which the owner engages a developer in a collaborative “predevelopment” phase to assess project feasibility before entering into a comprehensive development agreement.)
(including CM/GC, progressive DB, and progressive P3) typically entail a preconstruction (or predevelopment) services phase through which the owner and its industry partner collaboratively advance the scope and design of the project and subsequently negotiate a contract price for the work.
Key findings from the research are summarized in the following list. Complete details are available in NCHRP Web-Only Document 434: Defining Contractual Risk Profiles to Increase Competition on Alternative Project Delivery Methods, which can be found on the National Academies Press website (nationalacademies.org/publications).
The first thing that we look at is who the authority is and whatʼs their level of experience and expertise. Who have they brought on board to help guide them through the process? Thatʼs very key because they are going to be our partner and for P3s they are going to be our partner for 30 or 50 years. We have to make sure there is alignment with values, goals and objectives.
Industry design professionals further reinforced this issue, stating that, if the general engineering consultant team representing the owner is unknown, inexperienced with APDs, or is incentivized (under cost-plus fee agreements) to excessively comment on submittals or over-inspect the work, this would be another consideration for declining to pursue a project.
We want to look at the project champion and community support, or whatʼs driving the project. Whoʼs against the project? But you really want a high-level and stable project champion, and with two-to-four-year election cycles, this can be challenging.
To address the findings noted earlier, this Guide presents practical strategies and tools to help DOTs/owners increase the likelihood of a solicitation that attracts a suitable number of competitive bids and that ultimately results in positive project performance outcomes. To achieve this objective, the Guide addresses the following:
Following the Introduction, the remaining chapters within this Guide are organized as follows:
The Guide also includes appendices presenting summaries of key tools relevant to fixed-price and progressive APD methods, as well as information and example contract provisions relevant to risk allocation strategies.